Opening nearly 500m of road planned for 26 years, 14 years

HƯNG THƠ |

Quang Tri - The road section is less than 500m long but takes 14 years of construction, increasing the capital to 44 billion VND, causing many concerns and questioning investment efficiency.

On December 15, the Dong Ha Ward Construction Investment Project Management Board confirmed that after 14 years of implementation, the extended Nguyen Trai route has been officially opened to traffic, and people can travel smoothly.

Recorded at the intersection between Nguyen Trai Street extension and National Highway 9, the biggest bottleneck of the project was previously cleared and the connection was completed. Vehicles pass smoothly, ending the long-standing road in disarray.

According to the records, the section of Nguyen Trai Street extended from National Highway 9 to Tran Binh Trong Street, planned since June 1999. However, it was not until early 2011 that the People's Committee of Quang Tri province approved the technical economic report, with a total investment of more than 7.6 billion VND from the central budget. The project was then only able to implement a few items and then fell into a state of stagnation since 2013 due to lack of capital allocation.

The "suspended" situation has lasted for many years, greatly affecting the lives of people in the area. Lao Dong Newspaper has previously reported many times the project's delay, unfinished land, dusty and risk of traffic insecurity, causing public outrage.

At the end of 2020, the project was restarted when the People's Committee of Dong Ha City (old) approved a new feasibility study report and adjusted the investment scale. The total investment at that time was increased to 24 billion VND, the total length of the route was 472.43m, the investor was the Dong Ha City Construction Investment Project Management Board.

Not stopping there, until April 2022, the project continued to be adjusted with the reason of recalculating the cost of site clearance to get closer to reality. This adjustment has pushed the total investment to 44 billion VND, an increase of nearly 6 times compared to the original figure. The construction process was still interrupted after that, and at times had to stop, such as in June 2023, making local people even more frustrated.

Although the route is basically completed by May 2025, there are still about 20m of the route that cannot be constructed due to procedures to connect with National Highway 9.

Anh: Hung Tho
Construction of traffic lights at the intersection of National Highway 9 and the extended Nguyen Trai Street. Photo: Hung Tho

According to Mr. Thai Vinh Hai, Director of the Dong Ha Ward Construction Investment Project Management Board, the reason for the delay in connecting is due to the change of the authority to manage National Highway 9, from the Central agency to the People's Committee of Quang Tri province, while the handover procedures have not been completed, leading to legal gaps in allowing connections.

The fact that a nearly 500m long road section takes 14 years to construct, with an increase of 44 billion VND to be put into use shows many problems in planning, capital allocation, project adjustment and coordination between management agencies. This is an valuable lesson in the effectiveness of public investment, which needs to be taken seriously to avoid repeating long-term projects, causing waste and undermining people's confidence.

HƯNG THƠ
RELATED NEWS

Dak Lak requests to transfer information about a project with hundreds of billions of VND to the police for handling

|

Dak Lak - Provincial leaders requested to transfer information about the Pan Lam - Ko Sier resettlement area construction project to the police for handling to clarify any violations.

Live Vietnam vs Thailand women's volleyball in the 33rd SEA Games final

|

Live match between the Vietnamese women's volleyball team and Thailand in the final of the 33rd SEA Games, taking place at 5:30 p.m. today (December 15).

Is the land compensated for more than 400 billion VND in Hanoi consistent with the current land price list

|

A household that owns more than 400m2 of land on Dinh Tien Hoang street was compensated more than 400 billion VND when reclaiming land to build a park - square in the East.

Hanoi urgently clears the construction of Ring Road 1, will build 2 direct overpasses

|

Hanoi - After receiving the clean site, the investor will deploy the construction of road items and 2 overpasses to directly open the Ring Road 1 project, Hoang Cau - Voi Phuc section.

The shape of the nearly 9 km section of Ho Chi Minh City Ring Road 3 through Binh Duong area

|

HCMC - The Ho Chi Minh City Ring Road 3 project, the section passing through Binh Duong province, was previously being accelerated, the nearly 9 km section of road is gradually taking shape.

Promoting the sharing of information and experience on trade union activities

|

Hanoi The Vietnam General Confederation of Labor and the Indonesian Trade Union Confederation have just held a meeting.

Gold price hits new peak, many people wait for their turn to buy gold rings

|

Gold prices continue to increase, people with demand are busy buying again. Number of sellers receiving coupons waiting in line to trade.

SEA Games 33 Medal Schedule on December 15

|

Updated total medal table of the 33rd SEA Games on December 15.

Dak Lak requests to transfer information about a project with hundreds of billions of VND to the police for handling

BẢO TRUNG |

Dak Lak - Provincial leaders requested to transfer information about the Pan Lam - Ko Sier resettlement area construction project to the police for handling to clarify any violations.

Gần 500m đường xây dựng 14 năm vẫn chưa thể thông tuyến

HƯNG THƠ |

Sau hơn 26 năm được quy hoạch và 14 năm triển khai xây dựng, đoạn đường Nguyễn Trãi nối dài (TP Đông Hà, tỉnh Quảng Trị) dài chưa đến 500m chưa thể hoàn thiện, khiến người dân bức xúc vì phải sống trong cảnh đi đường vòng gây bất tiện.

Thi công ì ạch, nhiều tuyến đường chưa có ngày về đích tại Quảng Trị

HƯNG THƠ |

Nhiều tuyến đường tại thành phố Đông Hà, tỉnh Quảng Trị sau khi khởi công thì thi công chậm chạp, làm ảnh hưởng đến việc đi lại của người dân. Có dự án đường giao thông còn bị cắt vốn, chưa rõ bao giờ mới có thể hoàn thành.