Good news about the project to open a 46-56m wide arterial road in Hanoi
HỮU CHÁNH |
Hanoi - It is expected that in 2024, Thanh Tri district will complete site clearance for the expansion of National Highway 1A after many years of delay.
In 2010, Thanh Tri district (Hanoi) began site clearance work, reclaiming more than 185,000m2 of land to construct the project to renovate and upgrade National Highway 1A, Van Dien - Ngoc Hoi section (Km185-Km189), with a total investment of nearly 890 billion VND.
The project is 3.8km long, passing through 4 communes: Tu Hiep, Ngu Hiep, Ngoc Hoi and Lien Ninh. The cross-section will be widened to 46-56m, meeting the needs of 8-10 lanes.
In 2012 and 2013, Thanh Tri District People's Committee handed over 92,674m2 of land area to Hanoi Traffic Construction Investment Project Management Board (investor). This area has been completed and put into use.
The remaining area is about 93,072 square meters of land, corresponding to 806 land and construction projects on land of 806 households, individuals and organizations.
According to the People's Committee of Thanh Tri district, the project implementation process lasted for many years (since 2016), due to difficulties in determining the origin of the land, incomplete updates in the management of cadastral records for all land along National Highway 1A in communes, and complicated land use origins of households and individuals.
Currently, 718 cases have received compensation, support and handed over the land. For the remaining 88 cases that have not agreed, the Thanh Tri District People's Committee has developed a plan to organize compulsory land recovery for the above cases according to regulations.
According to the leader of Thanh Tri District People's Committee, the site clearance work for the National Highway 1A expansion project was carried out by the locality in the spirit of benefiting the people but ensuring determination and effectiveness.
Administrative measures (coercive measures) are the last resort for households that do not comply with the handover of land.
Thanh Tri district aims to complete site clearance in 2024 to complete the project to expand National Highway 1A, Van Dien - Ngoc Hoi section, after many years of delay.
Images recording the National Highway 1A expansion project after 14 years of implementation
Hanoi - Hoang Mai District will build two 30-40m wide roads to help synchronize traffic infrastructure, contributing to the socio-economic development of the southern gateway of the city.
Hanoi - The Ring Road 2.5 underpass is expected to be completed in 2025, but the road connecting to this tunnel has been unfinished for many years, with no completion date set.
Hanoi - Hoang Mai District is preparing to build a road connecting Ring Road 2.5 to Ring Road 3, about 2km long, with an investment capital of 370 billion VND.
Today (November 19), the Hanoi People's Council held its 19th session to review and promulgate contents for implementing the 2024 Capital Law and other contents.
Nam Dinh - In nearly 30 years of working, Mr. Phan Van Trien (47 years old, Nam Truc district) has carved tens of thousands of water puppets to serve puppetry troupes from North to South.
Hanoi - Hoang Mai District will build two 30-40m wide roads to help synchronize traffic infrastructure, contributing to the socio-economic development of the southern gateway of the city.
Hanoi - The Ring Road 2.5 underpass is expected to be completed in 2025, but the road connecting to this tunnel has been unfinished for many years, with no completion date set.
Hanoi - Hoang Mai District is preparing to build a road connecting Ring Road 2.5 to Ring Road 3, about 2km long, with an investment capital of 370 billion VND.