These are the projects:
- Exploiting the underpass for the expansion of Ha Rang mine (Hon Gai Coal Company), capacity of 900,000 tons/year, total investment of about 1,413 billion VND;
- Exploitation of Coc Sau - Deo Nai Mining Cluster, capacity of 2.7 million tons/year, total investment of about 2,074 billion VND;
- Exploiting the underpass of Tan Yen - Dong Trang Bach mine, capacity of 0.45 million tons/year, total investment of about 1,111 billion VND;
- Nam Mau coal screening plant, capacity of 2.5 million tons/year, total investment of about 1,019 billion VND;
- The underground workers' apartment building of Nui Beo Coal Joint Stock Company, with a total investment of about 299 billion VND, with a scale of 398 rooms according to the 1-person/house model, will be deployed from 2025 to 2027.
These are key projects of TKV, which are of great significance in improving coal production, processing and supply capacity, meeting national energy demand, while contributing to modernizing the coal industry, improving working and living conditions for workers.
Notably, the Ha Rang mine expansion tunnel exploitation project is one of 34 main bridges among the bridges with works and projects selected by the Government to start construction and inaugurate at the same time, celebrating the 80th anniversary of the successful August Revolution and the National Day of the Socialist Republic of Vietnam (September 2, 1945 - September 2, 2025) on the morning of August 19.
The Ha Rang mine expansion tunnel exploitation project is a continuation of the old Ha Rang mine, which has now completed coal mining at +50÷-100m, located in Cao Xanh ward and Quang Hanh ward, Quang Ninh province.
Accordingly, Hon Gai Coal Company continues to invest in coal mining at a depth of - 50÷ -250m, with an industrial reserve of 8.93 million tons of clean coal; the volume of raw coal converted is about 11.85 million tons.
According to the design, the age of the mine is 17 years, including 4 years of basic construction, with a capacity of 900,000 tons/year. The volume of underground mine roads built deep underground by this mine project is more than 11.6km. The first market is expected to be put into operation around the first quarter of 2028.