The 600 billion VND flood drainage project in Gia Lai cracked after a few months of operation, the investor spoke up

Hoài Phương |

Gia Lai - The Dinh River flood drainage system appeared cracked after a few months of operation, the investor confirmed that the incident did not affect the quality of the project.

s
Inaugurated at the end of March 2025, the Dinh River Flood drainage System project (Quy Nhon Dong and Quy Nhon Bac wards, Gia Lai province) with a total investment of more than 600 billion VND is expected to help unblock the flow, increase flood drainage capacity, protect residential areas, urban areas and local technical infrastructure. Photo: Hoai Phuong
s
However, after only a few months of operation, cracks have appeared along both sides of the embankment and sidewalk of the project, stretching for hundreds of meters, causing concerns about the quality and safety of the project, especially as the rainy and stormy season is approaching. Photo: Hoai Phuong
s
According to Lao Dong's records in early August 2025, the cracks were concentrated in the adjacent location between the embankment and the sidewalk of the project. Photo: Hoai Phuong
s
Faced with this situation, the leaders of the Gia Lai Province Agricultural and Rural Development Project Management Board (abbreviated as Gia Lai Agricultural and Rural Development Project Management Board, investor) sent officers to inspect the site, and at the same time reinforced and repaired the damaged locations. Photo: Hoai Phuong
s
According to the leader of the Gia Lai Agriculture and Rural Development Project Management Board, the reason for the cracks appearing is the impact of the process of rolling and treating weak soil of the traffic project under construction on the side. Photo: Hoai Phuong
s
"The Board has sent human resources to dig up all cracked areas of cement, expected to be completed today. However, because the rolling of the project next to it is still ongoing, we will regularly check and promptly repair if more cracks arise," he said. Photo: Hoai Phuong
s
The leader of the Gia Lai Agriculture and Rural Development Project Management Board affirmed that the incident was a small problem, not affecting the overall quality of the Dinh River flood drainage system. The cost of repairing the damage is less than 10 million VND, including labor and materials. Photo: Hoai Phuong
Hoài Phương
RELATED NEWS

Garbage still overflows onto riverside roads in Gia Lai despite instructions for treatment

|

Gia Lai - More than ten days after the province's direction, household waste and Soap along the Dinh River have not been collected, and even more have been generated.

Gia Lai records 8 outbreaks of African swine fever, destroying nearly 500 infected pigs

|

Gia Lai - Since the end of June, the whole province has detected 8 outbreaks of African swine fever in 12 livestock households, forcing the destruction of nearly 500 infected pigs.

Thailand denies rumors of attacking Cambodia on the night of August 3

|

Thailand criticized Cambodia for spreading false rumors about the master plan for the attack on the night of August 3 after Hun Sen issued a warning.

Representative of Vietnam participates in monitoring the Thailand - Cambodia border

|

The representative of Vietnam is among the ASEAN observers deploying the second monitoring session at the Thailand - Cambodia border.

Inspecting a series of urban projects with signs of slow progress in Thai Nguyen

|

Thai Nguyen - A series of housing projects, residential areas, and urban areas with signs of being behind schedule and having legal problems are being inspected to clarify the causes and handle responsibilities.

The Ministry of Education solicits opinions on amending the program and textbooks for 4 subjects after merging provinces and cities

|

The Ministry of Education and Training is seeking comments on amending the 4- subject Program. This will be the basis for editing textbooks, after merging provinces and cities.

A V.League referee was hospitalized for emergency treatment while participating in a fitness test

|

The fitness test of referees before the new season recorded a case requiring emergency care due to unusual health signs.

Man falls from the 4th floor of Aeon Mall Long Bien shopping mall

|

Hanoi - A man fell from the 4th floor of Aeon Mall Long Bien shopping mall at noon on August 3, shocking many people present at the scene.

Garbage still overflows onto riverside roads in Gia Lai despite instructions for treatment

Hoài Phương |

Gia Lai - More than ten days after the province's direction, household waste and Soap along the Dinh River have not been collected, and even more have been generated.

Gia Lai records 8 outbreaks of African swine fever, destroying nearly 500 infected pigs

Hoài Phương |

Gia Lai - Since the end of June, the whole province has detected 8 outbreaks of African swine fever in 12 livestock households, forcing the destruction of nearly 500 infected pigs.

Điều tra vụ người phụ nữ tử vong bất thường tại nhà riêng ở Gia Lai

Hoài Phương |

Gia Lai - Cơ quan chức năng đang điều tra vụ một phụ nữ nằm tử vong bất thường tại nhà riêng, trên đầu có vết thương nghi do va chạm mạnh.