8 houses "blocking" a 1,500 billion VND project in Ho Chi Minh City is a huge waste

Lê Thanh Phong |

Ho Chi Minh City is implementing a 1,500 billion VND project to expand National Highway 50, but it has been stalled because 8 houses have not been cleared, causing the road to be interrupted.

The project through Binh Chanh district is nearly 7km long, connecting from Nguyen Van Linh intersection to Long An province border, including two main items: Building a new parallel route 4.2km long and expanding the existing road from 7m to 34m for 6 lanes.

The parallel route to National Highway 50 was started in 2022 and is now 75% complete, with many sections completed. However, the project is stuck due to site clearance.

The section through Gia Hoa residential area has 3 houses blocking the road under the management of Gia Hoa Company and has not been compensated. The section through Phong Phu 4 residential area has 5 other houses blocking the entire road in the area adjacent to Trinh Quang Nghi Street, managed by Khang Phuc Company, and has not been fully compensated.

The reason is the same as in many other projects, that is, the household owners demanded high compensation prices, so they could not reach an agreement. In one area, many households agreed with the compensation price, but 8 households did not agree, creating two bottlenecks on the route.

The road expansion project is to serve the travel needs of the people, but because 8 houses refused to agree to relocate, it was delayed, while the plan was to open to traffic at the end of December this year.

Representatives of the Management Board of Investment and Construction of Traffic Works in Ho Chi Minh City proposed a plan to open the completed sections to traffic first to serve the people, while waiting for the handover of the remaining locations.

It sounds hard to accept, a road, but only a few sections, but the congested areas are still congested. In addition to the problem of traffic congestion, it is also a problem of urban aesthetics. The existence of two congested areas on the road also shows the inability of local authorities to clear the land.

Of course, at most, we have to open the roads where cars can go, that is a temporary solution. But the local government must have a drastic solution, to completely handle the compensation and clearance of these 8 houses. Money spent on building roads but not being exploited is a waste.

Binh Chanh District People's Committee has proposed to Ho Chi Minh City People's Committee to request Gia Hoa and Khang Phuc enterprises to urgently compensate, support and hand over the site in November 2024. With 10 days left, will it be possible to do it or not?

If the two businesses and these households cannot reach an agreement, Binh Chanh district must handle the matter according to the law. The 8 houses cannot prevent the completion and operation of the 1,500 billion VND project.

Lê Thanh Phong
TIN LIÊN QUAN

The 1,500 billion VND project to expand the gateway to Ho Chi Minh City is "stuck" because of 8 houses

|

HCMC - The 1,500 billion VND National Highway 50 expansion project has been stalled because 8 houses have not been cleared, causing the parallel road to be interrupted even though it is 75% complete.

Replace and transfer staff if the project is delayed or wasteful

|

Ha Tinh - Chairman of Ha Tinh Provincial People's Committee Vo Trong Hai has just signed an urgent document directing the handling of slow-progressing projects, abandoned and wasteful headquarters.

Russia reveals retaliation for Western asset seizures

|

The West has frozen $300 billion in Russian assets since the Ukraine conflict escalated in February 2022.

Hanoi finalizes plan to handle illegal recruitment of 170 students

|

The Hanoi Department of Education and Training has a plan to transfer 174 10th grade students illegally recruited by To Hien Thanh High School to Van Lang High School.

By the end of 2023, there will be about 33,000 workers with occupational diseases

|

On the morning of November 21, the Vietnam General Confederation of Labor held a meeting of the Research Group to develop the Project "Building a cultural movement and labor safety among workers".

Proposal for priority housing sale for officers and soldiers

|

The draft Resolution on piloting the implementation of commercial housing projects mentions the case of giving priority to selling houses to officers and soldiers of the armed forces.

2024 National Volleyball Championship Phase 2 Men's Group Prediction

|

Today (November 21), the second phase of the men's event at the 2024 National Volleyball Championship begins.

Ho Chi Minh City announces Ben Thanh - Suoi Tien Metro ticket prices

|

On November 21, the Ho Chi Minh City People's Committee issued a decision on ticket prices for public passenger transport services by train on Metro Line 1 (Ben Thanh - Suoi Tien).

The 1,500 billion VND project to expand the gateway to Ho Chi Minh City is "stuck" because of 8 houses

MINH QUÂN |

HCMC - The 1,500 billion VND National Highway 50 expansion project has been stalled because 8 houses have not been cleared, causing the parallel road to be interrupted even though it is 75% complete.

Replace and transfer staff if the project is delayed or wasteful

TRẦN TUẤN |

Ha Tinh - Chairman of Ha Tinh Provincial People's Committee Vo Trong Hai has just signed an urgent document directing the handling of slow-progressing projects, abandoned and wasteful headquarters.

Lãng phí công trình cấp nước, không phải thanh lý là xong

VIÊN NGUYỄN |

Hai công trình nước sạch ở Quảng Ngãi tốn 15 tỉ đồng đầu tư nhưng không hiệu quả, nên được đề xuất thanh lý. Ai phải chịu trách nhiệm cho sự lãng phí này?