Tens of billions of VND in budget money have been invested but the factory is currently abandoned, with untreated waste, causing environmental pollution and affecting urban aesthetics.
According to the report of the Department of Agriculture and Environment of Cao Bang province, in the past 4 years, the locality has had 16 treatment facilities renovated or newly built.
However, many waste treatment facilities are not operating, abandoned, overgrown with weeds, machinery, equipment, and facilities are degraded, causing great waste.
At the landfill in Tra Linh commune, the leachate treatment system was invested with 15 billion VND, but many equipment have been stolen by thieves, causing loss of public property.
Hoa An commune waste treatment area, invested with 18 billion VND but has no waste treatment equipment. This is an abandoned area, becoming a landfill.
The Khuoi Kep - Na Lan waste treatment area (Tan Giang ward) has a total initial investment of 25 billion VND, after many adjustments, it has nearly doubled, up to nearly 50 billion VND, but after 10 years of implementation, it has become a scrap area.
Not to mention, the province invested in an additional incinerator worth 2.8 billion VND but has not yet officially operated, now it is a pile of scrap iron.
The waste treatment facilities are abandoned and burned billions of dong by the state, while the garbage is still overflooding. Damage overlaps with damage, waste continues waste.
Who are the people who have signed the approval of these projects, must clarify their responsibilities and take responsibility.
State money is spent on waste treatment, environmental protection, and people's health protection. That good purpose has been damaged by irresponsible people, dissolved into scrap yards, causing more pollution to the environment.
The primary responsibility is the Cao Bang Provincial Environment and Development Investment Company, the investor and contractor for the above projects.
According to the Department of Agriculture and Environment of Cao Bang province, the reason why the completed investment projects cannot be operated is due to the initial survey and design stages. Technical specifications and design options are not suitable for actual conditions, exceeding the investment limit.
Oh good! Perhaps the Environment and Development Investment Company cannot do whatever it wants, while local management agencies do not stop to check and consider before " nodding" to agree to implement the projects.
Clarify the responsibility, not only for the Development and Environment Investment Company but also for local management agencies, if there are signs of embezzlement and corruption, they will be investigated and handled according to the provisions of law.