Belt 4 Hanoi is sprawled with the front of the handover

HỮU CHÁNH |

Hanoi - Chairman of the City People's Committee assigns districts and districts to complete land acquisition for belt 4 before 15.4 but so far many segments have not been liberated.

The project of building Ring Road 4 of the Capital area through the territory of Hanoi city is longer than 57km, passing through districts: Soc Son, Me Linh, Dan Phuong, Hoai Duc, Ha Dong, Thanh Oai and Thuong Tin.

Regarding the clearance of the Hanoi Ring 4 Project, nearly 1 month ago, Chairman of Hanoi People's Committee Tran Sy Thanh asked the districts to resolve the remaining land area to be recovered and completed before April 15.

According to Mr. Tran Sy Thanh, this is the last time, not allowed later.

However, the recognition of labor on April 13 shows that the 4 -section belt project through Hanoi still has many positions that have not been cleared.

Khu dan cu thong Tan Chau (xa Chu Phan, Me Linh) chua duoc giai phong mat bang. Anh: Huu Chanh
A residential area of ​​Tan Chau village (Chu Phan commune, Me Linh) has not handed over the ground to the Belt 4 project. Photo: Huu Chanh Chanh
Trong anh la mot so ho dan song
Pictured are some households at the intersection of Ring Road 4 - Highway 23 (Dai Thinh commune, Me Linh) has not handed over the ground. Photo: Huu Chanh

At Package 8 - Building Song Hanh Ring 4 through Soc Son and Me Linh districts, underground and floating infrastructure works have been basically relocated.

However, up to now, there are still two residential areas in Dai Thinh and Chu Phan communes (Me Linh district) that has not handed over the ground to the project.

At Package No. 9 - Building Ring Road 4 through the territory of Dan Phuong and Hoai Duc districts, up to now, there are still premises in three residential areas in Duc Thuong, Dong La (Hoai Duc) and Ha Mo commune (Dan Phuong).

s
Belt 4 through Ha Mo commune (Dan Phuong) is entangled in some households. Photo: Huu Chanh
Nha xuong, khu dan cu
Factories and residential areas in Duc Thuong commune (intersection with Highway 32, Hoai Duc, Hanoi) have not been cleared. Photo: Huu Chanh

In the construction area of ​​Hong Ha Bridge, located in Hong Ha commune (Dan Phuong district) and Van Khe commune (Me Linh district), many households have not agreed to hand over the ground.

Khu cu dan xa Hong Ha (Dan Phuong) nam trong pham vi xay dung cau Hong Ha noi Dan Phuong voi Me Linh chua duoc giai phong mat bang. Anh: Huu Chanh
The residential area of ​​Hong Ha commune (Dan Phuong) is within the scope of construction of Hong Ha bridge connecting Dan Phuong with Me Linh that has not been cleared. Photo: Huu Chanh
Phia doi dien, nhieu ho dan xa Van Khe, Me Linh cung chua di doi, nhuong dat cho du an. Anh: Huu Chanh
On the opposite side, many households in Van Khe and Me Linh commune have not relocated and yielded to the project. Photo: Huu Chanh

Talking to the Lao Dong newspaper reporter, the commander of the Bidding Package No. 9 (Vinaconex contractor) Nguyen Hoang Hai said that the contractor regularly contacted Hoai Duc and Dan Phuong districts to update the site clearance progress.

"The relevant units are moving underground and embossed technical infrastructure. However, the three residential areas are still unclear when the locality will be handed over to the contractor to construct the project" - Mr. Hai said.

Similarly, some segments in the package No. 10 - Building a parallel road through Ha Dong and Thanh Oai districts also have many points that have not been handed over. The main obstacles are residential areas, workshops and underground technical infrastructure.

Mot doan Vanh dai 4 doan qua phuong Phu Luong (quan Ha Dong) chua the thi cong do vuong duong dien. Anh: Huu Chanh
A section of belt 4 through Phu Luong ward (Ha Dong district, package of bidding package No. 10) has not been constructed due to electricity problems. Photo: Huu Chanh
a
A branch of To Lich Bridge (Package 11) is waiting for the movement of electricity for construction. Photo: Huu Chanh

In Package 11, the section through Thuong Tin district, residential areas within the project scope have been cleared. There are more than 10 points that have not been handed over, mainly underground and floating infrastructure works.

Mr. Tran Viet Son - Commander of Package No. 11 (Cienco 4 contractor) - said that before, the city asked localities to assign enough premises to the contractor in the first quarter, then backward before April 15.

"The completion of the Road Road 4 in October as directed by the Chairman of the Hanoi People's Committee is almost impossible, because the handover progress of the locality is too slow. Not to mention, the rainy season is approaching and will last many months, greatly affecting the progress of the project" - Mr. Son said.

HỮU CHÁNH
TIN LIÊN QUAN

Ha Dong approves compensation plan of 778.05 billion VND for Ring Road 4 project

|

Hanoi - The People's Committee of Ha Dong District has appraised and approved a compensation plan with a budget of up to 778.05 billion VND when implementing the Ring Road 4 - Capital Region project.

Accelerating the construction of Hanoi Ring Road 4, many sections have been revealed

|

Hanoi - The packages of the Ring Road 4 parallel road project are being accelerated to complete in 2025.

Guarding for holidays, sticking to the construction site of Ring Road 4

|

Many workers and engineers postpone the Hung Vuong Commemoration Day holiday to stay at the construction site, speeding up the progress of the Ring Road 4 parallel road project in the Capital region.

Big fire at night in Ba Vi National Park

|

Hanoi - A large fire suddenly broke out in the Chang Re mountain area - Ba Vi National Park.

Binh Thuan celebrates 50 years of construction, innovation and development

|

Binh Thuan - On the evening of April 19, in Phan Thiet city, Binh Thuan province held a ceremony to celebrate the 50th anniversary of the Liberation of the province.

For the first time, Con Dao has a sea turtle conservation tour worth more than 20 million VND

|

Ba Ria - Vung Tau - Tourists will experience eating, staying and doing work related to sea turtle rescue with the forest rangers in Con Dao.

Nghe An has 3,530 surplus cadres after administrative unit arrangement

|

Nghe An - The whole province will have a surplus of about 3,530 cadres and civil servants after the arrangement of commune-level administrative units.

Reasons for choosing Bac Giang City as the administrative center of Bac Ninh province after the merger

|

Bac Ninh - The project to reorganize Bac Ninh and Bac Giang provinces clearly states the reasons for choosing Bac Giang city as the administrative center after the merger.

Ha Dong approves compensation plan of 778.05 billion VND for Ring Road 4 project

Anh Tuấn |

Hanoi - The People's Committee of Ha Dong District has appraised and approved a compensation plan with a budget of up to 778.05 billion VND when implementing the Ring Road 4 - Capital Region project.

Accelerating the construction of Hanoi Ring Road 4, many sections have been revealed

HỮU CHÁNH |

Hanoi - The packages of the Ring Road 4 parallel road project are being accelerated to complete in 2025.

Guarding for holidays, sticking to the construction site of Ring Road 4

Hữu Chánh |

Many workers and engineers postpone the Hung Vuong Commemoration Day holiday to stay at the construction site, speeding up the progress of the Ring Road 4 parallel road project in the Capital region.