High-speed railway will choose consultants to prepare feasibility study reports in the second quarter

PHẠM ĐÔNG |

The Standing Deputy Prime Minister requested to complete the procedures for selecting consultants to prepare a feasibility study report for the North-South high-speed railway project in the second quarter of 2026.

The Government Office has issued Notice No. 217/TB-VPCP dated April 28, 2026, concluding the meeting of Standing Deputy Prime Minister Pham Gia Tuc at the meeting on the implementation of the North-South high-speed railway project and other railway lines.

The Standing Deputy Prime Minister requested ministries, branches, and localities to ensure progress, quality, investment efficiency, within their authority, and not shirk or evade responsibility. Localities with projects passing through urgently carry out site clearance work immediately after the Ministry of Construction hands over dossiers and site clearance boundaries.

The Ministry of Science and Technology and the Ministry of Construction urgently complete standards and regulations on urban railways in June 2026 for uniform application nationwide, noting that it is necessary to consider connecting with the national railway system.

Regarding the North-South high-speed railway project, the Ministry of Construction urgently completes procedures to select consultants to prepare a feasibility study report for the project in the second quarter of 2026. Localities urgently plan to promote the economic efficiency of the high-speed railway line.

The selection of technology transfer partners must be associated with the prerequisite of technology transfer to Vietnam.

Đồ họa dự án đường sắt tốc độ cao Bắc - Nam. Đồ họa: Phạm Đông
Graphic of the North-South high-speed railway project. Graphic: Pham Dong

Regarding the Lao Cai - Hanoi - Hai Phong railway line, the Ministry of Construction urgently reviews and evaluates the research contents and proposals of consultants on the project feasibility study report, ensuring project efficiency, long-term vision, connecting economic centers and synchronizing transport modes.

Government leaders noted that they must not underestimate the processes, technical standards, quality, and efficiency of the project due to schedule pressure, and must ensure absolute safety in all cases for the entire project life cycle.

In case it is necessary to adjust the investment policy of the project, the Ministry of Construction should urgently complete the dossier to submit to the Government in May 2026, and submit to the National Assembly Standing Committee in June 2026.

The Ministry of Finance presides over and coordinates with the Ministry of Construction and the Ministry of Foreign Affairs to urgently implement procedures for negotiating a loan agreement for the project.

For the Hanoi - Dong Dang railway line, the Ministry of Construction and ministries, branches, and localities urgently implement the conclusions of the General Secretary in Notice No. 28-TB/VPTW on cooperation in connecting Vietnam - China railways and the Government leaders assigned in official letter No. 1359/VPCP-CN.

Regarding Hanoi and Ho Chi Minh City urban railway projects, the Standing Deputy Prime Minister requested the two localities to coordinate with the Ministry of Construction and relevant ministries and sectors to urgently review the progress of urban railway projects being implemented.

Focus on removing difficulties in investment procedures, site clearance, capital and technology; ensuring projects operate safely and effectively, adapt to climate change, in accordance with approved plans, with inter-regional connectivity and new situations.

For new projects, it is necessary to study carefully, select appropriate and synchronous technologies, and have a reasonable investment roadmap according to the local budget balance capacity, avoiding spreading out.

The two localities urgently report to the Ministry of Construction and the Prime Minister on the plan to implement projects planned to start construction in 2026 and the following years of the 2026-2030 period.

PHẠM ĐÔNG
RELATED NEWS

National Assembly supervises Long Thanh airport and high-speed railway projects in 2027

|

The National Assembly will supervise the North-South high-speed railway project and the Long Thanh International Airport project in 2027.

Need 743,907 billion VND to build 30 urban railway lines in Hanoi and Ho Chi Minh City

|

The Minister of Construction said that 30 urban railway lines in Hanoi and Ho Chi Minh City have a total length of about 2,224km, and the capital demand is about 743,907 billion VND.

Prime Minister Le Minh Hung attends the groundbreaking ceremony of the Hanoi - Quang Ninh express railway line

|

On April 12, Comrade Le Minh Hung - Member of the Politburo, Prime Minister attended the groundbreaking ceremony of the Hanoi - Quang Ninh high-speed railway line.

Collecting opinions from officials and people on the Special Urban Law for Ho Chi Minh City

|

Ho Chi Minh City is implementing the collection of opinions from officials, party members and people from all walks of life to complete the draft Law on Special Cities.

Collecting opinions on the Draft Political Report and Draft Charter of the 14th Trade Union

|

On the afternoon of April 28, the Vietnam General Confederation of Labor organized a Conference to Collect Opinions from Chairmen of Provincial and City Labor Federations, Central Industry Trade Unions, Economic Group Trade Unions, and Corporations directly under the General Confederation to contribute opinions on the Draft Political Report and Draft Trade Union Charter to be submitted to the 14th Vietnam Trade Union Congress.

Trade union officials must be closer to workers, understand workers better

|

On April 28, in Hanoi, the Presidium of the Vietnam General Confederation of Labour organized a ceremony to celebrate the 140th anniversary of International Labor Day (May 1, 1886 - May 1, 2026) and commend outstanding grassroots trade union presidents in collective dialogue and negotiation.

National Assembly supervises Long Thanh airport and high-speed railway projects in 2027

PHẠM ĐÔNG |

The National Assembly will supervise the North-South high-speed railway project and the Long Thanh International Airport project in 2027.

Need 743,907 billion VND to build 30 urban railway lines in Hanoi and Ho Chi Minh City

PHẠM ĐÔNG |

The Minister of Construction said that 30 urban railway lines in Hanoi and Ho Chi Minh City have a total length of about 2,224km, and the capital demand is about 743,907 billion VND.

Prime Minister Le Minh Hung attends the groundbreaking ceremony of the Hanoi - Quang Ninh express railway line

Xuyên Đông |

On April 12, Comrade Le Minh Hung - Member of the Politburo, Prime Minister attended the groundbreaking ceremony of the Hanoi - Quang Ninh high-speed railway line.