Some localities and ministries are confused in removing difficulties for backlogged projects

PHẠM ĐÔNG |

Some localities, ministries, branches and agencies are confused and have not fulfilled their responsibilities in removing difficulties for backlog projects under their management.

Deputy Prime Minister Nguyen Hoa Binh has just signed Official Dispatch No. 138/CD-TTg dated August 20, 2025 of the Prime Minister on focusing on effectively implementing solutions to promptly remove obstacles and difficulties for long-standing projects to immediately implement projects.

The dispatch stated that in the past, the Prime Minister has issued many documents directing and requesting ministries, branches and localities to focus on reviewing projects with difficulties, problems, and prolonged backlogs, urgently and thoroughly developing solutions to immediately implement projects, contributing to promoting socio-economic development, not wasting assets and money of the state, businesses, people and society.

On April 11, 2025, the Prime Minister issued Decision No. 751/QD-TTg on the establishment of a Steering Committee on resolving difficulties and problems of backlog projects (Steering Committee 751) to direct and resolve important, inter-sectoral issues to remove difficulties and problems related to backlog projects.

This includes projects using public investment capital, domestic private capital, foreign direct investment capital and other capital sources (if any).

However, during the implementation process, there are still some localities, ministries, branches and agencies confused; have not properly and fully implemented the contents according to the requirements and instructions of Steering Committee 751 and have not fulfilled their responsibility in removing difficulties for projects under their management.

To overcome this situation, the Prime Minister requested ministers, heads of ministerial-level agencies, agencies under the Government, Chairmen of People's Committees of provinces and cities to focus on quickly and effectively resolving projects with difficulties, problems, and long-standing backlogs to each cadre, civil servant, public employee, and party member. Do not shift responsibility from one agency to another, one level to another.

At the same time, continue to comprehensively review, update information, and a full list of projects with difficulties, problems, and long-term backlogs within the scope of management and be responsible for fully and accurately implementing the content and information in accordance with the requirements on the Database System of Steering Committee 751.

Establish a Working Group on reviewing and removing difficulties and obstacles for projects of ministries, branches and localities, with leaders of ministries, central agencies, and Chairmen of the Provincial/City People's Committees (Work Group) as the Head of the Working Group, reporting to the Standing Committee of Steering Committee 751.

Responsible for thoroughly handling problems that have sufficient legal basis according to authority; not allowing new violations to arise; not pushing or avoiding the responsibility to resolve problems of the project.

Strengthen the organization of inspection and supervision of implementation, do not let the handling of old violations lead to new violations; do not let violations, losses, and waste occur in project implementation within the scope of management.

Record, preserve, and hand over complete documents and data to avoid loss or loss of documents and records related to projects when merging provincial and commune-level administrative units.

Strictly handle cadres, civil servants, public employees, and party members who are irresponsible in handling work records related to projects with difficulties, problems, and long-standing backlogs.

PHẠM ĐÔNG
RELATED NEWS

Over 250 projects worth over 1.2 million billion VND are about to be inaugurated and started

|

It is expected that over 250 projects with a total capital of more than 1.2 million billion VND will be inaugurated and started to celebrate the 80th anniversary of National Day.

Ministries, branches and localities are responsible to the Prime Minister if they miss out, and projects are still pending

|

Ministries, branches and localities must take full responsibility to the Prime Minister if they miss out, and if there are backlogs and difficulties, they cannot be included in the report.

Assigning 9 localities and many solutions to difficulties for renewable energy projects

|

The Prime Minister directed ministries, branches and 9 localities to urgently remove difficulties for renewable energy projects.

Rare cold weather in Ho Chi Minh City, young people are excited

|

On the evening of January 9, the temperature in Ho Chi Minh City continued to drop deeply, making many people clearly feel the rare cold.

Reasons why fraud boss Chen Zhi was extradited by Cambodia to China

|

Chen Zhi, who is accused of operating online fraud activities from Cambodia, has been extradited to China.

Live football U23 Vietnam vs U23 Kyrgyzstan at the AFC U23 Championship

|

Live broadcast of the match between U23 Vietnam and U23 Kyrgyzstan at the 2026 AFC U23 Championship, taking place at 9:00 PM today (January 9).

Trade union activities need to be upgraded and more effective in 2026

|

Ho Chi Minh City - The streamlined trade union organization model requires management, administration and operational efficiency to be raised to a new level in 2026.

Merging two central hospitals into Hanoi Medical University

|

Central Hospital 71 and the Central Nursing and Rehabilitation Hospital will merge into Hanoi Medical University, according to the policy of the Ministry of Health.

Over 250 projects worth over 1.2 million billion VND are about to be inaugurated and started

PHẠM ĐÔNG |

It is expected that over 250 projects with a total capital of more than 1.2 million billion VND will be inaugurated and started to celebrate the 80th anniversary of National Day.

Ministries, branches and localities are responsible to the Prime Minister if they miss out, and projects are still pending

PHẠM ĐÔNG |

Ministries, branches and localities must take full responsibility to the Prime Minister if they miss out, and if there are backlogs and difficulties, they cannot be included in the report.

Assigning 9 localities and many solutions to difficulties for renewable energy projects

PHẠM ĐÔNG |

The Prime Minister directed ministries, branches and 9 localities to urgently remove difficulties for renewable energy projects.