Some localities and ministries are confused in removing difficulties for backlogged projects

PHẠM ĐÔNG |

Some localities, ministries, branches and agencies are confused and have not fulfilled their responsibilities in removing difficulties for backlog projects under their management.

Deputy Prime Minister Nguyen Hoa Binh has just signed Official Dispatch No. 138/CD-TTg dated August 20, 2025 of the Prime Minister on focusing on effectively implementing solutions to promptly remove obstacles and difficulties for long-standing projects to immediately implement projects.

The dispatch stated that in the past, the Prime Minister has issued many documents directing and requesting ministries, branches and localities to focus on reviewing projects with difficulties, problems, and prolonged backlogs, urgently and thoroughly developing solutions to immediately implement projects, contributing to promoting socio-economic development, not wasting assets and money of the state, businesses, people and society.

On April 11, 2025, the Prime Minister issued Decision No. 751/QD-TTg on the establishment of a Steering Committee on resolving difficulties and problems of backlog projects (Steering Committee 751) to direct and resolve important, inter-sectoral issues to remove difficulties and problems related to backlog projects.

This includes projects using public investment capital, domestic private capital, foreign direct investment capital and other capital sources (if any).

However, during the implementation process, there are still some localities, ministries, branches and agencies confused; have not properly and fully implemented the contents according to the requirements and instructions of Steering Committee 751 and have not fulfilled their responsibility in removing difficulties for projects under their management.

To overcome this situation, the Prime Minister requested ministers, heads of ministerial-level agencies, agencies under the Government, Chairmen of People's Committees of provinces and cities to focus on quickly and effectively resolving projects with difficulties, problems, and long-standing backlogs to each cadre, civil servant, public employee, and party member. Do not shift responsibility from one agency to another, one level to another.

At the same time, continue to comprehensively review, update information, and a full list of projects with difficulties, problems, and long-term backlogs within the scope of management and be responsible for fully and accurately implementing the content and information in accordance with the requirements on the Database System of Steering Committee 751.

Establish a Working Group on reviewing and removing difficulties and obstacles for projects of ministries, branches and localities, with leaders of ministries, central agencies, and Chairmen of the Provincial/City People's Committees (Work Group) as the Head of the Working Group, reporting to the Standing Committee of Steering Committee 751.

Responsible for thoroughly handling problems that have sufficient legal basis according to authority; not allowing new violations to arise; not pushing or avoiding the responsibility to resolve problems of the project.

Strengthen the organization of inspection and supervision of implementation, do not let the handling of old violations lead to new violations; do not let violations, losses, and waste occur in project implementation within the scope of management.

Record, preserve, and hand over complete documents and data to avoid loss or loss of documents and records related to projects when merging provincial and commune-level administrative units.

Strictly handle cadres, civil servants, public employees, and party members who are irresponsible in handling work records related to projects with difficulties, problems, and long-standing backlogs.

PHẠM ĐÔNG
RELATED NEWS

Over 250 projects worth over 1.2 million billion VND are about to be inaugurated and started

|

It is expected that over 250 projects with a total capital of more than 1.2 million billion VND will be inaugurated and started to celebrate the 80th anniversary of National Day.

Ministries, branches and localities are responsible to the Prime Minister if they miss out, and projects are still pending

|

Ministries, branches and localities must take full responsibility to the Prime Minister if they miss out, and if there are backlogs and difficulties, they cannot be included in the report.

Assigning 9 localities and many solutions to difficulties for renewable energy projects

|

The Prime Minister directed ministries, branches and 9 localities to urgently remove difficulties for renewable energy projects.

More than 13,500 Vinh Long workers join the Trade Union organization

|

In the first 6 months of 2026, Vinh Long province's trade union levels developed more than 13,500 new union members, reaching over 51% of the annual plan, affirming the attraction from practical benefits for workers.

Expanding international relations, raising the level of caring for maritime workers

|

In the context of deep integration, the Trade Union of Vietnam National Shipping Lines has proactively expanded cooperation with international trade union organizations to improve the quality of human resources, strengthen the cross-border support network and more effectively protect the rights and interests of maritime workers.

The bravery to overcome "storms" and the digital journey of aviation workers

|

In the exchange to welcome the 14th Vietnam Trade Union Congress, Mr. Dao Manh Kien - Chairman of the Trade Union of Vietnam Airlines Corporation (General Corporation Trade Union) shared many thoughts about the responsibility of the trade union organization in accompanying, protecting and helping workers (NLĐ) adapt to changes and the new technology era.

Accompanying the Railway industry to enter a new era of development

|

Chairman of the Vietnam Railway Trade Union Ha Trong Thang said that in the context of the railway industry facing the requirement of strong restructuring, transforming the management model and improving competitiveness, the trade union organization continues to affirm its role as a bridge between workers and businesses, and also an important companion force in the process of modernizing the railway industry.

An Giang Provincial Trade Union: Promoting internal strength to improve Trade Union activities

|

An Giang Trade Union continues to innovate the content and methods of operation, focusing on grassroots levels, promoting internal strengths and strengths after the merger.

Over 250 projects worth over 1.2 million billion VND are about to be inaugurated and started

PHẠM ĐÔNG |

It is expected that over 250 projects with a total capital of more than 1.2 million billion VND will be inaugurated and started to celebrate the 80th anniversary of National Day.

Ministries, branches and localities are responsible to the Prime Minister if they miss out, and projects are still pending

PHẠM ĐÔNG |

Ministries, branches and localities must take full responsibility to the Prime Minister if they miss out, and if there are backlogs and difficulties, they cannot be included in the report.

Assigning 9 localities and many solutions to difficulties for renewable energy projects

PHẠM ĐÔNG |

The Prime Minister directed ministries, branches and 9 localities to urgently remove difficulties for renewable energy projects.