Deputy Prime Minister inspects Bach Mai Hospital and Viet Duc Hospital projects in Ninh Binh

NGUYỄN TRƯỜNG |

Ninh Binh - On the afternoon of October 28, Deputy Prime Minister Le Thanh Long inspected the construction progress of facilities 2 of Bach Mai Hospital and Viet Duc Hospital.

Accompanying him were leaders of the Ministry of Health, leaders of a number of central ministries and branches, leaders of Bach Mai Hospital, Viet Duc Hospital and the construction contractor.

After inspecting the situation, Deputy Prime Minister Le Thanh Long and the working delegation had a working session to discuss and discuss solutions to remove difficulties and obstacles to complete the project on schedule.

At the meeting, Deputy Minister of Health Le Duc Luan reported on the construction progress of the items of the two hospitals, which will be basically completed before November 30, 2025.

Pho Thu tuong Le Thanh Long phat bieu ket luan tai buoi lam viec. Anh: Nguyen Truong
Deputy Prime Minister Le Thanh Long delivered a concluding speech at the meeting. Photo: Nguyen Truong

For facility 2 of Bach Mai Hospital, it is continuing to complete items such as: IPS cabinet system; Hot water system; Fire Prevention and Fighting System, Light Electrical System; Complete outdoor lighting system connection; Irrigation and water supply system for auxiliary houses; Installment of auxiliary houses' equipment...

The Viet Duc Hospital's Facility 2 project is continuing to construct the plaster ceiling, aluminum ceiling, paint the exterior of the house; complete the operating room, install doors; install electrical and water equipment; complete the basement; complete industrial hygiene; parking lot; construct the rainwater drainage system, wastewater, construct the lighting system...

Anh: Nguyen Truong
Bach Mai Hospital, Facility 2 in Ninh Binh has basically completed construction and is ready for operation. Photo: Nguyen Truong

Facility 2 of Bach Mai and Viet Duc Hospitals has implemented the direct procurement of part of the medical equipment and is expected to be completed before December 25. At the same time, widely bidding for other medical equipment is being implemented and it is expected to complete the installation and handover of all equipment for use before April 30, 2026.

At the meeting, representatives of the leaders of Viet Duc Hospital and Bach Mai Hospital reported on the contents of the work in the Project of operations of the two hospitals, including urgently arranging human resources, completing information technology infrastructure to connect and unify operations between Facility 1 and Facility 2; purchasing materials and medical equipment to serve Facility 2 when it comes into operation...

Anh: Nguyen Truong
The infrastructure of Bach Mai Hospital, Facility 2, is invested in and built spaciously and modernly. Photo: Nguyen Truong

At the same time, it is recommended that the Government, the Ministry of Health, ministries and central branches on a number of contents such as: completing the items of purchasing medical supplies and equipment; promptly approving a special financial mechanism for hospitals to recruit talents to serve at facility 2...

Concluding the meeting, Deputy Prime Minister Le Thanh Long acknowledged and highly appreciated the efforts of the Ministry of Health, the Project Management Board, Bach Mai Hospital and Viet Duc Hospital and contractors to implement the Project on schedule. At the same time, he emphasized that the Government is very determined and determined to direct the implementation of the two facilities 2 of Bach Mai Hospital and Viet Duc Hospital in 2025.

Viec Anh: Nguyen Truong
According to the Ministry of Health, the construction progress of the items of the two hospitals will basically be completed before November 30, 2025. Photo: Nguyen Truong

To put the second facility of the two hospitals into operation according to the set plan, Deputy Prime Minister Le Thanh Long suggested that the Ministry of Health coordinate with relevant ministries and branches to find specific solutions to remove obstacles in financial mechanisms and promptly pay the construction volumes to contractors. At the same time, pay attention to promoting the progress of project quality supervision.

The project management board needs to closely follow the plan, focus on human resources, time, intelligence, and be determined to work with contractors to carry out the work.

Contractors need to arrange engineers and workers to speed up the progress of bidding packages for equipment, information technology infrastructure, and fire prevention and fighting to meet the requirements when putting the second facility of Bach Mai and Viet Duc Hospitals into operation, ensuring the requirements of medical examination and treatment of the people.

NGUYỄN TRƯỜNG
RELATED NEWS

Morning news 14.10: Bach Mai Hospital, Facility 2, completed 98%, expected completion time

|

Morning news 14.10: Bach Mai Hospital, Facility 2, completed construction and installation of 98%; More than 300 people ran red lights recorded by AI cameras on a Hanoi street...

Bach Mai Hospital, Facility 2, completes construction and installation of 98%

|

Ninh Binh - The construction unit is making efforts, racing against time to complete the Bach Mai Hospital Project, Facility 2 in Ninh Binh.

Bach Mai Hospital, Facility 2, will receive patients on November 30, cannot be postponed

|

In about 50 days, Bach Mai Hospital, Viet Duc Facility 2 will be put into operation, this is the wish of many patients because people have been waiting for many years.

Bach Mai Hospital, Facility 2, will operate and receive patients on November 30

|

The Government does not avoid or dare to face difficulties and challenges, typically the removal of the Bach Mai Hospital project for operation on November 30.

A thousand-ton train convoy withdraws from Bach Ho bridge as floods in Hue gradually recede

|

HUE - At 9:20 a.m. on October 30, the railway industry allowed the locomotive to withdraw from Bach Ho bridge after many days of "guarding" the water flow as the floodwaters of the Huong River were gradually receding.

Russian plane carries 29 tons of emergency relief goods for people in flooded areas of Hue

|

On the morning of October 30, at Noi Bai airport (Hanoi), a Russian private plane landed, carrying 29 tons of emergency aid to the people of Hue city

Accelerate waste-to-energy projects to end the situation of waste being left behind

|

Ninh Binh - With a large amount of waste remaining, causing environmental pollution, Ninh Binh province is directing to speed up the progress of waste treatment projects to end the above situation.

Forecast of the risk of 2-3 typhoons near the East Sea in November

|

The low pressure is forecast to strengthen into a storm in early November, and there may be 2-3 storms near the East Sea throughout the month.

Morning news 14.10: Bach Mai Hospital, Facility 2, completed 98%, expected completion time

NHÓM PV |

Morning news 14.10: Bach Mai Hospital, Facility 2, completed construction and installation of 98%; More than 300 people ran red lights recorded by AI cameras on a Hanoi street...

Bach Mai Hospital, Facility 2, completes construction and installation of 98%

NGUYỄN TRƯỜNG |

Ninh Binh - The construction unit is making efforts, racing against time to complete the Bach Mai Hospital Project, Facility 2 in Ninh Binh.

Bach Mai Hospital, Facility 2, will receive patients on November 30, cannot be postponed

Lê Thanh Phong |

In about 50 days, Bach Mai Hospital, Viet Duc Facility 2 will be put into operation, this is the wish of many patients because people have been waiting for many years.

Bach Mai Hospital, Facility 2, will operate and receive patients on November 30

PHẠM ĐÔNG |

The Government does not avoid or dare to face difficulties and challenges, typically the removal of the Bach Mai Hospital project for operation on November 30.