Standing Deputy Prime Minister requests not to let material shortage slow down expressways

NHẬT HỒ |

The Standing Deputy Prime Minister requested localities to proactively coordinate materials, not to let the shortage of sand and stone slow down urgent projects, especially expressways.

At a working session on the progress of transport projects in the Southwest region on September 12 in Ca Mau, Politburo Member, Standing Deputy Prime Minister Pham Gia Tuc noted that the progress of some projects is still slow. The component project of the Chau Doc - Can Tho - Soc Trang expressway managed by Can Tho City has only reached about 58% of output. Projects implemented by the Ministry of National Defense in Ca Mau face difficulties due to weak soil conditions.

The Standing Deputy Prime Minister requested ministries, branches, localities, investors, and contractors to strictly implement Official Dispatch No. 53/CD-TTg dated August 12, 2026 of the Prime Minister, focusing on removing difficulties, accelerating construction, disbursement, and supply of materials. Construction quality must be put first, especially projects constructed on weak soil.

For the Chau Doc - Can Tho - Soc Trang expressway, relevant units are required to strictly control progress, increase manpower, machinery, equipment, organize 3-shift, 4-shift construction; proactively propose technical solutions to shorten loading time and complete the project soon.

Phó Thủ tướng Thường trực yêu cầu các chủ đầu tư, nhà thầu tiếp tục tổ chức thi công hiệu quả, đưa các tuyến đường cao tốc vào khai thác (ảnh chụp ngày 12.9). Ảnh: Nhật Hồ.
Politburo member, Standing Deputy Prime Minister Pham Gia Tuc requested investors and contractors to continue to organize effective construction and put expressways into operation. Photo: Nhat Ho.

Regarding material sources, the Standing Deputy Prime Minister requested Can Tho City and An Giang, Dong Thap, and Vinh Long provinces to review supply sources, increase capacity, open more mines, and transfer materials between localities.

An Giang is required to prioritize supporting the remaining stone source for urgent projects. Can Tho City urgently receives and stockpiles the exploited stone, not letting materials that are available but have not been put into use while other projects lack supply.

The Standing Deputy Prime Minister requested localities to proactively work directly, closely grasp the coordination of materials, not just send documents and wait for resolution. If domestic supply does not meet, study importing sand and stone from Cambodia. In case of cost incursions, competent authorities should study appropriate mechanisms.

Regarding expressway projects in Ca Mau, the Standing Deputy Prime Minister requested the Ministry of National Defense to continue to accelerate the Ca Mau - Cai Nuoc, Cai Nuoc - Dat Mui expressways, ensuring completion according to the plan. The plan to convert some sections to overpasses must be considered carefully, not to prolong construction time, avoiding investment waste.

The Standing Deputy Prime Minister emphasized that projects that have been decided and assigned tasks by the National Assembly and the Prime Minister must be implemented on schedule, ensuring quality; arising problems must be reported promptly for handling.

NHẬT HỒ
RELATED NEWS

Standing Deputy Prime Minister requests to remove obstacles for expressway materials in the Mekong Delta

|

Can Tho - Standing Deputy Prime Minister Pham Gia Tuc requested to focus on removing material obstacles and accelerating the progress of expressway projects in the Mekong Delta.

Ninh Binh invests more than 1,900 billion VND in road construction connecting expressways

|

Ninh Binh approves a 4-lane road project, with a total investment of more than 1,900 billion VND, connecting Ninh Co Economic Zone with major expressways.

Expressway worth more than 9,100 billion VND through Ninh Binh accelerates construction

|

Ninh Binh - Ninh Binh - Hai Phong expressway section passing through the old Ninh Binh province with a total investment of more than 9,100 billion VND is being accelerated for construction and capital disbursement.

Nearly 10km road connecting Cai Mep port with National Highway 51 and expressway reaches 95% progress

|

Ho Chi Minh City - Road 991B connecting Cai Mep port area with National Highway 51 and Bien Hoa - Vung Tau expressway has reached about 95% progress, expected to be operational by the end of 2026.

People discovered a strange wooden statue drifting into Cua Lo beach

|

Nghe An - A wooden statue about 60cm high, carved with the image of a man with large ears, was discovered drifting on Cua Lo beach.

Imports of frozen chicken massively, domestic chicken under competitive price pressure

|

Dr. Nguyen Thanh Son - Chairman of the Vietnam Poultry Association said that frozen chicken meat imported massively into Vietnam makes domestic chickens difficult to compete in price.

Health and current life of People's Artist Quoc Khanh

|

People's Artist Quoc Khanh is currently living in a spacious, fully equipped house in the suburbs of Hanoi. He is often visited by colleagues and friends.

Building a happy school for children to study well and be happy when going to school

|

A happy school is not only about creating a place where children feel happy, but also about helping them be listened to, respected, confidently creative and developing.

Standing Deputy Prime Minister requests to remove obstacles for expressway materials in the Mekong Delta

TẠ QUANG |

Can Tho - Standing Deputy Prime Minister Pham Gia Tuc requested to focus on removing material obstacles and accelerating the progress of expressway projects in the Mekong Delta.

Ninh Binh invests more than 1,900 billion VND in road construction connecting expressways

Lương Hà |

Ninh Binh approves a 4-lane road project, with a total investment of more than 1,900 billion VND, connecting Ninh Co Economic Zone with major expressways.

Expressway worth more than 9,100 billion VND through Ninh Binh accelerates construction

NGUYỄN TRƯỜNG |

Ninh Binh - Ninh Binh - Hai Phong expressway section passing through the old Ninh Binh province with a total investment of more than 9,100 billion VND is being accelerated for construction and capital disbursement.

Nearly 10km road connecting Cai Mep port with National Highway 51 and expressway reaches 95% progress

THÀNH AN |

Ho Chi Minh City - Road 991B connecting Cai Mep port area with National Highway 51 and Bien Hoa - Vung Tau expressway has reached about 95% progress, expected to be operational by the end of 2026.