The Prime Minister noted that the allocation of material mines to enterprises is not suitable

PHẠM ĐÔNG |

The Prime Minister noted that the assignment of material mines to businesses and the private sector for management and exploitation as at present is not suitable, causing negative consequences, affecting the project's progress.

The Government Office issued Notice No. 125/TB-VPCP dated March 19, 2025 on the conclusion of Politburo member and Prime Minister Pham Minh Chinh - Head of the Steering Committee at the 16th Session of the State Steering Committee for important national projects and works, key to the transport sector.

According to the announcement, in addition to the achieved results, investment preparation for some projects is still slow, the appraisal time is still long, the site clearance progress has not met the required progress (Binh Duong, Hung Yen, Lang Son...), construction implementation is still slow (Can Tho, Soc Trang, Bac Ninh, Lang Son, Cao Bang).

Procedures for granting construction material mines still have many problems and inadequacies, while resources are the common property of the country. The current assignment of material mines to enterprises and individuals for management and exploitation is not suitable, causing negative impacts in the exploitation and supply of materials, affecting the progress of project implementation.

Require localities with mines to seriously implement their commitment that resources are the common property of the country, so they cannot be kept for their own localities. Absolutely do not allow corruption, embezzlement, or negativity in granting licenses for material mining.

The Prime Minister assigned Ho Chi Minh City and Tay Ninh province to speed up the preparation and approval of the Ho Chi Minh City - Moc Bai Project Feasibility Study Report, to be completed in March 2025.

Binh Phuoc and Dak Nong provinces speed up the completion of procedures to start the Gia Nghia - Chon Thanh project on April 30, 2025.

Hoa Binh province urgently submitted for approval the investment policy for the Hoa Lac - Hoa Binh project, to be completed in March 2025.

Ninh Binh province urgently completes procedures to start the Ninh Binh - Hai Phong project through Ninh Binh in April 2025 as committed.

Thai Binh provinces and Hanoi City speed up the bidding process to select investors to start construction in April 2025 for the Ninh Binh - Hai Phong Expressway Project through Nam Dinh and Thai Binh and start construction in May 2025 for component project 3 of Ring Road 4 - Capital Region.

Hai Phong proactively implements the Ninh Binh - Hai Phong project through Hai Phong, promptly proposing if there are difficulties and problems.

Hanoi decides under its authority to adjust the total investment between component site clearance projects of the Ring Road 4 project to ensure that it does not exceed the preliminary total investment approved by the National Assembly; no corruption, negativity, waste.

Regarding railway projects, the Prime Minister requested localities with high-speed railway projects on the North-South axis, Lao Cai - Hanoi - Hai Phong railway projects to proactively coordinate with the Ministry of Construction to immediately implement site clearance procedures, approve resettlement projects to meet project progress.

Ho Chi Minh City urgently organizes research and implementation of urban railway projects (submarine ships) Ho Chi Minh City - Can Gio and Ho Chi Minh City to Long Thanh International Airport; calls on investors and contractors with capacity to participate in investment; report to the Prime Minister in April 2025.

For the Long Thanh International Airport Construction Investment Project and Connecting Infrastructure, the Prime Minister requested ACV to review procedures to soon start the second runway in March 2025.

PHẠM ĐÔNG
RELATED NEWS

deadline for completing the Chau Doc - Can Tho - Soc Trang expressway

|

The Prime Minister requested to restore the delayed progress, completing the Chau Doc - Can Tho - Soc Trang expressway in June 2026.

Progress milestones for the two expressway projects through Lang Son and Cao Bang

|

Before March 31, Lang Son and Cao Bang must clear and hand over clean land to implement the construction of 2 expressway projects in the area.

Resolving difficulties in material mines for Ninh Binh – Hai Phong expressway

|

Ninh Binh - The implementation of the Ninh Binh - Hai Phong expressway construction project, the section passing through Ninh Binh province, is facing some difficulties regarding material quarries.

China warns of July storm peak, risk of Ba Vi going deep inland

|

China forecasts more storms than the average in July, with the number of storms making landfall or affecting coastal areas higher than in previous years.

Gold price update morning of July 8th: Continues to decline

|

Gold price update morning of July 8th: Gold bars and gold rings sharply decreased by 1 million VND/tael. World gold is struggling, waiting for the Fed's decision.

Complete site clearance for the most complex area of the 345.5 billion VND project in Hanoi

|

Hanoi - Thanh Oai commune has completed site clearance for the National Highway 21B expansion project, with a total investment of about 345.5 billion VND.

Live football Argentina vs Egypt at World Cup 2026

|

Live football match Argentina vs Egypt in the 1/8 round of the 2026 World Cup at 11:00 PM on July 7 (Vietnam time).

People hope to abolish the 12-month limit on pension authorization

|

Hanoi - The proposal to remove the regulation that the power of attorney to receive pensions is only valid for a maximum of 12 months is receiving the consensus of many people.

deadline for completing the Chau Doc - Can Tho - Soc Trang expressway

PHẠM ĐÔNG |

The Prime Minister requested to restore the delayed progress, completing the Chau Doc - Can Tho - Soc Trang expressway in June 2026.

Progress milestones for the two expressway projects through Lang Son and Cao Bang

PHẠM ĐÔNG |

Before March 31, Lang Son and Cao Bang must clear and hand over clean land to implement the construction of 2 expressway projects in the area.

Resolving difficulties in material mines for Ninh Binh – Hai Phong expressway

NGUYỄN TRƯỜNG |

Ninh Binh - The implementation of the Ninh Binh - Hai Phong expressway construction project, the section passing through Ninh Binh province, is facing some difficulties regarding material quarries.