Northwest end of the day: Sa Pa airport still sends soldiers stationary
Nhóm PV |
Sa Pa airport is still deserted; Dense fog covers National Highway 6; The shape of a billion-dollar industrial park in Thai Nguyen...
Nhóm PV |
Sa Pa airport is still deserted; Dense fog covers National Highway 6; The shape of a billion-dollar industrial park in Thai Nguyen...
|
Dense fog covered National Highway 6, causing many sections of the road with a view to decrease to only 20m, causing drivers to move slowly.
|
Lao Cai - After 3 years of construction, the progress of Sa Pa airport construction is still only at the completion stage of the resettlement area.
|
A series of machines are focused on preparing for the groundbreaking of the Song Cong II industrial park project, taking place in the first quarter of 2025, with a construction period of 36 months.
|
Civil servants, public employees, and retired officers will be able to participate in international integration; the force will be regularly supported with 100% of their current salary.
|
The year-end sales season easily triggers the psychology of buying hastily, causing many people to excitedly close orders and worry about exceeding the spending budget.
|
Lam Dong - The strong northeast monsoon causes high waves. High-speed trains carrying passengers to Phu Quy Island must temporarily suspend operations.
|
After the " Say a day for you" fever, AI music continues to cause a storm on the internet, creating a series of million-view covers and opening a big debate in the professional world.
|
In the early morning of November 19 (Vietnam time), the Spanish team won a ticket to the 2026 World Cup after a draw against Türkiye.
Khánh Linh |
Dense fog covered National Highway 6, causing many sections of the road with a view to decrease to only 20m, causing drivers to move slowly.
Đinh Đại |
Lao Cai - After 3 years of construction, the progress of Sa Pa airport construction is still only at the completion stage of the resettlement area.
Nguyễn Hoàn |
A series of machines are focused on preparing for the groundbreaking of the Song Cong II industrial park project, taking place in the first quarter of 2025, with a construction period of 36 months.