Northwest end of the day: Sa Pa airport still sends soldiers stationary
Nhóm PV |
Sa Pa airport is still deserted; Dense fog covers National Highway 6; The shape of a billion-dollar industrial park in Thai Nguyen...
Nhóm PV |
Sa Pa airport is still deserted; Dense fog covers National Highway 6; The shape of a billion-dollar industrial park in Thai Nguyen...
|
Dense fog covered National Highway 6, causing many sections of the road with a view to decrease to only 20m, causing drivers to move slowly.
|
Lao Cai - After 3 years of construction, the progress of Sa Pa airport construction is still only at the completion stage of the resettlement area.
|
A series of machines are focused on preparing for the groundbreaking of the Song Cong II industrial park project, taking place in the first quarter of 2025, with a construction period of 36 months.
|
Hanoi - In the afternoon of April 24, the Executive Committee of the Vietnam General Confederation of Labour organized a Conference to discuss 14 contents, many of which are related to the 14th Vietnam Trade Union Congress.
|
Tuyen Quang - Many households located within the Son Duong - Tan Trao road project area that have not been relocated are facing dusty weather and muddy rain.
|
Nearly 23 million PC1 shares were dumped on the floor in a context of no buyers, reflecting great selling pressure from investors.
|
The amount transferred from the state budget in 2024 to 2025 is 1,439.178 billion VND, of which the cost of implementing salary reform is 58,061 billion VND.
|
Inside the roughly built house, which has not been granted a food safety certificate, an office kitchen is still busy preparing hundreds of meals to deliver to customers.
Khánh Linh |
Dense fog covered National Highway 6, causing many sections of the road with a view to decrease to only 20m, causing drivers to move slowly.
Đinh Đại |
Lao Cai - After 3 years of construction, the progress of Sa Pa airport construction is still only at the completion stage of the resettlement area.
Nguyễn Hoàn |
A series of machines are focused on preparing for the groundbreaking of the Song Cong II industrial park project, taking place in the first quarter of 2025, with a construction period of 36 months.