2 traffic routes connecting Long Thanh airport are basically completed

HÀ ANH CHIẾN |

Dong Nai - The total output of component project 3 of Long Thanh airport reached about 77.85%, of which 2 connecting traffic routes have been basically completed.

Some key bidding packages achieved output of over 90%

According to the Airports Corporation of Vietnam (ACV), component project 3 of Long Thanh airport to date, total output has reached about 77.85%. In which, package 4.6 construction of runways and aprons reached 90.82%; package 4.7 construction of aircraft aprons reached 89.97%; package 4.8 construction of inland port traffic and technical infrastructure reached 64.82%; package 4.9 aircraft fuel supply reached 87.72%; package 5.10 passenger terminal reached 67.08%; package 6.12 construction of 2 connecting traffic routes basically completed...

Gói thầu 6.12 thi công 2 tuyến giao thông kết nối sân bay Long Thành cơ bản hoàn thiện. Ảnh: Tổng Công ty Cảng hàng không Việt Nam ACV
Package 6. 12 construction of 2 traffic routes connecting Long Thanh airport is basically completed. Photo: Airports Corporation of Vietnam ACV

To ensure the progress of putting Long Thanh airport into operation by the end of 2026, ACV requires contractors to mobilize more personnel, aiming for the target of nearly 9,000 direct workers and an indirect team to accelerate internal work and complete dossiers.

ACV has also officially received airport operation registration from domestic airlines including: Vietnam Airlines, Vietjet Air and Vietravel Airlines.

Arranging space to serve airlines

Accordingly, ACV has worked with Vietravel Airlines on commercial operation plans at Long Thanh airport from the end of 2026 and increased operating frequency from the summer flight schedule in 2027; Vietjet Air commits to maintaining operation of at least 2 international routes; Vietnam Airlines proposes to transfer some international routes from Tan Son Nhat to Long Thanh, with a proportion of about 12% of the airline's international flights.

Bên trong nhà ga hành khách sân bay Long Thành. Ảnh: Tổng Công ty Cảng hàng không Việt Nam (ACV)
Inside the passenger terminal of Long Thanh airport. Photo: Airports Corporation of Vietnam (ACV)

ACV also exchanged views on the layout plan to serve Vietnam Airlines and VIAGS, including check-in counter areas, kiosks, luggage self-delivery areas, departure gates, luggage conveyor belts, Premium Check-in Lounge, CIP Lounge international and CIP domestic.

For foreign airlines, Long Thanh airport has also worked with representatives of 34 international airlines such as Korean Air, All Nippon Airways, Cathay Pacific and Japan Airlines to discuss and prepare operating plans according to the plan.

Preparations for the operation of Long Thanh airport are also being accelerated. To date, Long Thanh International Airport said it has received a total of 257 personnel to prepare for operation.

Representatives of Long Thanh International Airport said that personnel are being arranged to work in reality at Tan Son Nhat International Airport and at the Long Thanh International Airport Project to accumulate experience; and at the same time, learn from the new technical systems equipped in the near future when Long Thanh airport goes into operation, planned for the end of 2026.

ACV has signed a consulting contract with the Incheon Airport consortium to support the development of an operation and exploitation plan for Long Thanh airport. Up to now, the contents on operation, core processes, trade policies, business plans and financial strategies have been completed.

HÀ ANH CHIẾN
RELATED NEWS

Dong Nai leases more than 58ha of land to build a high-tech industrial park near Long Thanh airport

|

Dong Nai - The City People's Committee leases land to Amata Long Thanh Urban Joint Stock Company to build a high-tech industrial park in An Phuoc commune and Long Thanh ward.

Transfer to the Ministry of Public Security to consider investigating and handling a number of contractors for the Long Thanh airport project

|

The Government Inspectorate transferred information to the Ministry of Public Security to consider investigating and handling a number of contractors related to the Long Thanh airport project.

Mobilizing nearly 9,000 workers to build Long Thanh airport

|

The investor is drastically requesting contractors to mobilize nearly 9,000 direct workers to accelerate the progress of the Long Thanh airport project.

Long Thanh Airport: Some bidding packages exceed 90%, new bidding packages reach 36%

|

Dong Nai - Many main construction packages at Long Thanh airport have reached over 90%, including a package that has been basically completed.

Earthquake occurs in Bao Lac, after a loud explosion, the whole commune shakes

|

Cao Bang - People in Bao Lac commune just experienced a fairly strong earthquake and tremors on the evening of July 30.

The first resettlement houses in Muong Than welcome people after the flash flood

|

Lai Chau - Local authorities have just handed over 7 resettlement houses to households who lost their homes after floods.

Coach Kim Sang-sik observes meticulously, arranging the squad for the match against Singapore

|

Coach Kim Sang-sik has the strongest squad in hand to arrange personnel for the match against Singapore.

Dismissal of all Party positions with Chairman of the Writers' Association Nguyen Quang Thieu

|

The Central Inspection Committee decided to dismiss Mr. Nguyen Quang Thieu - Secretary of the Party Committee, Chairman of the Vietnam Writers' Association from all Party positions.

Dong Nai leases more than 58ha of land to build a high-tech industrial park near Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The City People's Committee leases land to Amata Long Thanh Urban Joint Stock Company to build a high-tech industrial park in An Phuoc commune and Long Thanh ward.

Transfer to the Ministry of Public Security to consider investigating and handling a number of contractors for the Long Thanh airport project

ĐÌNH TRƯỜNG |

The Government Inspectorate transferred information to the Ministry of Public Security to consider investigating and handling a number of contractors related to the Long Thanh airport project.

Mobilizing nearly 9,000 workers to build Long Thanh airport

HÀ ANH CHIẾN |

The investor is drastically requesting contractors to mobilize nearly 9,000 direct workers to accelerate the progress of the Long Thanh airport project.

Long Thanh Airport: Some bidding packages exceed 90%, new bidding packages reach 36%

HÀ ANH CHIẾN |

Dong Nai - Many main construction packages at Long Thanh airport have reached over 90%, including a package that has been basically completed.