On December 1, the People's Committee of Gia Lai province approved the decision to invest in the construction of the Quy Nhon - Pleiku expressway project, component 1, from Km0+000 - Km22+000.
The total investment for the construction of 22km of highway is about VND6,989 billion. Of which, the cost of compensation and resettlement support is more than 1,577 billion VND; the cost of construction is 4,482 billion VND; the cost of construction investment consulting is 165 billion VND; the contingency cost is 562 billion VND...
Component expressway project 1 starts at National Highway 19B and ends at the west of Phu Phong bypass, passing through the communes and wards: An Nhon Bac, An Nhon, Binh An, Binh Hiep, Binh Phu.
The entire route is designed to build 28 bridges with reinforced concrete and prestressed reinforced concrete, and bored pile foundations.
The province assigned the Civil Traffic Project Management Board to survey and collect information on terrain, geology, and hydrology to assess design solutions; at the same time, calculate hydrology to determine flooded areas and flood drainage opportunities along the entire route and neighboring areas.
The People's Committee of Gia Lai province assigned departments and functional branches to calculate and design bridges and roads that are load-bearing and economically - technically optimal.
Environmental impact assessment work must be carried out in accordance with regulations, ensuring publicity, transparency, and no loss or waste of capital.
The group of joint ventures includes: Thang Long Construction Consulting Joint Stock Company - Traffic Construction and Design Consulting Joint Stock Company 4 - IDECO Vietnam Joint Stock Company - Traffic Construction Consulting Joint Stock Company 5 participated in consulting on surveys, preparing technical research reports on construction investment.
Components 2 and 3 of the Quy Nhon - Pleiku expressway project to connect the entire route, connect forests and seas, increase the ability to transport goods are being accelerated, procedures and preparation steps for project approval are being accelerated.