The People's Committee of Bac Ninh province has just sent an official dispatch to the Department of Finance on reporting, reviewing and removing difficulties and obstacles related to the projects.
Accordingly, the Chairman of the People's Committee of Bac Ninh province requested the Department of Finance to preside over and coordinate with relevant agencies and units to urgently review, report, and update data on investment projects with difficulties, problems, and long-standing backlogs; remove difficulties and obstacles related to projects. Report to the Chairman of the Provincial People's Committee at the weekly meeting.
According to the reporter's investigation, in a report sent to the Prime Minister in December 2024, the People's Committee of Bac Ninh province said that in the province, there are 37 projects using public investment capital that have encountered difficulties and problems in the implementation process and are having to temporarily suspend construction to resolve difficulties and problems.
Of which, the project is invested by the provincial level, the district level is invested by 14 projects, the commune level is 17 projects.
According to the report, there are 4 main difficulties and problems that have led to projects using public investment capital that are in the process of implementation having to temporarily suspend construction.
Specifically, problems in site clearance for 22 projects. Reasons from the contractor (weak construction capacity; enforcement of judgments...) for 8 projects; Difficulties in project documents and legal documents (need to add fire prevention tanks; control documents; waiting for adjustment of investment policies and projects) for 5 projects.
Difficulties in project implementation capital (commune-level capital sources are having difficulty in requesting support for higher-level budget capital) for the two projects.
Bac Ninh Provincial Party Secretary Nguyen Anh Tuan also directed to strengthen urging, reviewing and thoroughly handling projects using public investment capital that are slow to/stop construction in the province.