Lessons learned in the construction of the Dong Dang - Tra Linh expressway

Duy Dũng |

Cao Bang - In the process of deploying the Dong Dang - Tra Linh expressway, the locality has drawn many important lessons learned.

On January 14, according to PV's investigation, Cao Bang Provincial People's Committee has just issued a summary report on the Emulation Movement "Completion of traffic connection for the Dong Dang - Tra Linh expressway construction investment project".

The report shows that the expressway was started on January 1, 2024. After a long period of construction, phase 1 officially opened technically on December 19, 2025, marking an important milestone in the formation of the strategic traffic axis in the Northeast region.

According to Cao Bang Provincial People's Committee, the expressway has a total length of more than 121km, of which the section passing through the province is about 69km. To date, phase 1 has completed the foundation and road surface of over 85km.

Two complex technical items, the tunnels through the mountains of Dong Khe and That Khe, are being focused on construction and completion by contractors.

Traffic safety, lighting and smart control systems are also being installed synchronously, ready for operation.

The project implementation process associated with the peak emulation movement has brought clear results. In Cao Bang, site clearance work has been accelerated, with a total cost of compensation, support, and resettlement of more than 243 billion VND, promptly paid to affected people", report No. 76 shows.

It is known that currently on many construction sites, more than 3,000 officials, engineers, workers and machinery are still working continuously.

Besides the achieved results, Cao Bang Provincial People's Committee also pointed out some limitations, such as the organization of emulation movements in some places is still formalistic and lacks depth; propaganda work is not diverse, and the level of spread is not uniform.

In the early stages of the project, there was a large workload, so the synthesis and reporting work was sometimes not timely.

From the actual implementation, Cao Bang province draws many lessons learned such as emphasizing the leadership and directing role throughout the Provincial Party Committee and Provincial People's Committee.

At the same time, it is necessary to link the emulation movement with timely commendation; pay attention to discovering and replicating models and advanced typical examples.

In parallel with that, inspection and supervision in the implementation process need to be given special attention.

Duy Dũng
RELATED NEWS

Cao Bang adjusts the number of villages, increases the criteria for specially difficult communes

|

Cao Bang - The Provincial People's Committee decided to adjust to increase 19 particularly difficult villages and increase criteria in 6 communes.

Dong Dang - Tra Linh Expressway is as beautiful as a painting before the "opening" date

|

In just 2 days, the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway will officially open the route, opening up opportunities for the Northeastern provinces.

85km of foundation and 20km of asphalt paving will be opened on the Dong Dang - Tra Linh Expressway

|

Cao Bang - At the Dong Dang - Tra Linh expressway construction site, workers are working overtime day and night to open the technical route in time.

14th Congress replaces 1.6 million pages of paper documents with tablets

|

The 14th Party Congress had about 1.6 million pages of paper documents replaced by documents on tablets, saving a lot of resources.

Ms. Ha Thi Nga holds the position of Vice Chairwoman - Secretary General of the Central Committee of the Vietnam Fatherland Front

|

Ms. Ha Thi Nga was consulted to hold the position of Vice Chairwoman - Secretary General of the Central Committee of the Vietnam Fatherland Front.

The era of Vietnam's rise from an international perspective

|

International media noted that Vietnam is entering an era of reaching out with a vision and structural reforms, creating the foundation for sustainable growth.

Waking up from 3 am to hunt for a brilliant sunrise at the flower wharf at the foot of Long Bien bridge, Hanoi

|

Hanoi - Phuc Xa Flower Wharf at the foot of Long Bien Bridge is a destination chosen by many people to take photos and welcome the capital's sunrise.

Cao Bang adjusts the number of villages, increases the criteria for specially difficult communes

Duy Dũng |

Cao Bang - The Provincial People's Committee decided to adjust to increase 19 particularly difficult villages and increase criteria in 6 communes.

Dong Dang - Tra Linh Expressway is as beautiful as a painting before the "opening" date

Khánh Linh |

In just 2 days, the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway will officially open the route, opening up opportunities for the Northeastern provinces.

85km of foundation and 20km of asphalt paving will be opened on the Dong Dang - Tra Linh Expressway

Duy Dũng |

Cao Bang - At the Dong Dang - Tra Linh expressway construction site, workers are working overtime day and night to open the technical route in time.