Khuong Dinh Secretary: Hope people sympathize with the shortcomings in site clearance of Ring Road 2.5

HỮU CHÁNH |

Hanoi - Mr. Vo Dang Dung hopes that people will sympathize, share and forgive the unpleasant things, not yet of officials performing the GPMB task of Ring Road 2.5 project.

Thank you People for agreeing to hand over land

On May 28, Khuong Dinh ward (Hanoi) organized a conference to summarize the site clearance work of the Ring Road 2.5 construction investment project in Khuong Dinh ward.

In nearly 20 minutes of speaking at the Conference, Secretary of the Party Committee, Chairman of the People's Council of Khuong Dinh Ward Vo Dang Dung mentioned the word "thank you" many times.

Mr. Dung respectfully thanked the organizations, households, and individuals whose land was recovered for the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, for their coordination, support, assistance, and creation of all conditions for the local government to implement the land clearance task.

The workload is very large, but with the determination of the entire political system, especially the companionship of the people, up to this point, Khuong Dinh ward has basically completed the site clearance of the Ring Road 2.5 project, Nguyen Trai - Dam Hong section and exceeded the set schedule," Mr. Dung announced the good news at the Conference.

x
Party Secretary, Chairman of Khuong Dinh Ward People's Council Vo Dang Dung. Photo: Huu Chanh

According to Secretary of the Party Committee of Khuong Dinh Ward Vo Dang Dung, the positive results in site clearance for the Ring Road 2.5 project come from many factors, the most important of which is creating consensus among the people.

Mr. Dung said that many households in the land clearance area have suffered many disadvantages. However, when people understood the urgency and long-term significance of the project, they shared and coordinated with the government in the implementation process.

This is the biggest lesson learned and also the biggest result of the project, which is to create consensus among the people," Mr. Dung emphasized.

In addition, the ward leaders determined that publicizing and making transparent the guidelines and policies related to compensation, support, and resettlement are key factors for people to feel secure and trust.

According to Mr. Vo Dang Dung, direct dialogue with the people also plays a particularly important role.

Meetings and answering petitions all have the direct participation of ward leaders, especially the Chairman of the Ward People's Committee, in order to promptly remove obstacles and help people understand the regulations of the State.

People cannot fully grasp the regulations related to site clearance. Therefore, ward leaders must directly dialogue, listen and thoroughly answer petitions," Mr. Dung said.

x
Secretary of the Party Committee of Khuong Dinh Ward Vo Dang Dung commended households and individuals with achievements in site clearance for the Ring Road 2.5 project. Photo: Huu Chanh

In addition to focused meetings, the Party Secretary, Chairman of the People's Council; Chairman of the Ward People's Committee and working groups also went to each residential area to grasp the thoughts and aspirations of the people to consider and remove arising difficulties.

For contents under its authority, the ward prioritizes immediate resolution with a spirit of urgency and flexibility while still ensuring compliance with legal regulations.

Issues beyond authority are summarized and promptly reported to the Steering Committee for Site Clearance for key projects of the city and the Hanoi People's Committee for consideration and handling.

We always try to be flexible in the process of resolving people's petitions, on the basis of ensuring compliance with regulations and maintaining stability in the locality," Mr. Dung said.

I hope people always consider Khuong Dinh a familiar place.

Although site clearance work has achieved many positive results, Secretary of the Party Committee of Khuong Dinh Ward Vo Dang Dung said that some people are still concerned and not really satisfied with the mechanism and policies of compensation and resettlement support.

This is also something that the Secretary and leaders of Khuong Dinh ward are extremely concerned about throughout the project site clearance process.

Faced with that reality, ward leaders often have to sit down together to find solutions.

I and the Chairman of the Ward People's Committee almost every day discuss the problems of the people, see what mechanisms and policies still need to be proposed to remove to ensure maximum benefits for them within the framework of legal regulations," Mr. Dung shared.

x
x
Leaders of Khuong Dinh ward commend households and individuals with achievements in site clearance for the Ring Road 2.5 project. Photo: Huu Chanh

Leaders of Khuong Dinh ward also frankly acknowledged that in the process of performing tasks, there were times when officials working on site clearance were not really flexible and adaptable in handling work.

In the process of performing tasks, if we have things that are not good or not right, we really hope people will sympathize, share and forgive us," Mr. Dung said.

According to the Secretary of the Party Committee of Khuong Dinh ward, the pressure of progress and the large workload sometimes make the implementation process tense. However, the local government always strives to stick to reality, flexibly handle each case with the goal of harmonizing the interests between the State and the people.

Before concluding his speech, the leaders of Khuong Dinh ward once again thanked the households who agreed to give land to the project.

I hope people, wherever they are, will always consider Khuong Dinh as a familiar place, and at the same time continue to maintain contact, share and accompany the local government in the coming time," Secretary of the Party Committee of Khuong Dinh Ward Vo Dang Dung concluded.

HỮU CHÁNH
RELATED NEWS

Handing over clean ground, forming the 2.5 Ring Road section through Thanh Xuan

|

Hanoi - Ring Road 2.5 section passing through Thanh Xuan ward gradually forms a road frame after the locality completes the handover of 100% clean ground.

Construction progress of Ring Road 2.5 section of Dich Vong - Duong Dinh Nghe New Urban Area

|

Hanoi - The Ring Road 2.5 project section passing through Dich Vong - Duong Dinh Nghe New Urban Area is targeted by the contractor to pave the road surface before September 2.

Intense heat, machinery still operating at full capacity at Ring Road 2.5 construction site

|

Hanoi - Intense heat but Ring Road 2.5 construction site still maintains continuous construction, with many machinery and equipment operating at full capacity.

Ministry of Industry and Trade responds to concerns about the compatibility of car engines when using E10 gasoline

|

According to Deputy Minister Nguyen Sinh Nhat Tan, most cars and motorbikes currently in circulation in Vietnam can use E10 gasoline as recommended by manufacturers.

Strong El Nino is coming soon, forecast of increased risk of intense heatstroke

|

When the El Nino phase begins to have a strong impact, hot weather in Vietnam will continue to last and increase pressure in both intensity and frequency in the coming months.

Thai Nguyen Chairman directs inspection of ash and slag storage yard on the Cau River bank

|

After the reflection of Lao Dong Newspaper, the Chairman of Thai Nguyen Provincial People's Committee directed functional sectors to inspect the ash and slag storage yard near the Cau River bank and strictly handle violations if any.

US launches new airstrike on Iran

|

US launches new airstrike on Iran on the morning of May 28, Vietnam time.

Summoning 780 official delegates to attend the 14th Vietnam Trade Union Congress

|

The Presidium of the Vietnam General Confederation of Labour has just issued a Decision on convening delegates to attend the 14th Vietnam Trade Union Congress, term 2026-2031 (Decision).

Handing over clean ground, forming the 2.5 Ring Road section through Thanh Xuan

HOÀI ANH |

Hanoi - Ring Road 2.5 section passing through Thanh Xuan ward gradually forms a road frame after the locality completes the handover of 100% clean ground.

Construction progress of Ring Road 2.5 section of Dich Vong - Duong Dinh Nghe New Urban Area

Hữu Vũ - Thiện Nhân |

Hanoi - The Ring Road 2.5 project section passing through Dich Vong - Duong Dinh Nghe New Urban Area is targeted by the contractor to pave the road surface before September 2.

Intense heat, machinery still operating at full capacity at Ring Road 2.5 construction site

Hữu Vũ - Thiện Nhân |

Hanoi - Intense heat but Ring Road 2.5 construction site still maintains continuous construction, with many machinery and equipment operating at full capacity.