Lam Dong Provincial Party Secretary requested to speed up progress, ensuring the quality of National Highway 28B project

PHÚC KHÁNH - PHAN TUẤN |

The Lam Dong Provincial Party Secretary requested the functional units to speed up the progress of the National Highway 28B renovation and upgrade project but must ensure the quality of the project.

Mr. Le Van Chung - Deputy Director of Project Management Board 5 said that up to now, the implementation value of the National Highway 28B renovation and upgrade project is about 620/1,083 billion VND, reaching 57%.

Of which, crushed stone aggregate is granted 45/68km (reaching 66%), asphalt concrete is granted 37/68km (reaching 54%). The site has been handed over to relevant units for 63km/68km (reaching 91.5%).

Regarding the implementation of the packages, it is worth noting that package XD1 (Km0 - Km42) has only been paved with asphalt concrete for 13/41km (32%). Thus, this package is behind schedule compared to the Ministry of Construction's request to shorten the progress.

The construction units said that the route is in the rainy season, causing difficulties in implementing roadbed construction, especially the excavation and filling of soil, affecting the project implementation progress.

In late October 2025, widespread heavy rain affected the construction and caused the slope of the positive slope to collapse (Km21+500, Km22+100, Km45+300, Km44+500, Km48+800). Therefore, the contractor must focus on moving to ensure traffic safety.

Mot goc Du an cai tao, nang cap Quoc lo 28B dang duoc trien khai. Anh: Phuc Khanh
A corner of the National Highway 28B renovation and upgrade project is being implemented. Photo: Phuc Khanh

At the meeting on November 1, Mr. Y Thanh Ha Nie K dam - Secretary of Lam Dong Provincial Party Committee requested investors and contractors to proactively overcome difficulties in the construction process. Lam Dong province will continue to accompany relevant units to implement the project with the highest efficiency

Currently, the remaining project volume is relatively large (about 43% of the contract value) while the remaining construction time is not much.

Lam Dong Provincial Party Secretary Thanh Ha Nie K dam suggested that Project Management Board 5 focus on implementing measures to speed up construction progress, especially for locations with clean land.

The Secretary of Lam Dong Provincial Party Committee also noted that along with speeding up the construction progress, it is necessary to ensure the quality of the project is in accordance with prescribed standards.

The project to renovate and upgrade National Highway 28B was approved by the Ministry of Construction in November 2023. The project is invested by Project Management Board 5.

The project has a total length of about 68km, part of the medium-term public investment plan for the period 2021-2025, expected to be handed over in 2026.

Recently, the Provincial Party Committee and the People's Committee of Lam Dong province have strongly directed the handover of clean land for the project and coordinated land sources within the scope of regulations for contractors to carry out construction in a series.

PHÚC KHÁNH - PHAN TUẤN
RELATED NEWS

National Highway 28B upgrade project worth over VND1,400 billion is 3 months behind schedule

|

Lam Dong - The National Highway 28B renovation and upgrade project has just had its completion schedule adjusted to 2026 instead of the original 2025 target.

Chairman of Lam Dong province warns investors and department leaders if National Highway 28B is still behind schedule

|

Lam Dong - The Chairman of the Provincial People's Committee warned that he would change the department's leaders and propose to change the investor and contractor if the National Highway 28B project continued to be behind schedule.

National Highway 28B upgrade project is sluggish due to slow handover of land

|

Lam Dong - The construction progress of the National Highway 28B upgrade project is still sluggish due to slow site handover and contractors not focusing on construction equipment and materials.

National Highway 28B project is in disarray, construction is sluggish, lacking labor

|

Lam Dong - On National Highway 28B, many construction sites are shabby, with only signs and markers but no workers or machinery.

aggressive crazy buffalo chases and attacks 7 people in Nghe An

|

Nghe An - In just 3 days, a wild buffalo appeared in Binh Chuan commune and chased and attacked 7 people.

20h News: More than 130 hectares of land recovered to widen the road connecting Long Thanh airport

|

20h News on November 1: Reclaim more than 130 hectares of land in 3 communes to widen road near Long Thanh airport; Search Truong Ngoc Anh villa, police seize iPad and 2 important documents;...

Teachers and soldiers busy cleaning schools in Da Nang after floods

|

Da Nang - Military forces, militia and teachers in Dai Loc commune urgently cleaned up and overcame the damage after a long period of deep flooding.

Hanoi shows another deep hole on Tran Hung Dao street

|

Hanoi - A deep hole appeared on Tran Hung Dao Street, causing many people to worry because this is an area with a lot of people and vehicles passing through.

National Highway 28B upgrade project worth over VND1,400 billion is 3 months behind schedule

Duy Tuấn |

Lam Dong - The National Highway 28B renovation and upgrade project has just had its completion schedule adjusted to 2026 instead of the original 2025 target.

Chairman of Lam Dong province warns investors and department leaders if National Highway 28B is still behind schedule

Duy Tuấn |

Lam Dong - The Chairman of the Provincial People's Committee warned that he would change the department's leaders and propose to change the investor and contractor if the National Highway 28B project continued to be behind schedule.

National Highway 28B upgrade project is sluggish due to slow handover of land

Duy Tuấn |

Lam Dong - The construction progress of the National Highway 28B upgrade project is still sluggish due to slow site handover and contractors not focusing on construction equipment and materials.

National Highway 28B project is in disarray, construction is sluggish, lacking labor

Duy Tuấn |

Lam Dong - On National Highway 28B, many construction sites are shabby, with only signs and markers but no workers or machinery.