Close-up of the 500kV Lao Cai - Vinh Yen route

Nhóm PV |

In the last days at the construction site of the 500kV Lao Cai - Vinh Yen route, workers took advantage of favorable weather to pull the lines and clear the entire route.

During the hot weather of the last days of August, the working atmosphere at the Lao Cai - Vinh Yen 500kV transmission line construction site became even more exciting.

The steel pillars rising high in the mountains and forests, the sound of welding machines, the sound of drilling and cutting symbolises the will and great determination of thousands of engineers and workers who are stuck day and night.

Hang loat cot thep tren tuyen 500kV Lao Cai - Vinh Yen da duoc dung xong, tao tien de cho giai doan keo day va nghiem thu.
A series of steel poles on the 500kV Lao Cai - Vinh Yen route have been completed. Photo: Van Duc

The most difficult and complicated construction locations of package 1 such as VT04 pillar are being assembled by workers and engineers to complete the final steel bars to complete the pillar body and prepare specialized equipment and means to be ready for cable stretching and pulling.

The service road from the foot of the hill to the construction site is deeply repeated with the chain reaction of excavators and cranes. Previously, workers had to use 2 excavators to "pull" the 120-ton crane down the slope to the construction site.

Nguoi dan ho tro cong nhan dinh vi day moi
Workers position the hook ropes.

According to Lao Dong, at the locations of poles from 100 to 113 through Khanh Hoa commune, Lao Cai province, many workers are preparing machinery and equipment to pull the rope.

Each team has a task, people climb to the top of the pillar to install porcelain firmly on the barges. A team installs a rope support scaffolding that does not affect traffic safety. The remaining workers were divided into two groups of up to two pillars to bring the hay ropes to the top of the pillars.

After nearly 1 hour of preparation, theprey rope was at the top of the pole, the 5-ton excavator, connected to a 12-horsepower diesel, began to lift the rope.

Pulling up the rope requires good coordination, because each person is in a position several dozen meters apart, so everyone uses a walkie-talkie to discuss.

De rai day, treo day len dinh cot doi hoi nguoi co kinh nghiem va su dung may toi.
To stretch ropes and hang ropes to the top of a pole, it requires experienced people and the use of a winch. Photo: Van Duc

Mr. Vu Quang Chien (Lam Dong power transmission team, Power Transmission Company 3), who has 10 years of experience in pulling wires, moves the hand to connect power wires and match wires. After connecting, he signaled to the driver of the winch to pull the wire. Immediately, the winch was accelerated to lift the rope to the necessary position.

Each coil of electric wire is more than 2km long, weighing nearly 5 tons, if the wire is not spread well, leaving it crossed together will cost the whole day to remove. To stretch ropes and hang ropes to the top of a pole, it requires experienced people and the use of a winch.

Cong nhan lap rap thi cong cot thep ong. Anh: Van Duc
Workers assemble the construction of steel pipes. Photo: Van Duc

According to the workers, spreading 500kV wires and pulling them across rivers and mountains is a difficult period for the electricity industry, this job requires workers to have flexible health and experience to do it.

"First of all, the electrician will spread ropes along the road, connecting from the top of one pole to the other to make a bidding line. This bidding cable was then stretched to the pillar and then tied to a 500kV power cable to pull it up.

When the wire was removed to the necessary location, 2 workers were waiting to do the task of locating the wire in the porous insulation to securely insulate the electricity. At this time, the worker has completed his work...", Mr. Chien shared.

Duong day 500kV Lao Cai - Vinh Yen nam tren nui cao, vi tri hiem tro, nen viec keo day rat gian nan. Anh: Van Duc
The 500kV Lao Cai - Vinh Yen line is located on a high mountain, in a difficult location, so pulling the rope is very difficult. Photo: Van Duc

Mr. Nguyen Duy Hung - Director of Hung Phu Thinh Power Construction Company said that contractors are currently mobilizing maximum forces, focusing on completing the installation of poles while the power transmission unit is transporting wires and cables to the locations.

As soon as the pole erection was completed, the construction unit coordinated with the army to run ropes to connect the poles in time for the power outage on September 2.

The 500kV Lao Cai - Vinh Yen Line project has a total length of nearly 230 km, passing through the two provinces of Lao Cai and Phu Tho, with a total investment of more than VND 7,410 billion.

A team of workers and engineers from all over have met here, they are "eating mountains, sleeping in the forest" working "3 shifts, 4 teams" overcoming all difficulties to strive to complete the project on schedule.

Nhóm PV
RELATED NEWS

Forests, mountains, and mountains will be built towers for the 500kV Lao Cai - Vinh Yen power line

|

To transport steel, cables, and electric poles to the foundation and erect poles for the 500kV Lao Cai - Vinh Yen line, trucks had to move each section over the slope.

Lao Cai - Vinh Yen 500kV transmission line project urgently before power outage

|

In just a few days, the 500kV Lao Cai - Vinh Yen line will be energized. From the construction site to the inspections, the words of encouragement from the Prime Minister and the leaders of the Vietnam General Confederation of Labor have given strength to hundreds of engineers and workers working tirelessly in the hot sun.

Total efforts to bring the Lao Cai - Vinh Yen 500kV transmission line project to the finish line

|

The 500kV Lao Cai - Vinh Yen transmission line project is being accelerated every day to complete on August 19.

What Ho Chi Minh City will do after universal bus ticket exemption

|

Ho Chi Minh City exempts all-people bus tickets along with improving service quality, optimizing routes and applying technology to attract people, reducing private cars.

Innovating leadership methods, preparing carefully for the 14th Trade Union Congress

|

Hanoi - In the first quarter of 2026, the Party Committee of the Vietnam General Confederation of Labor considered, gave opinions and decided on many important contents.

Commercial banks agree to reduce interest rates

|

Commercial banks agreed to reduce interest rates after a meeting with the State Bank, in order to support businesses and people.

Mr. Pham Quang Ngoc elected Secretary of Hung Yen Provincial Party Committee

|

Hung Yen - In the afternoon of April 9, the Provincial Party Committee Executive Committee for the 2025-2030 term held a conference to elect the title of Provincial Party Secretary and introduce key personnel.

Ho Chi Minh City Department of Health informs about the case of more than 50 elementary school students suffering from digestive disorders

|

Ho Chi Minh City - Recorded from Binh Quoi Ward Health Station and 3 hospitals, 53 students of Binh Quoi Tay Primary School came for examination due to symptoms of digestive disorders.

Forests, mountains, and mountains will be built towers for the 500kV Lao Cai - Vinh Yen power line

Nhóm PV |

To transport steel, cables, and electric poles to the foundation and erect poles for the 500kV Lao Cai - Vinh Yen line, trucks had to move each section over the slope.

Lao Cai - Vinh Yen 500kV transmission line project urgently before power outage

Nhóm PV |

In just a few days, the 500kV Lao Cai - Vinh Yen line will be energized. From the construction site to the inspections, the words of encouragement from the Prime Minister and the leaders of the Vietnam General Confederation of Labor have given strength to hundreds of engineers and workers working tirelessly in the hot sun.

Total efforts to bring the Lao Cai - Vinh Yen 500kV transmission line project to the finish line

Bảo Nguyên |

The 500kV Lao Cai - Vinh Yen transmission line project is being accelerated every day to complete on August 19.