Forests, mountains, and mountains will be built towers for the 500kV Lao Cai - Vinh Yen power line

Nhóm PV |

To transport steel, cables, and electric poles to the foundation and erect poles for the 500kV Lao Cai - Vinh Yen line, trucks had to move each section over the slope.

Under the burning sun in mid-August, each convoy of specialized vehicles, excavators, and winchers is still operating tirelessly on the Northwest mountainous and forest routes to construct the Lao Cai - Vinh Yen 500kV transmission line project.

Transporting hundreds of tons of steel, wires, and super-school equipment to erect massive electric poles in the terrain of high mountains and deep streams is a big challenge for those on the construction site.

Nhung chiec xe tai cho vat lieu len doc phai di kem voi mot may xuc banh xich de vuot doc.
Trucks carrying materials up the slope must be accompanied by a chain reactionor to climb the slope. Photo: Van Duc

At the pole locations in Thuong Ha commune, Lao Cai province, specialized vehicles with 3 bridges sloped down the slope, while in front of the excavator, they had to go ahead to remove mud and pull the support cable. Each meter of road is dozens of minutes of brain-tenching for drivers and technical staff. Many sections are just wide enough for wheels, with deep, steep abyss on both sides.

"There were days when the slope was too steep, we had to connect the cable of two vehicles to pull them over for a long time to get through. Many sections of the road are stuck all day, excavators have to come and pull them all the time, said engineer Nguyen Huu Hung - technical director of the project.

De nhung thanh thep, cuon cap hay cot dien nay den duoc vi tri dung, tung chuyen xe phai vuot lay bat ke nang mua.
For these steel bars, cables or electric poles to be erected, each trip has to go through the mountains and over the forests regardless of the sun or rain. Photo: Van Duc

In some locations such as 78, 79, the entire foundation is located on the top of the mountain in the shape of a hat, the flat surface is narrow, and materials must be transported in small pieces.

Or like column No. 56, a slope over 1km long, specialized vehicles have to be divided into many small trips, combining both trailers and dump trucks, pulling each section. Every time it rains, the mud is thick, the vehicle can only get by meters.

Theo chia se cua don vi thi cong, co ngay 36 dau xe van chuyen hon 300 tan cot. Dia hinh nay thi cu mua la lo nen don vi phai bo tri may xuc di truoc, vua mo duong vua sua duong.
According to the construction unit, there was a day when the first 36 vehicles transported more than 300 tons of poles. This terrain is eroded every time it rains, so the unit has to arrange excavators first, both opening the road and repairing the road. Photo: Van Duc

Speaking to Lao Dong Newspaper, Mr. Do Quang Khai, Deputy Director of the Power 1 Project Management Board and Director of the Lao Cai - Vinh Yen 500kV Power Line Project Management Board, said that these days, construction units are urgently deploying to ensure the pulling of ropes according to the general plan of the entire route.

"Everyone is working in a spirit of water retreat. Every day, the construction teams and units report the progress and plan for the next day" - Mr. Do Quang Khai said.

De dua xe cau 100 tan tiep can vi tri thi cong, don vi thi cong phai mat toi 2 ngay di chuyen, tham chi phai su dung mai ngoi de chong lay. Anh: Van Duc
To bring the 100-ton crane to the construction site, the driver had to spend many days moving in erratic weather conditions. Photo: Van Duc

Up to now, the volume of pillar construction in Lao Cai province has basically reached progress. The contractor arranged construction in parallel and simultaneously at the locations to soon hand over the grid and energize the power plant.

At the piers passing through Phu Tho province, the contractor has completed the erection of 38/48 piers. Units are focusing on human resources and machinery to complete the remaining 10 locations before September 2.

Du troi nang nong tren 37 do C, cong nhan o day van miet mai, hang say lao dong de hoan thanh cac cot mong cuoi cung duong day 500kV Lao Cai – Vinh Yen. Anh: Van Duc
Despite the hot weather above 37 degrees Celsius, workers here are still working hard to complete the final foundations of the 500kV Lao Cai - Vinh Yen line. Photo: Van Duc

The 500kV Lao Cai - Vinh Yen transmission line project is a national key project, with a total length of 229.5km with 468 pole foundation locations, passing through Lao Cai and Vinh Phuc provinces with a total investment of VND 7,410 billion.

The project plays an important role in transmitting the capacity of hydropower plants in the Northwest region and connecting with the national power system to coordinate electricity from the plains to the Northwest.

Nhóm PV
RELATED NEWS

The Prime Minister requested determination to complete the 500kV Lao Cai - Vinh Yen line by August 19, 2025

|

Prime Minister Pham Minh Chinh requested that by August 19, 2025, the 500kV Lao Cai - Vinh Yen transmission line must be completed so that the national power system can operate safely and stably.

Continue to focus on taking care of workers constructing the 500kV Lao Cai - Vinh Yen line

|

The leaders of the Vietnam General Confederation of Labor directly presented gifts and encouraged workers constructing the 500kV Lao Cai - Vinh Yen line.

Nearly 600 engineers and workers deploy the construction of poles for the 500kV Lao Cai - Vinh Yen transmission line project

|

Nearly 600 engineers and workers urgently deploy the erection of poles for the 500kV Lao Cai - Vinh Yen transmission line project.

Chairman of Ho Chi Minh City People's Committee Nguyen Van Duoc has high expectations for the most populous ward in Ho Chi Minh City

|

HCMC - Chairman of the HCMC People's Committee Nguyen Van Duoc hopes that Di An ward will become a bright spot in the development of a smart, modern, green and charitable city.

Promoting courage, affirming the role in building a modern and strong Vietnamese working class

|

On this day, 5 years ago, on August 18, 2020, the Party Committee of the Vietnam General Confederation of Labor (VGCL) held a congress of delegates for the 2020-2025 term. Over the term, the Party Committee of the Vietnam General Confederation of Labor has overcome many difficulties and challenges to excellently complete its tasks, promoting the core political leadership role of the Party organization operating at the Central agency of the Vietnam Trade Union.

Over VND 181,967 billion from initiatives of union members and workers

|

From 2020-2025, emulation movements launched and implemented by the Trade Union will attract a large number of union members and workers to participate.

Passenger bus collides with car in Deo Ngang tunnel, 2 people died

|

Quang Tri - A passenger bus collided with a 7-seat car in the Deo Ngang tunnel (connecting Ha Tinh with Quang Tri), killing 2 people.

Unprecedented major protest shakes Israel, 1 million people take to the streets to demand a ceasefire

|

Nearly 500,000 people took part in the protest in Tel Aviv, and 1 million people took part in the nationwide protests on August 17.

The Prime Minister requested determination to complete the 500kV Lao Cai - Vinh Yen line by August 19, 2025

Tuyết Lan |

Prime Minister Pham Minh Chinh requested that by August 19, 2025, the 500kV Lao Cai - Vinh Yen transmission line must be completed so that the national power system can operate safely and stably.

Continue to focus on taking care of workers constructing the 500kV Lao Cai - Vinh Yen line

Hà Anh |

The leaders of the Vietnam General Confederation of Labor directly presented gifts and encouraged workers constructing the 500kV Lao Cai - Vinh Yen line.

Nearly 600 engineers and workers deploy the construction of poles for the 500kV Lao Cai - Vinh Yen transmission line project

Kiều Vũ |

Nearly 600 engineers and workers urgently deploy the erection of poles for the 500kV Lao Cai - Vinh Yen transmission line project.