Ensuring safety at the Lao Cai - Vinh Yen 500kV transmission line construction site during the rainy and stormy season

Nhóm PV |

The 500kV Lao Cai - Vinh Yen transmission line project is facing many difficulties due to the harsh terrain and the Northwest beginning of the rainy and stormy season.

In recent days, due to complicated weather developments, natural disaster prevention, control and safety assurance at the construction site of the 500kV Lao Cai - Vinh Yen transmission line project has become more urgent than ever.

At the location of VT140 pole in Lam Thuong commune, Lao Cai province, Mr. Le Van Du, the project's engineer, said: "The pole is located on the top of the hill, from the foot of the hill to the location of the pole, nearly 2km long. We divide shifts, stay from early morning to late night, trying to complete before the storm hits."

Toan canh vi tri cot VT140 nam tren dinh mot ngon doi tai xa Lam Thuong (Lao Cai). Anh: Ngoc Linh
Panorama of the location of VT140 pole located on the top of a hill in Lam Thuong commune (Lao Cai). Photo: Ngoc Linh

According to Mr. Du, this is one of the most difficult locations of the project. The nearly 2km road from the foot of the hill to the top after the heavy rain the previous day made it impossible for vehicles to travel.

Workers and engineers have to walk, carrying every meter of cable and iron bar to the top of the hill so that the work is not interrupted.

Cong nhan lap gian giao keo day vuot Quoc lo 4E, dia phan tinh Lao Cai. Hinh anh ghi nhan sang 22.7.2025
Workers install scaffolding to pull ropes across National Highway 4E, Lao Cai province. Image recorded on the morning of July 22, 2025

Mr. Van Minh Tam (construction unit) also shared: The work here is extremely difficult because of the complex terrain, dense hills, and large slopes.

Opening the road to the construction site also takes a lot of time and effort. Long, heavy steel pipes cannot be transported in whole, forcing them to be divided into many sections for easy transportation.

Mr. Tam confided that every time he hears a rain forecast, everyone is anxious and restless.

"Just one day's rain will result in a 2-3 day of stopping construction because the road is muddy and unsafe. Completing the project on schedule is not only a race against time, but also a fierce battle with harsh weather, he said.

Den thoi diem ngay 22.7, 461/468 vi tri ho mong du an duong day 500kV Lao Cai – Vinh Yen da duoc hoan thanh truoc khi bao ve. Anh: Bao Nguyen
As of July 22, 461/468 foundation holes of the Lao Cai - Vinh Yen 500kV transmission line project had been completed before the storm arrived. Photo: Bao Nguyen

On July 22, speaking with a reporter from Lao Dong Newspaper, Mr. Do Quang Khai, Deputy Director of the Power 1 Project Management Board, Director of the Project Management Board, said: Up to now, 461/468 foundation holes of the Lao Cai - Vinh Yen 500kV transmission line project have been completed. To respond to weather developments and proactively prevent and combat natural disasters, 100% of management board staff and contractors are mobilized and on duty at the construction site according to the "4 on-site" motto.

According to Mr. Do Quang Khai, in the context of the Lao Cai - Vinh Yen 500kV transmission line project being constructed on rugged mountainous terrain, ensuring absolute safety for people and equipment is especially important. The Project Management Board has directed contractors to fully grasp the proactive spirit of the workers and construction forces, absolutely not being subjective in the face of storm No. 3.

Dia hinh doi nui doc dung gay khong it kho khan cho don vi thi cong sau moi tran mua lon. Anh: Thanh Tuan
The steep hillside terrain causes many difficulties for the construction unit after each heavy rain. Photo: Thanh Tuan
Troi mua, mot so doan duong ngap nuoc, sinh lay, cac chien si phai nao vet bun, san lap duong de giup xe cho vat lieu di chuyen duoc len vi tri mong cot. Anh: Thanh Trung
Soldiers of Military Region 2 supported the construction unit in opening the road, directly participating in transporting materials and equipment for the construction of the Lao Cai - Vinh Yen 500kV transmission line project. Photo: Thanh Trung

At the same time, the contractor must arrange a full camp, warehouse and shelter for workers in safe and convenient locations. All construction equipment, machines such as excavators and bulldozers are also transferred from the high hill. Materials and equipment at the warehouse are carefully concealed and have a plan to relocate out of the area at risk of slipping and flash floods.

"Currently, taking advantage of favorable weather, we are focusing all resources on construction. Contractors also increased human resources, vehicles, and gathered columns, materials, and equipment to the foundation to compensate if affected by the storm, said Mr. Khai, emphasizing that the entire construction site is determined to maintain the construction atmosphere, ensuring both safety and progress.

Nhóm PV
TIN LIÊN QUAN

Overcoming the difficult terrain of the Lao Cai - Vinh Yen 500kV transmission line project

|

100 officers and soldiers of Military Region 2 were present at the project's difficult locations to work with construction units to speed up the progress.

Racing against storms to laid foundations for the 500kV Lao Cai - Vinh Yen power line

|

Despite the sunny weather, unusual rain, landslides and flash floods in Lao Cai and Yen Bai provinces, thousands of workers are still day and night, working hard at the Lao Cai - Vinh Yen 500kV transmission line project site.

Consolidating temporary roads for construction of the 500kV Lao Cai - Vinh Yen transmission line project

|

Yen Bai - The interspersed soil and rock caused many obstacles in the construction of the 500kV Lao Cai - Vinh Yen transmission line project through Luc Yen district.

High-rise house fire on Giai Phong Street, Hanoi

|

Hanoi - A high-rise house on Giai Phong Street suddenly caught fire fiercely on the afternoon of July 22. The authorities quickly arrived at the scene to put out the fire.

Hung Yen recovers after storm, people start taking to the streets, many trees fall

|

Hung Yen - On the afternoon of July 22, the weather in some wards such as Pho Hien, Nam Son, Hong Chau stabilized again after storm No. 3.

Hai Phong has big waves, strong winds after the storm, water overflows onto the road in the tourist area

|

Hai Phong - Due to the impact of storm No. 3, the sea area of Do Son 1 recorded high tides combined with big waves and strong winds.

To propose salary increase as a driving force for development

|

Mr. Le Dinh Quang - Former member of the National Wage Council shared in depth and frankly about the proposals to adjust the regional minimum wage in the coming time.

Witnessing the cable break in Dien Bien

|

Dien Bien - Rescue forces are planning to salvage the car that fell into the river due to a broken cable of a suspension bridge in Thanh Yen border commune.

Overcoming the difficult terrain of the Lao Cai - Vinh Yen 500kV transmission line project

Nhóm PV |

100 officers and soldiers of Military Region 2 were present at the project's difficult locations to work with construction units to speed up the progress.

Racing against storms to laid foundations for the 500kV Lao Cai - Vinh Yen power line

Nhóm PV |

Despite the sunny weather, unusual rain, landslides and flash floods in Lao Cai and Yen Bai provinces, thousands of workers are still day and night, working hard at the Lao Cai - Vinh Yen 500kV transmission line project site.

Consolidating temporary roads for construction of the 500kV Lao Cai - Vinh Yen transmission line project

Bảo Nguyên - Văn Đức |

Yen Bai - The interspersed soil and rock caused many obstacles in the construction of the 500kV Lao Cai - Vinh Yen transmission line project through Luc Yen district.