The Vung Ang - Bung expressway section is expected to open to traffic on August 19

TRẦN TUẤN |

Ha Tinh - Aiming to open the route on June 30, however, the Vung Ang - Bung expressway project has not been completed, so it is expected to open to traffic on August 19.

On June 22, the contractor, Hoa Binh 479 Joint Stock Company, is focusing on the construction of bridge No. 1 of the Vung Ang - Bung expressway project in Ha Tinh province.

Bridge No. 1 is 942 m long, with 22 spans, spanning the valley in Ky Hoa commune, Ky Anh town, and was officially started in February 2023. Up to now, the contractor is making efforts to connect the last two spans of this bridge.

The Deo But tunnel project under the construction of Son Hai Group is also being focused on completion. Up to now, the right tunnel has completed the road surface concrete paving, installed electromechanical systems, fire prevention and fighting, and painted the tunnel lining.

Ham Deo But thi cong kho khan. Anh: Quang Tuan.
Deo But tunnel is under construction with difficulties. Photo: Quang Tuan

On June 22, a reporter from Lao Dong Newspaper asked about the goal of opening the Vung Ang - Bung expressway section on June 30 whether it would be achieved or not, a leader of the Vung Ang - Bung expressway component project management board said that according to the Prime Minister's order, the opening ceremony of this route will not be held until August 19.

The Vung Ang - Bung expressway is 55.34 km long, passing through Ha Tinh province (12.9 km) and Quang Binh with the starting point intersecting with National Highway 12C, connecting with Ham Nghi - Vung Ang expressway in Ky Tan commune, Ky Anh district, Ha Tinh province and the end point is in Cu Nam commune, Bo Trach district, Quang Binh province connecting to the Bung - Van Ninh expressway.

The project is invested by Project Management Board 6 (Ministry of Construction). The project is divided into 2 construction packages, of which the XL01 construction package is undertaken by Son Hai Group - Vietnam Construction and Import-Export Joint Stock Corporation - Joint Stock Company 484 - Construction Joint Stock Company 369 - Joint Stock Company 479 Hoa Binh.

The XL02 construction package is constructed by Phuong Thanh Traffic Investment and Construction Joint Stock Company - Lizen Joint Stock Company.

There are still some unfinished items on the route. The project site in the section passing through Quang Binh province has not yet been handed over 100%.

Thus, the Vung Ang - Bung expressway component project cannot open the route and put it into operation on June 30 as planned by the Ministry of Construction.

One of the reasons for not achieving the plan is due to complicated and difficult construction terrain, construction through forests and mountains and related to site handover progress.

TRẦN TUẤN
TIN LIÊN QUAN

It is necessary to complete 800km of expressway, opening the Cao Bang - Ca Mau route in 2025

|

The Prime Minister requested that from now until the end of the year, about 800km of expressway should be completed and the expressway from Cao Bang to Ca Mau should be opened to traffic in 2025.

Plan to complete the construction of the Hanoi - Thai Nguyen expressway

|

The Hanoi - Thai Nguyen Expressway currently has a scale of only 2 - 4 lanes, so the upgrading and expansion is considered in accordance with the plan.

The Ministry of Construction accelerates to complete the target of 3,000 km of highways

|

Completing 3,000 km of expressway in 2025 is a key goal identified by the Ministry of Construction and determined to implement it from the first days of the year.

Driver drives a dangerous car along National Highway 1, traffic police patrol through and immediately support rescue

|

Binh Thuan - A driver was driving a car on National Highway 1 when he fell into a coma and was in critical condition. The traffic police patrol team passing by called an ambulance to assist in the emergency situation.

Glory of Vietnam 2025 - Pride and Aspiration

|

The Vietnam Glory Program in 2025 with the theme "Pride and Aspiration" honors 19 typical advanced collectives and individuals with outstanding achievements in key areas. They are quiet but persistent, creative flowers, committed to contributing to the appearance of Vietnam today.

Iran denies nuclear fortress wiped out after US airstrike

|

Iranian officials denied Mr Trump's claim that three of Iran's key nuclear facilities were wiped out after the airstrikes conducted by the US and Israel.

After 1 week of trial operation of the 2-level government model in Ho Chi Minh City

|

HCMC - About a week from the official operation of the 2-level government model, the new wards are trying to test the apparatus, ensuring progress.

The stock market may see an adjustment

|

With the indicators unable to break out and cash flow showing clear signs of caution, the stock market is likely to have an adjustment.

It is necessary to complete 800km of expressway, opening the Cao Bang - Ca Mau route in 2025

ANH HUY |

The Prime Minister requested that from now until the end of the year, about 800km of expressway should be completed and the expressway from Cao Bang to Ca Mau should be opened to traffic in 2025.

Plan to complete the construction of the Hanoi - Thai Nguyen expressway

Việt Bắc |

The Hanoi - Thai Nguyen Expressway currently has a scale of only 2 - 4 lanes, so the upgrading and expansion is considered in accordance with the plan.

The Ministry of Construction accelerates to complete the target of 3,000 km of highways

Phan Anh |

Completing 3,000 km of expressway in 2025 is a key goal identified by the Ministry of Construction and determined to implement it from the first days of the year.