Tô Công |

Phu Tho - The total value of the new Phong Chau bridge construction project is currently over 75%, striving to close the bridge on the occasion of the 80th anniversary of National Day on September 2.

The project to build the new Phong Chau bridge - National Highway 32C, Phu Tho province will be implemented from the end of 2024 according to the Emergency Construction Order.

The project has a total investment of more than 635 billion VND from the central budget reserve; Thang Long Project Management Board (under the Ministry of Construction) is the project investor, the construction unit is Army Corps 12 - Truong Son Construction Corporation.

Toan canh cong truong thi cong xay dung cau Phong Chau moi. Anh: To Cong.
Overview of the construction site of the new Phong Chau bridge. Photo: To Cong.

Coming to the new Phong Chau bridge construction site in early August, Lao Dong Newspaper reporters recorded that hundreds of officers, engineers, workers and many modern vehicles and equipment are rushing to construct this key project.

To soon complete the project and put it into use, meeting the people's expectations, Truong Son Construction Corporation has organized 3 shifts, 4 teams, working regardless of day or night, holidays, holidays... for more than 7 months since the start of construction.

Cong trinh cau Phong Chau moi sung sung tren song Hong. Anh: To Cong.
The new Phong Chau bridge project is a pillar on the Red River. Photo: To Cong.

Up to now, the new bridge across the Red River has gradually taken shape, with a total implementation value of over 75%. The important items such as bored piles, piers, and T-shaped beams have all been completed, the work of casting and balancing the main spans is being quickly implemented... The investor and the construction unit are determined to close the bridge on the occasion of the 80th anniversary of National Day on September 2.

Mr. Bui Van Tuyen - a business owner at the head of Phong Chau bridge (Van Xuan commune) - shared: "For me as well as thousands and tens of thousands of people living on both sides of the Red River, Phong Chau bridge is very important for travel, trade exchange, and economic development. We are looking forward to it, the day the new bridge is completed will be a festival".

Cac cong nhan miet mai thi cong cau duoi thoi tiet nang nong oi buc. Anh: To Cong.
Workers are working hard to construct the bridge in hot weather. Photo: To Cong.

Recently, during the progress inspection, encouraging officers, soldiers and workers who are constructing the new Phong Chau bridge, Chairman of Phu Tho Provincial People's Committee Tran Duy Dong requested the Department of Construction and related sectors to closely coordinate to promptly resolve problems as well as recommendations and proposals from investors; specifically calculate raw material prices, ensuring that they are suitable for the actual situation at each time.

The Chairman of Phu Tho Provincial People's Committee assigned the Department of Construction to review mines in the area, provide boulders for embankment construction and make additional estimates for the project.

Nguoi dan mong cho cong trinh cau Phong Chau moi se som duoc dua vao su dung. Anh: To Cong.
People are looking forward to the new Phong Chau bridge project being put into use soon. Photo: To Cong.

Representatives of the construction units pledged to focus all resources, work overtime, and increase shifts to complete the remaining items according to the set plan, and promptly hand over the project to Phu Tho province for exploitation and use.

The newly built Phong Chau bridge crosses the Red River, located on National Highway 32C, connecting the two communes of Phung Nguyen and Van Xuan of Phu Tho province (belonging to Phung Nguyen commune, Lam Thao district and Van Xuan commune, the old Tam Nong district).

According to the design, the main bridge is 383 m long, the approach road to the sliding bridge connecting to Phung Nguyen commune is 113 m long, the Van Xuan commune side is 155 m long, the surface is 20.5 m wide.

Tô Công
RELATED NEWS

Prime Minister sets deadline for completing Phong Chau bridge construction

|

Prime Minister Pham Minh Chinh requested Phu Tho province and the Ministry of National Defense to complete the construction of Phong Chau bridge before October 31, 2025.

The new Phong Chau bridge piers are stationary on the Red River at the beginning of the flood season

|

Phu Tho - After many months of urgent construction, the new Phong Chau bridge piers have now taken shape, standing on the Red River with rising water at the beginning of the flood season.

Investing 99 billion VND to extend the inter-regional road near Phong Chau bridge

|

Phu Tho - The 2,120 billion VND inter-regional road project is about to build an additional extended road connecting from the beginning of the route to the Phong Chau bridge area, in Tam Nong district.

Latest forecast of the path of the tropical depression and bad weather

|

According to the meteorological agency, it is forecasted that in the next 24 hours, the tropical depression will gradually weaken into a low pressure area.

Personnel transfer and appointment in Nghe An, Phu Tho, Thanh Hoa

|

From August 4 to August 8, in Nghe An, Phu Tho, Dong Nai, Son La, Thai Nguyen, Thanh Hoa, Khanh Hoa provinces... decisions on election, transfer, and appointment of personnel will be implemented.

The Royal Yard BT Project in Nha Trang falls into a spiral of debt

|

The BT project of the Royal Yacht Wharf Center in Nha Trang is falling into a bad debt situation, and its assets are being tightly regulated by the bank.

President Luong Cuong successfully concludes his visit to Angola

|

The farewell ceremony for President Luong Cuong and his wife was solemnly held at the President of Angola.

1 Major General, 5 Colonels, 5 Colonel-level military officers receive new assignments

|

1 Major General, 5 Colonels, 3 Lieutenant Colonels, 2 Major Cants, 1 Army Captain have just been elected, appointed, transferred, and appointed to new assignments last week (August 4 - August 8).

Prime Minister sets deadline for completing Phong Chau bridge construction

ANH HUY |

Prime Minister Pham Minh Chinh requested Phu Tho province and the Ministry of National Defense to complete the construction of Phong Chau bridge before October 31, 2025.

The new Phong Chau bridge piers are stationary on the Red River at the beginning of the flood season

Tô Công |

Phu Tho - After many months of urgent construction, the new Phong Chau bridge piers have now taken shape, standing on the Red River with rising water at the beginning of the flood season.

Investing 99 billion VND to extend the inter-regional road near Phong Chau bridge

Tô Công |

Phu Tho - The 2,120 billion VND inter-regional road project is about to build an additional extended road connecting from the beginning of the route to the Phong Chau bridge area, in Tam Nong district.