Racing for public investment progress in Nghe An before merging districts

QUANG ĐẠI |

Nghe An - The Provincial People's Committee requests investors to urgently complete public investment projects before July 1.

On May 17, Mr. Le Hong Vinh - Chairman of Nghe An Provincial People's Committee said that Nghe An Provincial People's Committee focuses on directing the acceleration of construction progress, completing acceptance procedures and putting public investment projects into use, with the goal of completing before the end of the operation of district-level administrative units (1.7).

According to a report from the People's Committee of Vinh City - where there are a large number of construction works under construction - many projects are still facing difficulties in site clearance, investment procedures and capital allocation. For example, the extended Ly Thuong Kiet route currently has about 400m left that cannot be constructed due to land clearance problems. The 18m planned road project connecting National Highway 46 with Vinh - Cua Lo Avenue has an investment capital of nearly 145 billion VND, after more than 2 years of construction, nearly 500m has been filled and then temporarily suspended due to lack of clean land.

Du an duong Ly Thuong Kiet (TP Vinh) thi cong do dang, keo dai. Anh: Quang Dai
The Ly Thuong Kiet road project (Vinh city) is under construction and has been prolonged. Photo: Quang Dai

Currently, the Vinh City Construction Investment Project Management Board has completed 165 projects. It is expected that 16 more projects will be completed before July 1, 2025. Meanwhile, the remaining 92 projects will be developed a plan to hand over to the receiving unit after the district-level administrative apparatus is rearranged.

In some other districts and towns, many public investment projects are still behind schedule due to land clearance problems.

The project to renovate and expand National Highway 46 Vinh - Nam Dan section, although the compensation plan has been approved, has only cleared about 4/10.69km of the site. Nam Dan District People's Committee is currently focusing on handling the remaining part to keep up with the progress.

As of April 30, 2025, the total disbursement value of public investment capital in the whole province reached about VND 2,212 billion, equivalent to 22.12% of the annual plan - higher than the national average (15.56%). However, site clearance is still a major "bottleneck". Some localities have not completed land records and have not agreed on compensation plans, causing many projects to be behind schedule.

Nghe An Provincial People's Committee has issued an official dispatch requesting investors and project management boards to proactively review and promote the progress of projects. Construction works need to complete payment and acceptance documents before June 30 to avoid legal problems when transferring. For projects that cannot be completed in time, localities must develop a reasonable technical arrest plan and hand over in accordance with regulations.

In addition, the Provincial People's Committee also directed the study of capital transfer options between projects to optimize budget efficiency and ensure that key projects are not stalled.

According to Chairman of Nghe An Provincial People's Committee Le Hong Vinh, accelerating public investment progress not only helps to effectively exploit infrastructure, but also avoids waste in the transition period of the administrative apparatus, creating growth momentum for localities that are about to merge.

QUANG ĐẠI
RELATED NEWS

Dak Nong speeds up disbursement, removes obstacles for public investment projects

|

Dak Nong is accelerating disbursement, removing obstacles for public investment projects, especially site clearance.

Low public investment disbursement rate, Chairman of Can Tho criticizes heads of 20 units

|

Can Tho - The Chairman of the city acknowledged that the public investment disbursement rate is slow to progress; the sense of responsibility of some Department Directors, Heads... is not high.

List of ministries, branches and localities with low public investment disbursement rates

|

Ministries, branches and localities with a disbursement rate of public investment capital lower than the national average need to speed up the implementation of investment and construction procedures in the coming time.

Updated gold price at the end of session 7.12: gloomy end of the week

|

Updated gold price at the end of the session on December 7: Gold prices last week decreased simultaneously in both domestic and international markets.

Long Thanh airport resettlement area is spacious with villas and townhouses after nearly 5 years

|

Dong Nai - The 280-hectare Long Thanh airport resettlement area has become a bustling urban area, bringing a better life than before to the people.

Proposal to handle trucks that are too bulky and cause sand to splash

|

Ha Tinh The government of Bac Hong Linh ward will issue a document recommending control and handling the situation of trucks carrying more than enough goods into bins causing sand to spill on National Highway 1.

Proposal to discipline the Deputy Director of Lam Dong Department of Agriculture and Environment

|

Lam Dong - Mr. Nguyen Van Duc, Deputy Director of Lam Dong Department of Agriculture and Rural Development, was proposed to consider implementing the party discipline for violating things that party members are not allowed to do.

HCMC builds 5 bridges larger than VND175,000 billion, ending ferry problems

|

Ho Chi Minh City is about to build a road and a sea overpass connecting Can Gio - Vung Tau, Can Gio bridge, Cat Lai bridge, Phu My 2 bridge, Dong Nai 2 bridge, with a total investment of about 175,000 billion VND.

Dak Nong speeds up disbursement, removes obstacles for public investment projects

BẢO LÂM |

Dak Nong is accelerating disbursement, removing obstacles for public investment projects, especially site clearance.

Low public investment disbursement rate, Chairman of Can Tho criticizes heads of 20 units

Hàn Lâm |

Can Tho - The Chairman of the city acknowledged that the public investment disbursement rate is slow to progress; the sense of responsibility of some Department Directors, Heads... is not high.

List of ministries, branches and localities with low public investment disbursement rates

ANH HUY |

Ministries, branches and localities with a disbursement rate of public investment capital lower than the national average need to speed up the implementation of investment and construction procedures in the coming time.