Ward Chairman proposes how to handle households that do not allocate land to build Ring Road 1

Anh Tuấn |

For households that deliberately do not hand over land for Ring Road 1, the People's Committee of Giang Vo Ward will cut off electricity, water, and corrugated iron fences to carry out enforcement.

In recent days, the authorities of Lang and Giang Vo wards have coordinated with relevant departments and branches of Hanoi to simultaneously organize compulsory land recovery to serve the site clearance for the investment project to build Ring Road 1, Hoang Cau - Voi Phuc section.

Enforcement activities are being implemented for organizations and individuals who are using land areas that have been decided to be reclaimed, in order to implement the direction of the city leaders on the goal of completing site clearance before December 15.

According to the records, the enforcement process was carried out in accordance with legal procedures and order, ensuring the safety of people, property, vehicles and participating forces, and not causing complicated situations. The enforcement measures were taken thoroughly, along with a plan to protect the scene and prevent re-encroachment after site clearance.

Mr. Co Nhu Dung, Chairman of Giang Vo Ward People's Committee, said that the volume of land acquisition plans in the area is large, while the time is urgent. Therefore, the locality must mobilize maximum forces, work on holidays, and take advantage of time outside of working hours to implement many tasks in parallel, ensuring the overall progress of the project.

Thanks to the synchronous and drastic participation of the forces, by 8:00 p.m. on December 10, 2025, the People's Committee of Giang Vo Ward had completed site clearance of more than 40,015 m2 of land of organizations and individuals, handing over the site to the investor 5 days earlier than the city's request.

Luc luong chuc nang di doi tai san, pha do cong trinh de ban giao mat bang cho du an duong Vanh dai 1 doan Hoang Cau - Voi Phuc. Anh: Hai Nguyen
The authorities relocated assets and demolished the construction to hand over the site for the Ring Road 1 project, Hoang Cau - Voi Phuc section. Photo: Hai Nguyen

According to Mr. Co Nhu Dung, the propaganda and mobilization work has been identified by the Party Committee, People's Committee and Vietnam Fatherland Front Committee of Giang Vo ward as a priority task, implemented throughout to minimize the need for enforcement measures.

The Ward People's Committee has organized citizen receptions and dialogues continuously day and night, promptly responding and resolving recommendations related to land recovery. For cases where people are not present at their place of residence, when contacted, ward officials directly go to their living address to mobilize and persuade them to hand over the site.

When households had not previously agreed to accept the land handover, the People's Committee of the ward publicly announced the results at the reclaimed area to create consensus and spread to surrounding households.

For cases where the site has been handed over, the locality urges the investor to immediately dismantle the project, handle it as soon as received, forming an empty site, thereby creating a positive effect in the compliance of adjacent households.

In parallel with the mobilization, the ward also applied administrative measures for cases of intentional non-compliance, such as stopping the supply of electricity, water, and corrugated iron fences in front of the sidewalk to ensure legal discipline in land recovery.

Thanks to this method, by the time of the enforcement on December 10, Giang Vo ward only had to apply enforcement measures to a household at 45 Nguyen Chi Thanh, ensuring compliance with legal regulations. The situation in the enforcement area is safe, without any problems with security and order.

According to Mr. Dung, the Ward People's Committee also promotes the application of digital technology to increase transparency and interaction with people. platforms such as Digital Capital Citizen (iHanoi) and internal Zalo groups are used to update progress by day, by the hour, receiving feedback from people 24/7. This helps expand propaganda channels, orient public opinion in a timely manner and limit false information.

In addition, the application "Giang Vo Ward Digital C updated" is exploited to serve the monitoring of land acquisition and site management after clearance.

This is a model of land management, construction order, construction planning and transport infrastructure based on a modern digital platform, with organized and centralized data storage, contributing to improving the efficiency of State management, said Mr. Dung.

Anh Tuấn
RELATED NEWS

Hanoi Secretary points out experience in site clearance from Ring Road 1 project

|

Hanoi - Mr. Nguyen Duy Ngoc pointed out the experiences in site clearance for Ring Road 1, which need to be replicated for other projects.

Hanoi announces good news about the Ring Road 1 project

|

Hanoi has basically completed the land acquisition and site clearance for the Ring Road 1 project (Hoang Cau - Voi Phuc section) after 7 years of implementation.

The first ward to complete site clearance for the Ring Road 1 project

|

Hanoi - O Cho Dua Ward has officially completed site clearance for the Hoang Cau - Voi Phuc section of Ring Road 1 construction project.

Former South Korean President Yoon Suk Yeol faces death penalty

|

On January 13, prosecutors proposed the death penalty for former South Korean President Yoon Suk Yeol.

Inside the 100-year-old memorial house under relocation as Ring Road 2.5

|

Hanoi - The revolutionary memorial house of Mr. Ta Dinh Tan in Cau Giay ward is under site clearance and relocation according to the Ring Road 2.5 project plan.

Million-dong lacquered horses become Tet gifts favored by businesses

|

Lacquer horse mascots priced at millions of VND are chosen by many business people as Tet gifts thanks to their feng shui meaning and the message of smooth traffic at the beginning of the year.

Many officials of Soc Son commune were named because hundreds of land dossiers were overdue

|

Hanoi - The inspection team determined the responsibility of many officials of Soc Son commune for delays and sluggishness in resolving dossiers, affecting people's rights.

Hanoi opens roads worth more than 1,300 billion VND in January 2026

|

Hanoi - The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is expected to be completed and technically opened to traffic in January 2026.

Hanoi Secretary points out experience in site clearance from Ring Road 1 project

SÓNG HỮU |

Hanoi - Mr. Nguyen Duy Ngoc pointed out the experiences in site clearance for Ring Road 1, which need to be replicated for other projects.

Hanoi announces good news about the Ring Road 1 project

SÓNG HỮU |

Hanoi has basically completed the land acquisition and site clearance for the Ring Road 1 project (Hoang Cau - Voi Phuc section) after 7 years of implementation.

The first ward to complete site clearance for the Ring Road 1 project

SÓNG HỮU |

Hanoi - O Cho Dua Ward has officially completed site clearance for the Hoang Cau - Voi Phuc section of Ring Road 1 construction project.