Urgent telegram on the expressway connecting 2 border provinces

Tân Văn |

Cao Bang - The locality sets a target to open the Dong Dang - Tra Linh expressway for traffic on April 30, 2026.

On February 11, according to PV's investigation, Chairman of Cao Bang Provincial People's Committee Le Hai Hoa has just issued an urgent telegram requesting departments, branches, localities and related units to accelerate the progress of the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway project.

Specific milestones are set, associated with each important holiday such as striving to open traffic to Dong Khe on April 30, 2026 and complete the entire phase 1 on May 19, 2026.

According to Cao Bang Provincial People's Committee, the Dong Dang - Tra Linh expressway project has a total length of 121km, implemented in complex mountainous terrain conditions, many slopes over 50m high, lacking access roads.

The Provincial People's Committee assessed that 2025 is a difficult year when prolonged rain and floods for many months have damaged temporary works, swept away temporary bridges, and even engineers have been swept away by floods, these things greatly affect the construction progress.

However, with the efforts of investors, project businesses, consulting units, contractors and workers, the volume of excavation and embankment of the project has reached nearly 40 million m3, equivalent to the infrastructure construction volume of the entire Cao Bang province in about 5 years.

The parallel implementation of two phases also helps save about 1,000 billion VND in costs.

To ensure the set progress milestones, the Chairman of Cao Bang Provincial People's Committee requested localities with projects passing through to urgently complete site clearance, hand over 100% of clean ground in February 2026, focusing on thoroughly handling bottlenecks such as IC04 intersection, TMC central area.

Project enterprises and contractors are required to organize construction throughout the Binh Ngo Lunar New Year 2026, increase shifts, increase crews, maximize favorable weather conditions; and at the same time review, transfer or replace contractors with limited capacity, especially in key sections from Km30 to Km38.

Along with that, quality supervision work must be tightened. Supervision consulting units and design consultants are required to strengthen on-site inspection, and promptly complete technical design documents and construction drawings to serve the next phase.

The early completion and opening of the Dong Dang - Tra Linh expressway, especially the section to Dong Khe, is expected to create an important driving force to promote socio-economic development, expand development space and strengthen inter-regional connectivity for Cao Bang province and the Northeast region.

Tân Văn
RELATED NEWS

Lessons learned in the construction of the Dong Dang - Tra Linh expressway

|

Cao Bang - In the process of deploying the Dong Dang - Tra Linh expressway, the locality has drawn many important lessons learned.

Dong Dang - Tra Linh Expressway is as beautiful as a painting before the "opening" date

|

In just 2 days, the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway will officially open the route, opening up opportunities for the Northeastern provinces.

85km of foundation and 20km of asphalt paving will be opened on the Dong Dang - Tra Linh Expressway

|

Cao Bang - At the Dong Dang - Tra Linh expressway construction site, workers are working overtime day and night to open the technical route in time.

The first Trade Union bus takes Da Nang workers home for Tet

|

Da Nang - On the morning of February 11, the first "Trade Union Buses" officially rolled, taking thousands of Da Nang workers to go home for Tet.

Peach blossoms bloom early, small traders throw away branches exposed on the sidewalk

|

Thanh Hoa - Because some peach trees bloomed early and there were no buyers, small traders cut down branches and left them exposed on the sidewalk.

Factory fire in industrial cluster in Ninh Binh

|

Ninh Binh - A factory under construction at Le Ho Industrial Cluster caught fire fiercely, causing many properties to be burned down.

North Korea reacts toughly to Japan's military move

|

Japan's establishment of close security and defense relations with Canada recently has caused significant concern for North Korea.

US unexpectedly changes strategy, opening the door for Venezuelan oil and gas

|

The US Treasury Department officially licensed the export of oil and gas technology and equipment to Venezuela, marking a noteworthy move to ease sanctions.

Lessons learned in the construction of the Dong Dang - Tra Linh expressway

Duy Dũng |

Cao Bang - In the process of deploying the Dong Dang - Tra Linh expressway, the locality has drawn many important lessons learned.

Dong Dang - Tra Linh Expressway is as beautiful as a painting before the "opening" date

Khánh Linh |

In just 2 days, the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway will officially open the route, opening up opportunities for the Northeastern provinces.

85km of foundation and 20km of asphalt paving will be opened on the Dong Dang - Tra Linh Expressway

Duy Dũng |

Cao Bang - At the Dong Dang - Tra Linh expressway construction site, workers are working overtime day and night to open the technical route in time.