On February 10, according to reporters of Lao Dong Newspaper, at the construction site of the central main road project connecting National Highway 1, the section bypassing Ky Anh town (old) to Vung Ang - Son Duong deep-water port cluster, many machines and workers are still focusing on construction.
Ms. Nguyen Thi Hoa (born 1986, residing in Song Tri ward, Ha Tinh province) and many workers are working on the item of cement filling connecting the hard median strips in the middle of the road - said that the company announced the start of Tet holiday from December 26th of the lunar calendar (ie February 13th).

It's almost Tet, everyone wants to have an early day off to go home to clean the house and prepare for Tet shopping. However, for the company's common work, we have to try our best to do it," Ms. Hoa shared.
According to Ms. Hoa, she is a local worker working at the construction site of the central main road project connecting National Highway 1, the section bypassing Ky Anh town (old) to the Vung Ang - Son Duong deep-water port complex for a year now.
Her income is calculated daily, every day is 450,000 VND. Whenever she goes to work, she has money, when she doesn't go to work, she has no income.
At package No. 18 of the Central Main Road Project connecting National Highway 1, the section avoiding Ky Anh town (old) to the Vung Ang - Son Duong deep-water port cluster, machinery and labor of Ha Tinh Industrial - Construction and Trade Development Joint Stock Company are pouring base stone for the roadbed.

Mr. Nguyen Thang Long - technical officer of Ha Tinh Industrial - Construction and Trading Development Joint Stock Company present at the construction site said that the Company plans to construct until December 26th of the lunar calendar to give workers Tet holiday. After that, on the 6th day of Tet, they will return to the construction site.
At the construction site of VinFast electric motorbike factory, which is the most bustling large construction site in Vung Ang Economic Zone. Here, hundreds of machines and thousands of workers are focusing on construction.
An official of the Project Management Board said that there are currently about 3,500 people constructing the VinFast electric motorcycle factory in Vung Ang. To speed up progress, it is expected that the contractor will arrange a part of workers to construct throughout Tet.



Along with accelerating the construction progress to expect VinFast electric motorcycle factory to go into operation from March 2026, the investor is also recruiting thousands of workers.
Mr. Nguyen Van Nam - Production Human Resources Director of VinFast Production and Trading Joint Stock Company - Ha Tinh Branch - said that according to forecasts, the VinFast electric motorcycle factory will go into operation from March 2026. Therefore, the Company currently needs to recruit 2,000 workers.
Both the electric car and electric motorbike factory from now until the end of 2026, we need to recruit about 8,000 more workers, on average each month we need to recruit an additional 700 to 1,000 workers," Mr. Nam shared.