Da Nang heats up again over slow-progressing waste plant issue

An Thượng |

Two large waste treatment plant projects in Da Nang have been delayed for many years, causing frustration and affecting the environment and development.

At the question-and-answer session on December 13 of the Da Nang City People's Council meeting at the end of 2024, the issue of slow progress in the construction of two large waste treatment plants once again became the focus of attention of voters and residents.

Director of the Department of Natural Resources and Environment Pham Nam Son said that the 650-ton/day waste treatment plant project has 9 implementation contents, of which only 3 have been completed. The remaining contents such as environmental impact assessment, design documents, and fire prevention and fighting are all in the process of completing procedures. The 1,000-ton/day plant project still has many problems in the appraisal of the feasibility study report, and is expected to be implemented by the third quarter of 2026.

In fact, these two projects have lasted for many years, through many terms, but have not been completed. The 650-ton plant started in 2010, and the 1,000-ton plant in 2017, but so far it is still only on paper. This situation not only makes it difficult to treat waste but also has a negative impact on the environment, as well as the city's goal of developing renewable energy.

The 650-ton factory project was granted the third adjustment certificate by the Department of Planning and Investment in 2023. The Department of Natural Resources and Environment has repeatedly sent official dispatches urging Vietnam Environment Corporation to speed up the progress. Although the investor is submitting an application for adjustment of the investment certificate, this application is still not consistent with the approval of the 1/500 detailed planning. This leads to continued editing, prolonging the implementation time.

According to the direction of the People's Committee of Da Nang City, the investor must urgently complete the documents, start construction in the first quarter of 2025, and commit to completing and putting into use in the third quarter of 2026.

For the 1,000-ton factory project, the City People's Committee has decided to implement it under the public-private partnership (PPP) model. However, the project encountered many difficulties during the appraisal of the feasibility study report. The appraisal team pointed out many unsatisfactory contents such as inappropriate area scale and total investment, and the proposed technology did not meet current standards.

The city has directed relevant agencies to assign specific tasks and progress to promptly resolve existing problems, ensuring that the project can be implemented in the third quarter of 2026.

The delay in the progress of the two waste treatment plant projects has caused many consequences. Waste collection and treatment in the area has encountered many difficulties, causing environmental pollution and affecting the quality of life of the people. At the same time, the policy of creating renewable energy from waste cannot be implemented, slowing down the sustainable socio-economic development of the city.

An Thượng
TIN LIÊN QUAN

Da Nang is still concerned about the shortage of medicine and medical supplies

|

The shortage of medicine and medical supplies in Da Nang continued to be a hot issue at the question-and-answer session on the morning of December 13, the People's Council meeting at the end of 2024.

Da Nang improves the efficiency of the People's Council in the urban government model

|

The People's Council of Da Nang City will improve the quality and efficiency of its operations in the context of implementing the urban government model from 2025.

Da Nang finds it difficult to meet the target on traffic land density

|

Some indicators of the Urban Development Program of Da Nang are difficult to supplement, typically indicators on traffic land density and traffic road density.

Da Nang needs to simplify procedures to facilitate investors

|

Mr. Nguyen Van Quang, Secretary of the Da Nang City Party Committee, proposed that the City People's Council focus on research and discussion to have policies suitable to local realities.

A series of dams in Dak Nong have run out of water during the dry season

|

Dak Nong - Up to this point, there are about 13 lakes and dams in the province that have run out of water; about 30 other lakes and dams have less than 30% of their capacity.

Open a tour to see art and party in 3 caves in Ha Long Bay

|

Quang Ninh - One of the most anticipated tourism products in 2025 is a light party and watching art performances at 3 famous caves in Ha Long Bay.

The story of the multi-heritage - Savior couple of Hai Phong villagers

|

Hai Phong - For local people, the two banyan trees in Don Rieng Temple (Duong Kinh, Hai Phong) are like a "savior", helping villagers overcome the big storm in 1955.

Strong earthquake in Tonga just a few days after Myanmar earthquake

|

A 7.1-magnitude earthquake near Tonga prompted an initial Tsunami warning but was later lifted.

Da Nang is still concerned about the shortage of medicine and medical supplies

An Thượng |

The shortage of medicine and medical supplies in Da Nang continued to be a hot issue at the question-and-answer session on the morning of December 13, the People's Council meeting at the end of 2024.

Da Nang improves the efficiency of the People's Council in the urban government model

An Thượng |

The People's Council of Da Nang City will improve the quality and efficiency of its operations in the context of implementing the urban government model from 2025.

Da Nang finds it difficult to meet the target on traffic land density

Nguyễn Linh |

Some indicators of the Urban Development Program of Da Nang are difficult to supplement, typically indicators on traffic land density and traffic road density.

Da Nang needs to simplify procedures to facilitate investors

Nguyễn Linh |

Mr. Nguyen Van Quang, Secretary of the Da Nang City Party Committee, proposed that the City People's Council focus on research and discussion to have policies suitable to local realities.