Pushing forward the progress of Thuan An sea bridge after many missed appointments

PHÚC ĐẠT - NGUYỄN LUÂN |

Hue is accelerating the completion of the Thuan An estuary overpass, striving to technically open to traffic on April 30th after a period of land congestion.

Site clearance

These days, many households along the National Highway 49A intersection, Thuan An ward are urgently dismantling houses and shops to hand over land to serve the Thuan An estuary overpass project. After receiving compensation money, households have proactively relocated the works, creating conditions for the construction unit to deploy access roads to the bridge. Although the clearance affects livelihoods, people still agree and expect the project to be completed soon, contributing to the development of regional traffic infrastructure.

Mr. Bui Ngoc Chanh - in charge of compensation, site clearance and land fund development of Area 1 Construction Investment Project Management Board, said that so far the ground north of Thuan An bridge has been handed over to Ho Van Do road section. The remaining part is about 200m long, the households have received compensation money and are continuing to hand it over for the construction unit to deploy the access road to the bridge.

The coastal road project through Hue City and Thuan An estuary overpass were started on March 24, 2022. According to the initial plan, the project was completed on March 23, 2025. However, due to many difficulties in site clearance, the project had to be extended to December 31, 2025 and continues to be extended to the present time.

Expected to open to traffic on April 30.

Mr. Nguyen Van Cuong - Deputy Director of the Hue City Traffic Construction Investment Project Management Board - informed that so far the main bridge section (from abutment M1 to abutment M2) has been completed, and the load testing has been completed. The project is expected to be technically opened to traffic on April 30, 2026.

For route 1A on the Hai Duong side, the asphalt concrete paving item has been completed, and the traffic safety system in the Tam Giang bridge intersection area is currently under construction and is expected to be completed before April 25. On route 1B on the Thuan An side to Ho Van Do road, the 1.85/2.15km section has completed the roadbed, and the crushed stone base and asphalt concrete paving of the remaining sections are continuing to be constructed.

The construction volume in April is estimated at about 20 billion VND. The realized value of the entire project to date has reached 1,944 billion VND out of the total contract value of 2,133 billion VND, equivalent to 91.13%. Regarding disbursement, the total capital allocated to the project to date is 2,483.25 billion VND, of which the capital plan for 2026 is 252.5 billion VND.

Accumulated disbursement to date reached 2,230.899 billion VND. In 2026 alone, 94.793 billion VND has been disbursed out of 252 billion VND, reaching 37.54% of the capital plan. Regarding site clearance, there are currently 4 households at the end of the route that have not completed handover. Of which, 3 households are undergoing handover, and the remaining 1 household is expected to be completed before April 30, 2026.

Currently, the route from Tam Giang bridge intersection to Thuan An bridge is about 3.1km long and has basically completed the main items such as asphalt concrete pavement, median strip. We are continuing to complete the drainage system, install signs, paint road markings and are expected to complete as soon as possible. When the items are completed, the route will be eligible for synchronous technical traffic opening" - Mr. Nguyen Van Cuong said.

PHÚC ĐẠT - NGUYỄN LUÂN
RELATED NEWS

Hanoi inspects and repairs river overpasses before the 2026 rainy season

|

Hanoi requests comprehensive inspection and repair of river overpasses such as Thang Long, Nhat Tan, Vinh Tuy... to ensure traffic safety before the 2026 rainy season.

Current shape of overpass pillars at two intersections of Ring Road 1 project

|

Hanoi - The overpass item at the Nguyen Chi Thanh and Lang Ha intersection of the Ring Road 1 project is under construction, and some bridge piers have taken shape.

Hanoi informs about the construction of overpasses and underpasses at key traffic junctions

|

Hanoi - Voters propose that Hanoi continue to invest in building overpasses and underpasses at key intersections, helping to reduce traffic congestion.

Discussing 14 contents, many of which are related to the 14th Vietnam Trade Union Congress

|

Hanoi - In the afternoon of April 24, the Executive Committee of the Vietnam General Confederation of Labour organized a Conference to discuss 14 contents, many of which are related to the 14th Vietnam Trade Union Congress.

People live in hardship beside the hundred-billion road project in Tuyen Quang

|

Tuyen Quang - Many households located within the Son Duong - Tan Trao road project area that have not been relocated are facing dusty weather and muddy rain.

Stocks are heavily sold off, PC1's capitalization evaporates nearly 1,500 billion VND

|

Nearly 23 million PC1 shares were dumped on the floor in a context of no buyers, reflecting great selling pressure from investors.

Salary reform: Transferring 58,061 billion VND from the state budget for implementation

|

The amount transferred from the state budget in 2024 to 2025 is 1,439.178 billion VND, of which the cost of implementing salary reform is 58,061 billion VND.

Hundreds of office meals in rough, damp buildings, without food safety and hygiene certificates

|

Inside the roughly built house, which has not been granted a food safety certificate, an office kitchen is still busy preparing hundreds of meals to deliver to customers.

Hanoi inspects and repairs river overpasses before the 2026 rainy season

Minh Hạnh |

Hanoi requests comprehensive inspection and repair of river overpasses such as Thang Long, Nhat Tan, Vinh Tuy... to ensure traffic safety before the 2026 rainy season.

Current shape of overpass pillars at two intersections of Ring Road 1 project

SÓNG HỮU |

Hanoi - The overpass item at the Nguyen Chi Thanh and Lang Ha intersection of the Ring Road 1 project is under construction, and some bridge piers have taken shape.

Hanoi informs about the construction of overpasses and underpasses at key traffic junctions

Anh Tuấn |

Hanoi - Voters propose that Hanoi continue to invest in building overpasses and underpasses at key intersections, helping to reduce traffic congestion.