Adjusting the scale of the entire Tuyen Quang - Ha Giang expressway to 4 lanes

Phạm Đông |

On September 24, Member of the Party Central Committee, Deputy Prime Minister of the Government Tran Hong Ha chaired a meeting with leaders of Tuyen Quang province and a number of relevant ministries and branches on the proposal to adjust the investment policy of the Tuyen Quang - Ha Giang expressway project (phase 1), the section passing through Tuyen Quang province.

According to the approved investment policy, the Tuyen Quang - Ha Giang expressway project (phase 1), the section through Tuyen Quang province has a length of 77km, of which 69.7km will be newly built with an investment scale of 2 lanes, a design speed of 80km/h, site clearance for 4 lanes, with a total investment of 6,800 billion VND.

Up to now, Tuyen Quang province has cleared 82% of the land with a scale of 4 complete lanes; construction has reached over 12% of the total construction volume of the entire route, ensuring the completion of the project by the end of 2025. However, to promote investment efficiency, connect with important routes serving the economic development of the locality and region, Tuyen Quang province has proposed to adjust the project investment policy for the section passing through Tuyen Quang province. Accordingly, the section from the intersection of National Highway 37 to the intersection of National Highway 3B (22km long) will be expanded to 4 lanes, with a design speed of 100km/h. The remaining section will continue to be implemented according to the approved project documents.

Concluding the meeting, the Deputy Prime Minister of the Government stated that the Prime Minister has given consistent instructions on investing in completed 4-lane expressways to ensure technical safety, economic efficiency, and investment efficiency. In addition, the National Assembly has decided to add additional capital for the Tuyen Quang - Ha Giang expressway project (phase 1) from the increased central budget revenue in 2023. Therefore, adjustments to the investment policy, scale, and design of the project need to be made.

Deputy Prime Minister of the Government assigned the Office of the Government, the Ministry of Planning and Investment to coordinate with Tuyen Quang and Ha Giang provinces, and a number of relevant ministries and branches to advise the Prime Minister to issue a document directing and assigning authority to the two provinces of Tuyen Quang and Ha Giang to decide on adjusting the investment policy and technical design for the project in the direction of adjusting the scale of the entire route to 4 lanes. In which, the construction of the section from the intersection of National Highway 37 to the intersection of National Highway 3B (22km long) passing through Tuyen Quang province must be completed with a scale of 4 lanes. At the same time, technical infrastructure works (residential roads, underpasses, underground works) in the section with 2 lanes must be adjusted in design, synchronized, minimizing demolition and generating large construction volume when expanding to 4 lanes in phase 2.

Regarding ensuring the project's completion schedule, the Deputy Prime Minister of the Government requested Tuyen Quang and Ha Giang provinces to map out the progress; make efforts, reach consensus, and be highly determined; mobilize the entire political system to join forces, work together, and stand side by side with contractors to strive to achieve the set goals.

Phạm Đông
RELATED NEWS

Hanoi traffic on the 28th of Tet is smooth, no congestion

|

Hanoi - Traffic is clear, vehicle density is reduced. Traffic Police (CSGT) strengthen patrols to ensure traffic safety for people.

Small traders travel hundreds of kilometers to bring kumquats and apricot blossoms to the mountain town for Tet sale

|

Dak Lak - Some small traders in the coastal area have traveled hundreds of kilometers to bring ornamental plants to the mountain town to sell during Tet, hoping for a bumper crop.

Year-end feast in Bat Trang ancient village

|

In the last days of the year, the year-end feast in Bat Trang is not only a reunion meal, but also a ritual to thank ancestors, preserving the family tradition through generations.

Russian gas unexpectedly reaches top of largest supply to EU

|

Russian gas still occupies a significant position in the European Union (EU) import structure in 2025.

Green banana prices in Hanoi reach 1 million VND per bunch

|

The price of green bananas on the 28th of Tet recorded a large difference, many bunches of small, large, and beautiful fruits were offered for sale from 500,000 VND to 1 million VND per bunch.

Ca Mau Hospital proposes handling people who livestreamed about deaths 1 day after hospitalization

|

Ca Mau Hospital affirms that there were no professional errors in the 84-year-old patient's death; proposes handling people who livestream on social networks.

The first houses with national grid electricity in Dien Bien

|

Dien Bien - More than 200 households of Mong people in Sang Nhe highland commune have just been able to use the national grid electricity before the Lunar New Year.

Unique horse mascot at Pho Do Pagoda

|

Ha Tinh - This year's Binh Ngo Tet holiday, Pho Do Pagoda (Tran Phu ward) is decorated with the mascot horse with brave wings, full of impressions.

Tuyen Quang - Ha Giang Expressway will be upgraded to 4 lanes

PHẠM ĐÔNG |

The Tuyen Quang - Ha Giang Expressway project (phase 1) will be adjusted to increase the scale of the entire route to 4 lanes.

Situation of injured passengers in highway accident

Duy Tuấn |

Binh Thuan - By noon on September 24, 7 passengers injured in the accident on the Vinh Hao - Phan Thiet highway were being treated at Binh Thuan General Hospital.

Many signs on the highway are hidden, posing a risk to traffic safety

Xuyên Đông |

Voters in Ho Chi Minh City reflect that some highways have signs but their visibility is obstructed.