Adjusting the scale of the entire Tuyen Quang - Ha Giang expressway to 4 lanes

Phạm Đông |

On September 24, Member of the Party Central Committee, Deputy Prime Minister of the Government Tran Hong Ha chaired a meeting with leaders of Tuyen Quang province and a number of relevant ministries and branches on the proposal to adjust the investment policy of the Tuyen Quang - Ha Giang expressway project (phase 1), the section passing through Tuyen Quang province.

According to the approved investment policy, the Tuyen Quang - Ha Giang expressway project (phase 1), the section through Tuyen Quang province has a length of 77km, of which 69.7km will be newly built with an investment scale of 2 lanes, a design speed of 80km/h, site clearance for 4 lanes, with a total investment of 6,800 billion VND.

Up to now, Tuyen Quang province has cleared 82% of the land with a scale of 4 complete lanes; construction has reached over 12% of the total construction volume of the entire route, ensuring the completion of the project by the end of 2025. However, to promote investment efficiency, connect with important routes serving the economic development of the locality and region, Tuyen Quang province has proposed to adjust the project investment policy for the section passing through Tuyen Quang province. Accordingly, the section from the intersection of National Highway 37 to the intersection of National Highway 3B (22km long) will be expanded to 4 lanes, with a design speed of 100km/h. The remaining section will continue to be implemented according to the approved project documents.

Concluding the meeting, the Deputy Prime Minister of the Government stated that the Prime Minister has given consistent instructions on investing in completed 4-lane expressways to ensure technical safety, economic efficiency, and investment efficiency. In addition, the National Assembly has decided to add additional capital for the Tuyen Quang - Ha Giang expressway project (phase 1) from the increased central budget revenue in 2023. Therefore, adjustments to the investment policy, scale, and design of the project need to be made.

Deputy Prime Minister of the Government assigned the Office of the Government, the Ministry of Planning and Investment to coordinate with Tuyen Quang and Ha Giang provinces, and a number of relevant ministries and branches to advise the Prime Minister to issue a document directing and assigning authority to the two provinces of Tuyen Quang and Ha Giang to decide on adjusting the investment policy and technical design for the project in the direction of adjusting the scale of the entire route to 4 lanes. In which, the construction of the section from the intersection of National Highway 37 to the intersection of National Highway 3B (22km long) passing through Tuyen Quang province must be completed with a scale of 4 lanes. At the same time, technical infrastructure works (residential roads, underpasses, underground works) in the section with 2 lanes must be adjusted in design, synchronized, minimizing demolition and generating large construction volume when expanding to 4 lanes in phase 2.

Regarding ensuring the project's completion schedule, the Deputy Prime Minister of the Government requested Tuyen Quang and Ha Giang provinces to map out the progress; make efforts, reach consensus, and be highly determined; mobilize the entire political system to join forces, work together, and stand side by side with contractors to strive to achieve the set goals.

Phạm Đông
RELATED NEWS

U19 Vietnam futsal team loses Southeast Asian semi-final match

|

On the afternoon of December 27, in Thailand, U19 Vietnam futsal suffered a 3-7 defeat to U19 Indonesia futsal in the semi-finals of the 2025 Southeast Asian U19 Futsal Championship.

Identities of 18 casualties in the overturned truck carrying a charity delegation in Lao Cai

|

Lao Cai - Functional agencies have identified the identities and health status of the victims in the overturned truck carrying the charity delegation.

Female workers contribute to beautifying Da Lat to attend the Patriotic Emulation Congress

|

Lam Dong - Ms. Trinh Thi Phung - Da Lat Urban Services Joint Stock Company was honored to represent more than 92,000 workers at the National Patriotic Emulation Congress.

Estimated number of Ukrainian soldiers leaving the army in 2025

|

The number of Ukrainian soldiers defecting in 2025 is said to account for 1/4 of the country's total army.

Ba Ngan bridge opens to motorbikes, reconnecting the bridge to live on for Da Nang workers

|

Da Nang - Ba Ngan bridge (Duy Phuoc bridge) has officially allowed motorbike traffic after a period of lightning-fast construction of an emergency steel girder span.

Controversy after the Vietnam Golden Ball Gala 2025

|

After the Gala night of the 2025 Vietnam Golden Ball award ceremony, controversy about the titles arose.

Silver prices increase, buyers are surprised by high profits

|

Silver prices on December 27 surged to nearly the threshold of 82 million VND/kg. Many investors expressed surprise at the profitability from this precious metal.

Principal will proactively arrange the Lunar New Year holiday schedule for students in Ho Chi Minh City

|

Ho Chi Minh City - Principals of schools in Ho Chi Minh City are proactive in arranging the 2026 Binh Ngo Lunar New Year holiday schedule for students according to the school year plan.

Tuyen Quang - Ha Giang Expressway will be upgraded to 4 lanes

PHẠM ĐÔNG |

The Tuyen Quang - Ha Giang Expressway project (phase 1) will be adjusted to increase the scale of the entire route to 4 lanes.

Situation of injured passengers in highway accident

Duy Tuấn |

Binh Thuan - By noon on September 24, 7 passengers injured in the accident on the Vinh Hao - Phan Thiet highway were being treated at Binh Thuan General Hospital.

Many signs on the highway are hidden, posing a risk to traffic safety

Xuyên Đông |

Voters in Ho Chi Minh City reflect that some highways have signs but their visibility is obstructed.