National Highway 21B expansion project cannot be completed due to site clearance problems

Anh Tuấn |

Hanoi - Thanh Oai Commune People's Committee said that the National Highway 21B expansion project still has some long sections that cannot be completed due to site clearance problems.

Site clearance for National Highway 21B upgrade and expansion project: Government commitment, people agree

According to Thanh Oai Commune People's Committee, the project to upgrade and expand National Highway 21B from the beginning of provincial road 427 to Kim Bai town is invested by Thanh Oai Commune People's Committee, with a total investment of about 345.5 billion VND, implementation time period 2021-2026.

To date, the construction volume has reached about 82%, but there are still some sections about 520m long that cannot be completed due to problems in site clearance (GPMB).

In which, the section passing through Ba Hang Mai area, My Thuong village currently has 94 households related to land recovery work. The land plots here have complex origins of use, existing from the time of Ha Tay province (old); most are agricultural land encroached upon for a long time, some cases are related to land for population expansion according to Decision No. 57 of Ha Tay province, assigned not in accordance with authority and have not been resolved definitively regarding rights.

Faced with difficulties and obstacles in site clearance work, immediately after the local government at two levels went into operation, the Party Committee - Thanh Oai Commune People's Committee urgently surveyed the reality, issued guiding documents, and implemented many synchronous solutions with the spirit of "doing it immediately, quickly, correctly, effectively and to the end", and at the same time thoroughly grasped the viewpoint of "putting people at the center of all policies".

To create consensus among the people, the Commune People's Committee has made 3 specific commitments: First, supporting funding for dismantling works and assets attached to recovered land; for cases where the recovered area affects beams and columns, the Infrastructure Investment Project Management Board and the construction unit will develop technical plans to ensure structural safety of works and stabilize people's lives.

Second, create conditions for households in need to renovate, repair, and embellish their houses; however, do not allow new construction, expansion or illegal expansion.

Third, accompanying people in petitioning the City to consider and definitively resolve existing issues related to land allocated under Decision No. 57 of Ha Tay province previously.

Previously, on April 20 and 21, 2026, the Commune People's Committee established 3 propaganda and mobilization groups, clearly assigned tasks, directly met and dialogued with each household subject to land acquisition (phase 1), and determined the origin of the land;

At the same time, publicly post the draft plan and cost estimate for compensation and support for site clearance. Through dialogue, working groups promptly explained policies, removed obstacles right from the grassroots level, and listened to and grasped the legitimate thoughts and aspirations of the people.

Giải phóng mặt bằng dự án nâng cấp, mở rộng Quốc lộ 21B là vấn đề được chính quyền thực hiện quyết liệt trong thời gian qua. UBND xã Thanh Oai
Site clearance for the project to upgrade and expand National Highway 21B is an issue that the government has implemented drastically in the past time. Thanh Oai Commune People's Committee

Thanks to the synchronous implementation of solutions and promoting the effectiveness of mass mobilization work, up to now, 54 households in the Ba Hang Mai area have voluntarily signed minutes of handover of land to serve project construction.

Currently, there are still 40 households; specialized agencies of the commune are urgently confirming the origin of the land, completing the draft plan and estimate of compensation and GPMB support costs; and at the same time continuing to strengthen propaganda and mobilize the remaining households to sign handover minutes before April 30, 2026.

In addition, specialized agencies of the commune coordinate with the construction unit to develop a detailed plan for dismantling and clearing for households that have handed over the site; organize the relocation and reception of the site from May 1 to May 10, 2026. Strive to complete the handover of the entire site in June 2026 according to the City's direction.

The project to upgrade and expand National Highway 21B includes two sections: from the beginning of provincial road 427 to Kim Bai town and from Kim Bai town to the Vác intersection (now Thanh Oai commune). After completion, the road will be expanded with a cross-section of 35m, including 6 lanes, contributing to completing traffic infrastructure, improving transport capacity, and reducing traffic pressure on the axis connecting the southern communes of the Capital.

Accelerating the progress of site clearance and completing the project is not only meaningful in terms of infrastructure but also creates an important driving force to promote socio-economic development, gradually improving the quality of life of people in the area.

Anh Tuấn
RELATED NEWS

Ho Chi Minh City establishes a new Compensation and Site Clearance Board to handle large projects

|

Ho Chi Minh City pilots the reorganization of the City-level Compensation and Site Clearance Board to improve the efficiency of implementing large-scale projects.

Cau Giay accelerates site clearance, Ring Road 2.5 accelerates progress

|

Hanoi - Cau Giay Ward promotes site clearance, contributing to speeding up the 2.5 Ring Road project through the area.

Ready for the Launching Ceremony of Workers' Month and Action Month on Occupational Safety and Health 2026

|

Quang Ninh - Preparations for the Launching Ceremony of Workers' Month and Action Month on Occupational Safety and Health in 2026 on the morning of April 24 have been basically completed.

Ho Chi Minh City Department of Culture and Sports intervenes in the case of B Ray causing controversy due to offensive rap lyrics

|

The Ho Chi Minh City Department of Culture and Sports said that it has grasped the reflected information and is coordinating with relevant agencies to consider the case of rapper B Ray showing offensive rap lyrics.

Hanoi Chairman proposes 3 solutions to soon bring the revised Capital Law into life

|

Chairman of Hanoi People's Committee Vu Dai Thang affirmed that the city will proactively and synchronously implement many solutions to soon bring the revised Capital Law into life.

National Assembly finalizes birth certificates, marriage certificates must be signed by the Chairman of the Commune People's Committee

|

The Law on Civil Status (amended) stipulates that the Chairman of the Commune-level People's Committee must directly sign birth certificates and marriage certificates.

Lao Cai gold - the first gold enterprise to list on the stock exchange fluctuates due to debt

|

Losing the right to exploit Minh Luong gold mine, accumulated losses exceeding charter capital, Lao Cai Gold Company is facing the most difficult period since listing on the stock exchange.

Dismantling construction that collapsed people's houses in Da Nang, many houses are cracked

|

A project on Tran Quy Cap street (Da Nang) during dismantling caused the collapse of a house and damage to many adjacent houses.

Ho Chi Minh City establishes a new Compensation and Site Clearance Board to handle large projects

MINH QUÂN |

Ho Chi Minh City pilots the reorganization of the City-level Compensation and Site Clearance Board to improve the efficiency of implementing large-scale projects.

Cau Giay accelerates site clearance, Ring Road 2.5 accelerates progress

Hữu Vũ |

Hanoi - Cau Giay Ward promotes site clearance, contributing to speeding up the 2.5 Ring Road project through the area.

Hà Nội đối thoại tháo gỡ vướng mắc giải phóng mặt bằng cầu Trần Hưng Đạo

Minh Hạnh |

Hà Nội tổ chức đối thoại với người dân phường Bồ Đề nhằm tháo gỡ vướng mắc giải phóng mặt bằng, đẩy nhanh tiến độ dự án cầu Trần Hưng Đạo.