The National Highway upgrade project worth over VND1,400 billion is sluggish, at risk of being behind schedule in Lam Dong

LAM HỒNG - BẢO LÂM |

Lam Dong - The National Highway 28B renovation and upgrade project is expected to be completed by the end of 2025, but the construction progress is slow, facing the risk of delays.

The project to renovate and upgrade National Highway 28B is about 68km long, with a total investment of about VND1,400 billion.The project is represented by Project Management Board 5, Ministry of Construction.

The project started in April 2024, expected to be completed and put into use by the end of 2025.This traffic project connects National Highway 1A, Vinh Hao - Phan Thiet Expressway with National Highway 20, a route connecting the plateau with the entire sea of Lam Dong province.

However, the construction process has been slow in the past, with the risk of being behind schedule.

Du an duoc xem la cung duong noi cao nguyen voi vung bien ca cua tinh Lam Dong. Anh: Lam Hong
The project is considered a route connecting the plateau with the entire sea area of Lam Dong province. Photo: Lam Hong

Regarding this issue, Lam Dong Department of Construction said that the authorities have handed over to the investor 62km/68km of site, the remaining 6km has not been handed over.The construction unit has paved 33km of road with asphalt concrete, and dozens of other kilometers have been granted gravel.

According to Lam Dong Department of Construction, the reason for the uncertain progress of the project is that the construction unit has not fully arranged machinery, equipment, and human resources.

Cong truong thi cong ngon ngang. Anh: Lam Hong
The construction site is littered with machinery and equipment. Photo: Lam Hong
Cong truong thi cong ngon ngang, co nguy co cham tien do. Anh: Lam Hong
The project is at risk of being behind schedule. Photo: Lam Hong

According to the records, the construction unit carried out a series of items along the entire length of the route. However, most of the project items are unfinished, the road surface is bumpy, the rocks and soil are messy and dusty.

Phan ke thep o taluy duong cong trinh nam ngon ngang ben duong. Anh: Lam Hong
The steel embankment on the positive slope of the project is lying around the road. Photo: Lam Hong
Phuong tien giao thong di chuyen trong bui bam. Anh: Lam Hong
Vehicles move in the dust. Photo: Lam Hong

Currently, 6 locations on the project route are designed for overpass construction, but the contractor has not yet ensured the progress. This has seriously affected the completion of the road surface.

Mr. Tran Van Loc (Phan Son commune, Lam Dong) has a house in the site clearance area of the National Highway 28B Upgrade and Renovation Project, and has allocated land to the authorities to implement the project. The family really hopes that the construction unit will soon complete the project to ensure traffic, stabilize life and production.

Nhieu vi tri tren tuyen duong dang trong qua trinh thi cong. Anh: Lam Hong
Many locations on the route are under construction. Photo: Lam Hong
Thoi gian thi cong keo dai anh huong den cuoc song cua nguoi dan dia phuong va cac phuong tien giao thong tren duong. Anh: Lam Hong
The prolonged construction time affects the lives of local people and vehicles on the road. Photo: Lam Hong

According to Mr. Vo Ngoc Danh (ta Hine commune, Lam Dong), National Highway 28B is a vital traffic route but the construction unit is implementing it too slowly. During the rainy season, the road surface is covered with mud, and the embankment is dug up and unfinished, which is very dangerous. On sunny days, the dust carried up, making travel on the road extremely difficult.

At a recent meeting, Vice Chairman of Lam Dong Provincial People's Committee Vo Ngoc Hiep requested units to resolve difficulties in site clearance for the remaining area in September. At the same time, investors and contractors are forced to overcome limitations and soon complete the constructed sections to put them into operation, avoiding affecting people's lives.

LAM HỒNG - BẢO LÂM
RELATED NEWS

Temporarily closing Vinh Hao - Phan Thiet expressway sections to construct camera installation prices

|

Lam Dong - The sections on the Vinh Hao - Phan Thiet expressway are temporarily closed in rotation to construct the gate to install traffic cameras.

After 6 months of construction, the trillion-dong project in Can Tho is still at a standstill

|

Can Tho - The project to renovate 5 key intersections in Can Tho City after 6 months of implementation is being delayed due to land clearance problems.

Resolutely control air pollution, restore clean sky

|

Directive 20/CT-TTg of the Prime Minister identifies urgent tasks and drastic solutions to prevent environmental pollution, especially air pollution.

Students riding motorbikes over 50cc are still allowed to collect tickets right in school

|

Hanoi - Although they are not old enough to drive vehicles over 50cc, many students still use them and park them in their school's parking lot.

About 400 billion VND will be spent on union officials with contract benefits due to organizational restructuring

|

Preliminary calculations show that about 400 billion VND will be spent from union finances on 425 union officials working under labor contracts affected by the organizational arrangement.

Proposal for employees to work no more than 8 hours/day, with at least 1 day off per week

|

The Ministry of Home Affairs proposes that workers' working hours must not exceed 8 hours/day, with at least 1 day off per week (24 consecutive hours).

"General" orders to beat coffee shop staff to apologize, but refused, invited to go out

|

On the morning of September 19, Nguyen Van Thien - the "general" who ordered the beating of a coffee shop employee in Hanoi - went to the restaurant to apologize but was invited by the restaurant owner to go out.

Temporarily closing Vinh Hao - Phan Thiet expressway sections to construct camera installation prices

Duy Tuấn |

Lam Dong - The sections on the Vinh Hao - Phan Thiet expressway are temporarily closed in rotation to construct the gate to install traffic cameras.

After 6 months of construction, the trillion-dong project in Can Tho is still at a standstill

Tạ Quang |

Can Tho - The project to renovate 5 key intersections in Can Tho City after 6 months of implementation is being delayed due to land clearance problems.

Land clearance problems, National Highway 32C Upgrade Project has been under construction for 13 years and has not been completed

Bảo Nguyên - Văn Đức |

Lao Cai - The National Highway 32C upgrade project started in 2012 but has not yet completed site clearance.