Suoi Cai project in Ho Chi Minh City is about to complete nearly the first 6 km

ĐÌNH TRỌNG |

Ho Chi Minh City - The Suoi Cai project passing through 3 wards in Ho Chi Minh City is accelerating construction, nearly completing the first 6 km.

On March 29, contractors are accelerating the construction progress of the Suoi Cai dredging and reinforcement project from Tho Ut bridge to Dong Nai river (abbreviated as the Suoi Cai project, section through Tan Uyen city, former Binh Duong province).

After more than 2 years of construction, the concreted shape of Suoi Cai has been formed. The first section from Tho Ut bridge to Ben San bridge, nearly 6 km long, is about to be completed.

Under the bed of Suoi Cai, stone is paved and concrete is poured. Both banks are also built with solid concrete slabs. Above, the railing is fenced with solid iron and steel. Notably, along both sides are built 2 roads about 10 m wide, opening up a new urban development space for the area that was originally rice fields and swamps.

According to the Ho Chi Minh City Urban Infrastructure Project Management Board (the unit assigned as the investor), the section from Tho Ut bridge to Ben San bridge has 2 construction packages. It is expected that these 2 packages will be completed as early as April 30th.

Khoảng 5km dự án Suối Cái đã được bê tông hóa. Ảnh: Đình Trọng
Nearly 6km of Suoi Cai project has been concreted. Photo: Dinh Trong

11 other packages are being urgently constructed, including 3 packages for relocating power grids. These packages are also being accelerated. Currently, the construction progress of the packages has reached from 20% to 98%. It is expected that the packages will be completed by the end of December 2026.

It is known that the Suoi Cai dredging and reinforcement project from Tho Ut bridge to Dong Nai river has a total investment of more than 5.892 billion VND. The project is about 19km long, passing through Binh Duong ward, Tan Hiep ward and Tan Khanh ward, invested by the Project Management Board of the Department of Agriculture and Rural Development of Binh Duong province (now the Ho Chi Minh City Urban Infrastructure Project Management Board).

The project's objective is to drain rainwater and treated wastewater for a basin area of 22,503ha. Contributing to environmental improvement, urban embellishment, and creating a premise for building 37.8 km of regional-level traffic roads.

Đoạn kênh đầu tiên được xây dựng hoàn thành. Ảnh: Đình Trọng
The first canal section is completed. Photo: Dinh Trong
Suối Cái có rào chắn bằng sắp thép. Ảnh: Đình Trọng
Cai stream has iron and steel barriers. Photo: Dinh Trong
Sau 2 năm thi công những đoạn đầu tiên của dự án đã hình thành. Ảnh: Đình Trọng
After 2 years of construction, the first sections of the project have been formed. Photo: Dinh Trong
Cây cầu mới xây đoạn qua phường Bình Dương đã cho xe lưu thông. Ảnh: Đình Trọng
The newly built bridge section passing through Binh Duong ward has allowed traffic. Photo: Dinh Trong
Dự án sẽ tạo tiền đề để phát triển đô thị và giao thông dọc Suối Cái. Ảnh: Đình Trọng
The project will create a premise for urban development and transportation along Suoi Cai. Photo: Dinh Trong
Dự kiến cuối năm nay sẽ hoàn thành xây dựng dự án Suối Cái. Ảnh: Đình Trọng
It is expected that the entire Suoi Cai project will be completed by the end of this year. Photo: Dinh Trong

Unseasonal rain affects project progress

According to records, the project's construction site is being deployed in the Suoi Cai riverbed area. This place receives rainwater in a large area in Binh Duong ward. This year, many consecutive unseasonal rains affected the project's progress. The rains followed by heavy water poured down on the construction site, causing erosion of unfinished construction items. Units are both constructing and striving to clear the flow, preventing damage caused by rain and floods to the project.

ĐÌNH TRỌNG
RELATED NEWS

3 projects to rescue traffic jams at the gateway of Ho Chi Minh City have been done for more than 10 years without being completed

|

Ho Chi Minh City - 3 projects to expand Hanoi Highway - National Highway 1, Luong Dinh Cua street and Pham Van Bach street have been implemented for more than 10 years but have not been completed due to site clearance issues.

Ring Road 3 HCMC elevated section asphalt paved seamlessly, racing for traffic opening progress 30. 4

|

Many elevated sections of Ring Road 3 in Ho Chi Minh City have been beautifully asphalted, and contractors are focusing their efforts on completing the final part to meet the traffic opening milestone on April 30th.

HCMC Chairman tightens progress for 3 metro lines connecting Long Thanh airport

|

HCMC - Metro lines Ben Thanh - Tham Luong, Ben Thanh - Thu Thiem and Thu Thiem - Long Thanh are required to speed up progress to be completed by 2030.

Trailer truck's truck bed burst, causing mud and soil to spill onto Ring Road 3

|

Hanoi - A tractor-trailer traveling on Ring Road 3 suddenly burst its truck bed, causing mud and soil to spill onto the road surface.

After Hormuz, another oil throat at risk of paralysis when Houthi fights

|

When Hormuz is almost paralyzed, all eyes are now on another vital oil transport route, the Bab el-Mandeb Strait, as the Houthi begins to fight.

streamlining the internal organization of central ministries and agencies in 2026

|

The internal organizations of ministries, central agencies and departments and branches in localities will continue to be reviewed and streamlined in the coming time.

Heavy rain in Hanoi, trees uprooted, crushing motorcyclists

|

Hanoi - Heavy rain accompanied by strong winds caused trees on To Hieu street to be uprooted, crushing a motorcyclist who had to be hospitalized for emergency treatment.

Food poisoning suspected from bread, 32 people hospitalized

|

Dak Lak - After eating bread, dozens of local people had to be hospitalized for treatment, suspected of food poisoning.

3 projects to rescue traffic jams at the gateway of Ho Chi Minh City have been done for more than 10 years without being completed

MINH QUÂN |

Ho Chi Minh City - 3 projects to expand Hanoi Highway - National Highway 1, Luong Dinh Cua street and Pham Van Bach street have been implemented for more than 10 years but have not been completed due to site clearance issues.

Ring Road 3 HCMC elevated section asphalt paved seamlessly, racing for traffic opening progress 30. 4

Anh Tú |

Many elevated sections of Ring Road 3 in Ho Chi Minh City have been beautifully asphalted, and contractors are focusing their efforts on completing the final part to meet the traffic opening milestone on April 30th.

HCMC Chairman tightens progress for 3 metro lines connecting Long Thanh airport

MINH QUÂN |

HCMC - Metro lines Ben Thanh - Tham Luong, Ben Thanh - Thu Thiem and Thu Thiem - Long Thanh are required to speed up progress to be completed by 2030.