Establishing barriers to relocate technical infrastructure for Metro No. 2, vehicles have difficulty circulating

Tâm Bảo |

HCMC - Metro Line 2 project is relocating technical infrastructure at Dan Chu roundabout, causing barriers in this area and making it difficult for vehicles to circulate.

Cac phuong tien di chuyen cham khi luu thong qua khu vuc dung rao chan dang thi cong. Anh: Thai Bao
Vehicles move slowly when traveling through the area where the fence is under construction. Photo: Thai Bao

According to records, the traffic flow through Dan Chu roundabout (HCMC) is being affected by barriers serving the package to relocate technical infrastructure of Metro No. 2 project, from CC1 station (Ben Thanh) to underground station S6. The main task of the package is to straighten and relocate power cables, telecommunication cables, water pipes... within the scope of 6 underground stations.

Currently, the relocation of technical infrastructure at 4 underground stations including Hoa Hung, Le Thi Rieng, Pham Van Hai and Tao Dan has been basically completed, the contractor has poured concrete to restore the site. Only Dan Chu Station ( Station S3) and the CC1 section near Ben Thanh Station are continuing construction. It is expected that the contractor will return the site at Dan Chu station in mid-October.

Viec di doi ha tang ky thuat phu vu cho du an Metro so 2 dang duoc day manh. Anh: Thai Bao
The relocation of technical infrastructure to serve Metro Line 2 project at Dan Chu roundabout is being accelerated. Photo: Thai Bao

Station S3 is located right at the Dan Chu roundabout area - an important intersection, often congested during rush hour - so the relocation of underground pipelines is more difficult. Workers must both maintain the construction and ensure that people's travel is not interrupted.

Du kien den giua thang 10 se hoan tra mat bang. Anh: Thai Bao
It is expected that the site will be returned by mid-October. Photo: Thai Bao

Mr. Phan Cong Bang, Head of the Ho Chi Minh City Urban Railway Management Board, said that up to now, the site clearance work for Metro Line 2 has been 100% completed, with all 585/585 cases having handed over the site. Thanks to that, contractors are simultaneously implementing the relocation of technical infrastructure at many key locations.

As of mid-July 2025, the volume of infrastructure relocation for the entire route has reached about 60%, with an implementation value of nearly 600 billion VND. Mr. Bang emphasized that some areas such as Dan Chu Station, Ba Queo Station, Pham Van Bach Station are complex points, requiring synchronous coordination with many units such as electricity, water supply and drainage, telecommunications.

To keep up with the progress, the Management Board will hold an operating meeting and update the construction progress every night. Some items are constructed at night to reduce traffic impact and shorten time. At construction sites, traffic police are deployed to support traffic flow.

According to the plan, the relocation of infrastructure will be completed around December 2025, creating conditions for the simultaneous start of construction of the main packages in 2026. "We have identified this as a key foundation phase of the project. Any problems beyond the authority are immediately reported for handling, not to affect the overall progress of the entire route", Mr. Phan Cong Bang emphasized.

Tâm Bảo
RELATED NEWS

Accelerating the relocation of technical infrastructure overnight to serve Metro Line 2 project

|

HCMC - Head of the HCMC Urban Railway Management Board was present at the construction site of Metro Line 2 project to inspect and urge the relocation of the technical infrastructure of the route.

Metro No. 2 has reached 60% of the infrastructure relocation progress, and will start construction of bidding packages in 2026

|

HCMC - Metro Line 2 has completed 100% of the site, infrastructure relocation has reached 60%, and is expected to start construction of all major packages in 2026.

HCMC is about to start construction of Metro Line 2, expected to be operational by 2030

|

Ho Chi Minh City is preparing to start construction of Metro Line 2, more than 11 km long, after completing 100% of site clearance work, expected to be operational by the end of 2030.

It is expected to submit to the Politburo a project to reorganize and streamline mass associations before August 31

|

On the afternoon of July 29, the Central Committee of the Vietnam Fatherland Front held a conference to give comments on the project to reorganize and streamline mass associations assigned by the Party and the State.

Upgrading the stock market, expanding capital mobilization channels for the economy

|

In order to improve quality and open up the ability to attract large-scale, stable and long-term international investment capital flows for the Vietnamese stock market, Lao Dong Newspaper in coordination with the Ministry of Finance organized a seminar on "Upgrading the stock market, expanding capital mobilization channels for the economy".

Khanh Hoa requests clarification of the responsibility for requesting the arrangement of a public housing at Bao Dai mansion

|

Khanh Hoa - The authorities have the results of the inspection and handling of the case, proposing to temporarily arrange accommodation for officials at the Cau Da villa relic site - where Bao Dai tower is located.

High sales caused stocks to lose the 1,500-point mark

|

Many investors have fallen into a state of anxiety and participated in strong selling when the stock market fell sharply to below the threshold of 1,500 points.

Thailand says Cambodia violates ceasefire agreement

|

On the afternoon of July 29, Thailand said Cambodia had not yet stopped fire and Bangkok had sent its protest to the presidents of ASEAN, China and the US.

Accelerating the relocation of technical infrastructure overnight to serve Metro Line 2 project

ÁNH TÂM |

HCMC - Head of the HCMC Urban Railway Management Board was present at the construction site of Metro Line 2 project to inspect and urge the relocation of the technical infrastructure of the route.

Metro No. 2 has reached 60% of the infrastructure relocation progress, and will start construction of bidding packages in 2026

Anh Tú |

HCMC - Metro Line 2 has completed 100% of the site, infrastructure relocation has reached 60%, and is expected to start construction of all major packages in 2026.

HCMC is about to start construction of Metro Line 2, expected to be operational by 2030

Nhóm PV |

Ho Chi Minh City is preparing to start construction of Metro Line 2, more than 11 km long, after completing 100% of site clearance work, expected to be operational by the end of 2030.