Public investment disbursement in Khanh Hoa lower than planned, still 34 projects facing site clearance problems

Hữu Long |

Khanh Hoa - At the question-and-answer session of the People's Council, many delegates expressed concern about the disbursement progress of public investment capital not reaching the set target.

On the morning of July 9, the 2nd session of the Khanh Hoa Provincial People's Council continued the working program with a question-and-answer session. The content of disbursement of public investment capital was of concern to many delegates when the implementation progress had not yet reached the set target.

Delegate Nguyen Thanh Hai said that the disbursement rate of public investment capital of the province is still low compared to the plan.

In addition, site clearance - one of the major "bottlenecks" - has not been effectively removed.

Đại biểu Nguyễn Thanh Hải chất vấn. Ảnh: Hữu Long
Delegate Nguyen Thanh Hai questioned. Photo: Huu Long

The delegate requested the Director of the Department of Finance to clarify the causes and propose breakthrough solutions to accelerate disbursement progress in the coming time.

According to the report, to date, the disbursement rate of public investment capital of Khanh Hoa province has reached 41.93% of the plan. This level is higher than the national average but still lower than the province's target.

Answering questions, Mr. Chau Ngo Anh Nhan - Director of the Department of Finance of Khanh Hoa province - admitted that in the first 6 months of the year, the province has not achieved the target of disbursing public investment capital.

According to Mr. Nhan, currently 36/64 communes and wards have a disbursement rate of over 50%. However, there are still 5/64 communes and wards and 4 provincial-level agencies and units with disbursement rates below 20%.

The Director of the Department of Finance said that there are three main groups of reasons leading to slow disbursement progress.

Giám đốc Sở Tài chính tỉnh Khánh Hòa trả lời chất vấn của đại biểu. Ảnh: Hữu Long
Director of Khanh Hoa Provincial Department of Finance answers delegates' questions. Photo: Huu Long

Among them, the biggest is the obstacle in site clearance with 34 affected projects, accounting for about 24% of the public investment capital plan.

The second group of reasons is the lack of raw materials for 3 projects, accounting for about 12% of the capital plan.

The third group is slow investment preparation, concentrated in 14 communes and wards due to investment procedures, affecting about 12% of the capital plan.

Besides objective reasons, Mr. Chau Ngo Anh Nhan also pointed out some subjective reasons such as the role and responsibility of the head in removing difficulties at projects is still limited; the quality of investment preparation work has not met requirements.

According to Mr. Nhan, after implementing the two-level local government model, the capacity of a part of officials in communes and wards has not yet met practical requirements.

He also cited that the Khanh Hoa Provincial Land Fund Development Center is facing difficulties due to lack of human resources.

In addition, the capacity of some consulting units and contractors also affects the project implementation progress.

In which, contractors are affected by price fluctuations and the supply of raw materials in the market.

Regarding solutions, the Director of the Department of Finance said that the province will continue to strengthen monitoring and supervision of project implementation progress; promote the application of technology in site clearance and focus on implementing a 90-day peak period to complete site clearance for key projects.

Leaders of the Department of Finance expect that by the end of the third quarter, Khanh Hoa province will significantly improve the disbursement results of public investment capital.

Hữu Long
RELATED NEWS

Gia Lai identifies factors causing slow disbursement of public investment capital

|

Gia Lai - Despite many obstacles, the province is still in the group of localities with the highest disbursement rate of public investment capital in the country.

Lam Dong breaks through in disbursing public capital investment thanks to management innovation

|

Lam Dong - After more than a month of removing bottlenecks, promoting digital transformation and tightening responsibility, the disbursement rate of public investment capital has made a strong breakthrough.

Vinh Long disburses 2 billion VND to support 40 farming households to develop production

|

Vinh Long - The Farmers' Support Fund disbursed 2 billion VND for 40 households to borrow, along with many outstanding activities of socio-political organizations.

Disciplining former Chief of Office of Thua Thien Hue Provincial Party Committee related to the Provincial Party Committee Guesthouse Project

|

The Standing Committee of Hue City Party Committee disciplined Mr. Luu Duc Hoan with a reprimand for violations in leading and directing the implementation of the Provincial Party Committee Guest House Project.

Police inform about the case of a car driver not giving way to an ambulance in Tuyen Quang

|

Tuyen Quang - Functional agencies determined that the car driver had the act of not giving way to priority vehicles, with a fine of 6 - 8 million VND and 4 points off the driver's license.

Prolonging the term of Deputy Inspector General of the Government with Mr. Le Sy Bay

|

The Prime Minister decided to extend the term of office of Deputy Inspector General of the Government to the time of retirement according to regulations for Mr. Le Sy Bay.

Many people came to Le Thi Rieng Park to burn incense to commemorate heroic martyrs

|

Before the information that martyrs' remains are being gathered at Le Thi Rieng Park, Ho Chi Minh City, many people came to offer incense and express their respect to the spirits of the martyrs.

Gia Lai identifies factors causing slow disbursement of public investment capital

THANH TUẤN |

Gia Lai - Despite many obstacles, the province is still in the group of localities with the highest disbursement rate of public investment capital in the country.

Lam Dong breaks through in disbursing public capital investment thanks to management innovation

Phan Tuấn |

Lam Dong - After more than a month of removing bottlenecks, promoting digital transformation and tightening responsibility, the disbursement rate of public investment capital has made a strong breakthrough.

Vinh Long disburses 2 billion VND to support 40 farming households to develop production

HOÀNG LỘC |

Vinh Long - The Farmers' Support Fund disbursed 2 billion VND for 40 households to borrow, along with many outstanding activities of socio-political organizations.