Removing bottlenecks to help the 6,000 billion VND traffic project in the Northwest reach the finish line

Nhóm PV |

The project to connect the traffic of the Northern mountainous provinces with a total investment of more than 6,000 billion VND, nearly 200 km long, is facing many difficulties in site clearance.

The project to connect the northern mountainous provinces with funding from the Asian Development Bank (ADB) and the Australian Government was approved by the Prime Minister, and started construction in December 2021.

The project consists of 2 routes with a total length of about 200km. Of which, the route connecting Lai Chau with Noi Bai - Lao Cai Expressway is about 147km long; the route connecting Nghia Lo with Noi Bai - Lao Cai Expressway is about 53km long.

Quoc lo 279 noi Lai Chau voi nut giao IC 16 cao toc Noi Bai - Lao Cai. Anh: Dinh Dai
National Highway 279 connects Lai Chau with IC 16 intersection of Noi Bai - Lao Cai Expressway. Photo: Dinh Dai

By the end of November 2025, many locations had been handed over the site, but there were still "bottlenecks" that had not been resolved.

For the Nghia Lo - Noi Bai - Lao Cai route alone, there are still about 63 documents that have not approved the compensation plan. The most complicated cases are cases related to power grid safety corridors, land lacking legal procedures or being affected outside the reclaimed area.

Mr. Do Cao Quyen - Chairman of the People's Committee of Mo Vang Commune, Lao Cai Province - said: "Mo Vang Commune still has 33 pending cases, including one case that must be enforced. We have had many dialogues and mobilized people but the content is beyond our authority, and we really need the support of superiors".

Do vuong mat bang nen Du an khong the hoan thanh vao thang 6.2025 va hien phai gia han den nam 2026. Anh: Dinh Dai
Due to land clearance problems, the project cannot be completed in June 2025 and must now be extended to 2026. Photo: Dinh Dai

Similarly, in Son Luong commune, Lao Cai province, there are still many households that have not handed over the site because the design of the residential branch road is not close to reality.

"We have organized many dialogues to help people understand the content of the adjustment. However, there are still some cases where investors and design consultants need to work directly to agree on a plan" - Mr. Pham Nguyen Binh, Chairman of Son Luong Commune People's Committee, informed.

Nhieu diem sat lo sau bao gay anh huong den qua trinh thi cong. Anh: Dinh Dai
Many landslides after the storm affected the construction process. Photo: Dinh Dai

An issue that people are particularly concerned about is the slow implementation of returned roads, ditches - irrigation culverts and intra-field roads.

In Mo Vang, the drainage system and Khe Sung - Khe Hop ditches have not been rebuilt, causing dozens of hectares of rice to be at risk of water shortage or flooding. People hope that the returned works must go hand in hand with the project progress so as not to affect production.

At the meetings, the authorities continuously requested Project Management Board 2 - Ministry of Construction to provide legal documents related to design adjustments; provide an additional VND34 billion to complete payments in 2025; and at the same time request departments and branches to speed up land appraisal and resettlement support plans, avoiding extending to 2026.

de bu tien do, cac cong nhan cung may moc duoc trien khai tang ca, tang kip. Anh: Dinh Dai
To make up for the progress, workers and machines are deployed to work overtime and increase shifts. Photo: Van Duc

Recently, the Ministry of Construction issued a document requesting Project Management Board 2 to speed up construction, disbursement and handling of backlogs of site clearance. The Ministry of Construction aims to complete construction packages before the Lunar New Year 2026.

For packages with a risk of being slow (XL01, XL03, XL04, XL07, XL10, XL11, Project Management Board 2 must monitor the progress weekly and monthly; if the contractor is slow, it must request immediate repair or consider transferring the volume, even replacing the contractor.

Nguoi dan mong cho duong ket noi giao thong cac tinh mien nui phia Bac som hoan thanh. Anh: Van Duc
People are looking forward to the completion of the traffic connection road for the northern mountainous provinces soon. Photo: Van Duc

For landslides on slopes, it is necessary to adjust and supplement design solutions to solidify; propose specific solutions and solutions to ensure investment efficiency, stabilize the project in the long term but not prolong the progress.

Regarding safety in construction, the Ministry of Construction also assigned the investor to direct the consultant and contractor to arrange full fences and systems to ensure traffic safety during construction, and organize the construction of the traffic safety system (encephalt guardrail, wave-etching corrugated iron) immediately after the asphalt concrete has been paved.

Nhóm PV
RELATED NEWS

More than 30 construction teams are racing for the project to connect traffic to the finish line

|

Regardless of day or night, more than 30 construction teams of the packages are working hard, racing against time for the Northern Mountainous Province Traffic Connection Project to be completed by the end of this year.

Explaining the reason for the delay in the billion-dollar road connecting Lao Cai - Lai Chau

|

Lao Cai - Up to now, the billion-dollar road under the project connecting traffic in the northern mountainous region is still unfinished and not completed.

Road connecting the Northern mountainous provinces is being constructed slowly

|

Yen Bai - Every time it rains, people in Van Chan district suffer and travel on the route connecting the northern mountainous provinces.

Nghe An nearly doubles the assigned social housing target

|

Nghe An - Nghe An province has nearly doubled the assigned targets, becoming a bright spot in the speed of implementing social housing projects.

Gold price update on the morning of November 28: High, investors waiting for the Fed's move

|

Gold price update on the morning of November 28: Steady near the highest level in two weeks. Investors assess the possibility of the Fed cutting interest rates in December.

Removing bottlenecks to help the 6,000 billion VND traffic project in the Northwest reach the finish line

|

The project to connect the traffic of the Northern mountainous provinces with a total investment of more than 6,000 billion VND, nearly 200 km long, is facing many difficulties in site clearance.

Impressive 31.5 km of Ho Chi Minh road through vast rubber gardens

|

HCMC - The 31.5 km long Ho Chi Minh road through Binh Duong province passes through vast rubber gardens, creating a rare landscape.

High waves damage 150m of sea dyke along seafood restaurants in Mui Ne

|

Lam Dong - A section of the sea dyke about 150m long through the area with a large seafood restaurant in Mui Ne was damaged by big waves.

More than 30 construction teams are racing for the project to connect traffic to the finish line

Văn Đức |

Regardless of day or night, more than 30 construction teams of the packages are working hard, racing against time for the Northern Mountainous Province Traffic Connection Project to be completed by the end of this year.

Explaining the reason for the delay in the billion-dollar road connecting Lao Cai - Lai Chau

Nhóm PV |

Lao Cai - Up to now, the billion-dollar road under the project connecting traffic in the northern mountainous region is still unfinished and not completed.

Road connecting the Northern mountainous provinces is being constructed slowly

Nhóm PV |

Yen Bai - Every time it rains, people in Van Chan district suffer and travel on the route connecting the northern mountainous provinces.