The underpass worth nearly 800 billion VND in Hanoi will be completed this year

HỮU CHÁNH |

Hanoi - Kim Dong - Giai Phong underpass is under construction until the railway section. The project's progress has reached 60%, expected to be completed in 2025.

The Kim Dong - Giai Phong underpass construction project (Hoang Mai district, Hanoi) started construction in October 2022. The project has a total investment of 778 billion VND, invested by the Hanoi Traffic Construction Investment Project Management Board.

This is the 5th underpass in the capital built from 2009 to present, after the Kim Lien, Trung Hoa, Thanh Xuan, and Le Van Luong tunnels.

The Kim Dong - Giai Phong underpass has a total tunnel and approach road length of 890m in the direction of Ring Road 2.5, of which the closed tunnel is 140m long and the open tunnel is 320m long. The section through the tunnel has 2 lanes each way, 3.5m wide/lane, the section outside the tunnel has 3 lanes each way, 3.5m wide/lane.

Ham chui phia Dam Hong da co ban hoan thanh. Anh: Huu Chanh
Kim Dong - Giai Phong underpass on the Dam Hong side (Hanoi). Photo: Huu Chanh
Nha thau hien dang thi cong hang muc phia Kim Dong. Anh: Huu Chanh
The contractor is currently constructing the project on the Kim Dong side and the section under the railway. Photo: Huu Chanh

According to Lao Dong in mid-March, at the construction site of the Kim Dong - Giai Phong underpass project, the investor and contractor mobilized many machines and construction workers spread across the entire project.

Mr. Do Duc Hung - an officer of Project Department 5, Hanoi Traffic Construction Investment Project Management Board said that the overall progress of the Kim Dong underpass project has reached about 60%.

The tunnel section on the Dam Hong side has basically completed the main items. The site here is currently stuck with 6 organizations and 4 households in the area of Giap Bat and Thinh Liet wards.

The opening tunnel on the Kim Dong side has also been revealed. Currently, the contractor is focusing on constructing 3 closed tunnel sections across 6 existing railway lines.

"Up to now, contractors have completed 37/40 bored piles to prepare for the construction of the railway rack system, ensuring that the train is still operating safely when digging the tunnel below" - Mr. Hung said.

s
Kim Dong underpass has reached about 60% of the workload after nearly 2.5 years of construction. Photo: Huu Chanh
x
The biggest difficulty is that the construction of the railway safety system is only allowed to be constructed 4 hours/day and there is no fixed time. Photo: Huu Chanh
“Diem gang” cua du an la thi cong 3 dot ham kin qua 6 line duong sat hien huu. Anh: Huu Chanh
The "goal" of the project is the construction of 3 closed tunnels across 6 existing railway lines. Photo: Huu Chanh

According to the contractor's calculation, it will take about 3 months to complete the construction of the railway safety value system. The biggest difficulty is that the construction of this railway safety system is only allowed to be constructed 4 hours/day and there is no fixed time.

"With the tunnel construction on the Kim Dong side and on Giai Phong Street, we are confident about the progress. With 3 tunnels on the Dam Hong side digging tunnels under 6 existing railway lines while the upper part still has to ensure safety for trains, we are not sure about the progress" - the project contractor representative shared.

Du an moi hoan thanh 37/40 coc khoan nhoi de chuan bi thi cong he thong gia do duong sat... Anh: Huu Chanh
The project has completed 37/40 bored piles to prepare for the construction of the railway rack system... Photo: Huu Chanh
Mat khoang 3 thang moi thi cong xong phan he thong gia do an toan cho duong sat.
It took about 3 months to complete the construction of the railway safety value system. Photo: Huu Chanh
Cong nhan lam viec tren cong truong du an. Anh: Huu Chanh
Workers working at the project site. Photo: Huu Chanh

According to this person, in the coming time, the contractor will complete the open tunnel sections on Kim Dong Street, rebuild the road on both sides of the tunnel until the entire layer of asphalt concrete is paved before April 30, 2025; complete the closed tunnel sections; retaining walls and embankments on the Red Dam side.

The route and works on the route (asphalt concrete pavement, sidewalk, tree, lighting, supply, drainage, traffic organization...) before August 31, 2025; complete the pumping station before October 31, 2025. The contractor strives to complete the project in 2025.

HỮU CHÁNH
TIN LIÊN QUAN

A series of projects are being implemented to connect National Highway 6 with Thanh Tri Bridge

|

Hanoi - The project to build Ring Road 2.5, Kim Dong underpass, and expand Linh Nam road, when completed, will help connect National Highway 6 with Thanh Tri bridge conveniently.

Hanoi to enforce land acquisition to build 2 traffic projects

|

Hanoi - The authorities will forcibly reclaim land from a number of households to implement the project to expand National Highway 1A and complete the construction of the new route of Provincial Road 427.

Starting schedule for 2 traffic projects worth 8,500 billion VND in Hanoi

|

Hanoi - Two important transport projects in the city center, with an investment capital of more than 8,500 billion VND, are starting construction after many years of stagnation.

5-star hotel, 1,005 rooms in Ha Long stop operating

|

Quang Ninh - A 5-star hotel located on the shore of Ha Long Bay, Ha Long City has officially stopped operating since April 1, 2025, surprising and regrettable to tourists.

Bottlenecks that need to be removed for businesses to break through green transformation

|

Green transformation is no longer a trend but a vital opportunity for development. However, many businesses still face difficulties with the problem of costs, technology, etc.

Many officials violated compensation for expressway projects

|

Ha Tinh - Announcing the results of the 39th session of the Ha Tinh Provincial Party Committee's Inspection Commission has just pointed out violations by a number of officials in compensation for the North - South expressway project.

Accident on Mai Dich overpass, Hanoi Ring Road 3 congested for 6km

|

Hanoi - The accident between a car and a motorbike on the Mai Dich overpass left 1 person dead, traffic on Ring Road 3 was congested for many kilometers.

Quang Ninh has another Deputy Secretary of the Provincial Party Committee

|

Quang Ninh - Ha Long City Party Secretary Vu Quyet Tien was elected to hold the position of Deputy Secretary of the Quang Ninh Provincial Party Committee.

A series of projects are being implemented to connect National Highway 6 with Thanh Tri Bridge

HỮU CHÁNH |

Hanoi - The project to build Ring Road 2.5, Kim Dong underpass, and expand Linh Nam road, when completed, will help connect National Highway 6 with Thanh Tri bridge conveniently.

Hanoi to enforce land acquisition to build 2 traffic projects

HỮU CHÁNH |

Hanoi - The authorities will forcibly reclaim land from a number of households to implement the project to expand National Highway 1A and complete the construction of the new route of Provincial Road 427.

Starting schedule for 2 traffic projects worth 8,500 billion VND in Hanoi

HỮU CHÁNH |

Hanoi - Two important transport projects in the city center, with an investment capital of more than 8,500 billion VND, are starting construction after many years of stagnation.