Image of 31.5 km of Ho Chi Minh road taken shape, about to be used for the entire route

ĐÌNH TRỌNG |

HCMC - The 31.5 km construction project of the Ho Chi Minh road has taken shape and is about to be fully opened.

The Ho Chi Minh Road project, the Chon Thanh - Duc Hoa section passing through Dong Nai, Ho Chi Minh City and Tay Ninh, is 72.75 km long, divided into 3 construction packages with a total investment of about VND 2,293 billion.

The road is built according to technical standards equivalent to a level III plain road, the completion phase of the 6-lane highway scale.

Of which, construction package 1 started at the end of November 2023 by Deo Ca Group. This section is 31.5 km from the border of Dong Nai to the Saigon River bordering Tay Ninh province, with a construction value of more than 681 billion VND.

Currently, the implementation output has reached more than 80% of the contract volume. The asphalt concrete paving of this route has been almost completed.

Gan 30 km da duoc tham nhua
Nearly 30 km of the road has been paved with asphalt concrete. Photo: Dinh Trong

On the route, there are 6 bridges including Kenh Phuoc Hoa bridge, Cay Truong bridge, Ba Tu bridge, Thi Tinh bridge, Suoi Tre bridge, and Thanh An bridge.

In which, Thi Tinh bridge, Ba Tu bridge, Thanh An bridge face difficulties during construction. These bridges were unfinished 12 years ago. After a long time of many changes in weather and climate, some structural items were damaged. The steel part waiting for rust is damaged and stolen, so the planting is difficult. The completion of the bridges takes a lot of time and money.

The contractor is actively constructing and overcoming difficulties. To date, 6 bridges have completed the bridge deck, the road section has basically completed the groundbreaking.

6 cay cau tren tuyen 31,5 km dang dan hoan thien. Anh: Dinh Trong
6 bridges on the 31.5 km route are gradually being completed. Photo: Dinh Trong
Cau Thanh An bac qua song Sai Gon la cay cau quan trong nhat trong du an nay, den nay sap hoan thien. Anh: Dinh Trong
Thanh An Bridge across the Saigon River is the most important bridge in this project, which is nearing completion. Photo: Dinh Trong
Tuyen duong di qua cac rung cao su bat ngan o Bau Bang va Dau Tieng. Anh: Dinh Trong
The route passes through vast rubber forests in Bau Bang and Dau Tieng. Photo: Dinh Trong

The project is still stuck with land clearance, affecting the progress of the project

It is known that this project was constructed in 2009, and was delayed due to lack of capital until 2011. By November 2023, the project was restarted with the goal of continuing to complete unfinished construction items.

The 31.5 km section is expected to be constructed 4 months ahead of schedule, but it will be difficult to complete due to some points that have not been handed over due to site clearance problems.

It is noted that at the DT 750 intersection in Bau Bang, there are still land issues. The two electric poles are still intersecting at the intersection between Ho Chi Minh Road and DT 750 Road. About 100 m of road here is under construction. At the intersection with DT 750, the roadbed cannot be treated.

Hai cot dien o nut giao duong Ho Chi Minh voi DT 750 van chua duoc di doi. Anh: Dinh Trong
The two electric poles at the Ho Chi Minh road intersection with DT 750 have not been relocated. Photo: Dinh Trong

The contractor's representative said that the delay in handing over the site greatly affects the construction progress and the project completion plan. If the locality does not handle it completely, it will be very difficult for the contractor to complete the task as committed.

Viec cham ban giao mat bang da anh huong den tien do thi cong du an. Anh: Dinh Trong
The delay in handing over the site has affected the project's progress. Photo: Dinh Trong
ĐÌNH TRỌNG
TIN LIÊN QUAN

Ho Chi Minh Road, Buon Ma Thuot bypass section, increases capital, delays land handover

|

The Ho Chi Minh Road project, the eastern bypass of Buon Ma Thuot City, is behind schedule and has increased capital due to land clearance problems.

A section of Ho Chi Minh road is spent 57 billion to repair

|

The Ministry of Transport said that in 2025, a section of Ho Chi Minh road will be spent 57 billion for repair.

Painter Le Thiet Cuong passes away

|

Painter Le Thiet Cuong passed away at the age of 63 after a long battle with cancer.

Ukraine has a female Prime Minister for the second time in history

|

On July 17, the Ukrainian parliament voted to appoint Yulia Svyrydenko as the country's new prime minister.

Bloody conflict flare up in Syria, more than 350 people killed

|

On July 17, at least 356 people were killed in an armed clash between new government forces and Druze self-defense units in Suwayda (Syria).

Discussion: Green transportation transformation - an irreversible trend

|

In order to protect the environment and improve people's health, Lao Dong Newspaper organized a seminar: Green transportation transformation - an irreversible trend.

Support rate for Ms. Paetongtarn to be reappointed as Prime Minister of Thailand

|

With Prime Minister Paetongtarn Shinawatra suspended from office, Thailand is facing a major turning point with 3 potential scenarios.

Ho Chi Minh Road, Buon Ma Thuot bypass section, increases capital, delays land handover

BẢO TRUNG |

The Ho Chi Minh Road project, the eastern bypass of Buon Ma Thuot City, is behind schedule and has increased capital due to land clearance problems.

A section of Ho Chi Minh road is spent 57 billion to repair

Xuyên Đông |

The Ministry of Transport said that in 2025, a section of Ho Chi Minh road will be spent 57 billion for repair.

Đường Hồ Chí Minh qua Bình Dương thảm nhựa xong vào 12.2024

ĐÌNH TRỌNG |

Dự án đường Hồ Chí Minh, đoạn Chơn Thành - Đức Hòa đi qua địa bàn tỉnh Bình Dương đang được đẩy nhanh tiến độ thi công, giải phóng mặt bằng.