Weather control, speed up progress on two trillion-dong expressways in Lang Son

Khánh Linh |

Lang Son - Nearly 5,000 workers and thousands of machines and equipment are working hard on two large expressway construction sites worth tens of thousands of billions of VND.

The rainy season is approaching. Every rainy season, the border area is completely eroded, causing many difficulties for the construction work.

On the two billion-dong expressway in Lang Son, workers and machinery are being mobilized to the maximum to "cautize" the weather, ensuring construction progress.

The Huu Nghi - Chi Lang Expressway Project is nearly 60km long, a vital route connecting Huu Nghi International Border Gate with the Bac Giang - Lang Son Expressway. With a total investment of more than VND 11,000 billion, the project is divided into two phases and is currently entering the phased construction phase.

Mua lon, nuoc suoi chay xiet gay anh huong khong nho den tien do thi cong. Anh: DVCC
Heavy rain and strong water flows have significantly affected the construction progress. Photo: DVCC

According to the latest report from the Project Management Board, up to now, the entire route has handed over more than 94% of the site, mobilizing about 2,300 engineers, workers and more than 1,000 construction equipment.

At the construction site, 95 construction teams are deployed simultaneously on 4 packages. The implementation value reached about 1,327/6,580 billion VND, equivalent to more than 20% of the contract volume.

Despite prolonged heavy rain causing local flooding, affecting material transportation and road construction, construction teams still maintain regular presence.

Mr. Nguyen Minh Binh, the worker operating the vibrating chiller, quickly wiped the dust and rain on his face, shared: "With the topography of high mountains, abnormal floods in the summer, it is a direct threat to the construction progress of two highways. Especially, in the past week, heavy rain made many areas flooded, soil became muddy, machinery could not access it."

According to Mr. Binh, to fix the problem, the contractor must pump out water and increase human resources to level the roadbed.

At the Dong Dang - Tra Linh Expressway project, nearly 2,000 workers and hundreds of motor vehicles are operating continuously to ensure progress.

The two main packages EC01 and EC02 have mobilized a total of 220 construction teams, focusing on the items of digging, filling, handling bridge foundations and constructing underpasses for people.

Some items such as bored piles and bridge piers have reached over 90% of the volume, showing construction efforts in complex geological conditions and unpredictable weather.

Mr. Pham Viet Cuong, representative of the contractor, said: "Land and excavators are muddy and this is a common occurrence. However, the brothers still persistently stay at the construction site, work overtime, and even work all night when the rain stops to make up for the progress.

According to many construction units, in case of prolonged rain, the option of covering the roadbed with tarpaulins after compacting the roadbed to limit water absorption has also been considered.

Cong truong “khong ngu” de dam bao tien do. Anh: Khanh Linh
The construction site "does not sleep" to ensure progress. Photo: Khanh Linh

Talking to reporters, the project business representative said that in order to cope with unfavorable conditions, contractors have deployed three consecutive shifts, arranging flexible construction teams to take advantage of favorable weather. Some sections of the route are prioritized for early implementation to prevent risks due to prolonged rain.

The investor's representative also affirmed his determination to complete the technical route in 2025, as committed to the Government.

To achieve this goal, the decisive factor is the synchronous coordination of local authorities in site clearance, handling of technical infrastructure and removing difficulties in construction materials.

Khánh Linh
TIN LIÊN QUAN

Revealing the reason why Son Hai contractor was hit by a landslide in the expressway construction package through Binh Phuoc

|

Regarding the decision of Son Hai Group Company Limited to protest the results of the contractor selection in Binh Phuoc, the authorities had previously bid and revealed the reason for the elimination of this unit.

Noise in the results of selecting contractors to build expressways through Binh Phuoc

|

Binh Phuoc - Information is circulating online that Son Hai Group opposes the results of the selection of contractors for the construction package of the expressway through Binh Phuoc.

Lam Dong reclaims land to build resettlement areas to serve the expressway project

|

Lam Dong - The resettlement area serving the relocation and resettlement work is affected by two key expressway projects in the locality.

The crisis of Lang Ha Thuc summer camp from the way MC Minh Trang apologizes

|

In recent days, Hanh Hung Village, a famous summer camp model, has faced an unprecedented media crisis after negative feedback from parents.

Mr. Trump sends more letters to many countries, promotes tariff agreements

|

President Trump continues to put trade pressure on many countries with letters announcing new tax rates expected to be applied.

Difficulty in clearing the channel to 2 fishing ports that are silted up, boats stranded

|

Ha Tinh - The channel to Thach Kim Fishing Port and Cua Nhuong Fishing Port is silted up, causing ships and boats to strand when the tide goes down.

Director of Hanoi Police issues request to the new commune-level police

|

The Director of Hanoi Police requested the new commune-level police to be closer to the people, closer to the people, and take the people's satisfaction as the target.

Minister of National Defense chaired the Conference on handover of the position of Commander of Military Region 7

|

HCMC - On July 9, General Phan Van Giang, Politburo member, Deputy Secretary of the Central Military Commission, Minister of National Defense chaired the Conference to hand over the position of Commander of Military Region 7.

Revealing the reason why Son Hai contractor was hit by a landslide in the expressway construction package through Binh Phuoc

Xuyên Đông |

Regarding the decision of Son Hai Group Company Limited to protest the results of the contractor selection in Binh Phuoc, the authorities had previously bid and revealed the reason for the elimination of this unit.

Noise in the results of selecting contractors to build expressways through Binh Phuoc

ĐÌNH TRỌNG |

Binh Phuoc - Information is circulating online that Son Hai Group opposes the results of the selection of contractors for the construction package of the expressway through Binh Phuoc.

Lam Dong reclaims land to build resettlement areas to serve the expressway project

LAM HỒNG |

Lam Dong - The resettlement area serving the relocation and resettlement work is affected by two key expressway projects in the locality.