Ninh Binh - After 36 months of construction, the East - West route, phase I in Ninh Binh, was officially put into operation from April 19.

The East-West Road Construction Investment Project, Ninh Binh Province (Phase I) is a route of great significance in creating momentum for economic, social development, and tourism development in Ninh Binh Province. This is the main axis to gradually complete the planned transport infrastructure, creating space and space to attract investors to the locality's strengths, contributing to the socio-economic development of the locality.

On April 18, speaking with a reporter from Lao Dong Newspaper, Mr. Pham Quoc Chinh - Director of the Ninh Binh Province Traffic Construction Investment Project Management Board (investor) of the East-West Road Construction Investment Project, Ninh Binh Province (phase I) said that after 36 months of construction, the project has completed the main items, meeting the conditions for inauguration and putting them into operation to serve the economic development and travel of the people.

The project has a total length of 22.95 km with 4 lanes. Particularly, the segment of km0+000 - km1+640.58 (from the beginning of the route to the intersection of the North - South Expressway) has 8 lanes of urban planning. The route is built according to grade II road standards, design speed of 100km/h, phase I Designing the design speed of design speed is 80km/h. Group A project with a total investment of nearly VND 2,000 billion.

The project has a particularly large construction volume, with a site clearance scope of about 163.69 hectares with a total of 990 households and individuals affected, but in a short time, localities with roads have handed over clean land to investors for construction contractors to focus on installing machinery and equipment to speed up the project's progress.

"With the efforts and involvement of the entire political system, the project has been shortened by 20 months compared to the approved project schedule. This is the largest traffic project ever in Ninh Binh approved by the locality. The project will be officially inaugurated and put into operation from December 19" - Mr. Chinh said.

NGUYỄN TRƯỜNG
TIN LIÊN QUAN

Thai Binh coastal road project accelerates to the finish line

|

Thai Binh - The coastal road project is being accelerated by the contractor, striving to open the entire route on the occasion of National Day, September 2 this year.

The overpass worth nearly VND1,500 billion connecting Nam Dinh - Ninh Binh awaits the highway

|

Nam Dinh - The Day River overpass connecting Nam Dinh and Ninh Binh provinces has been basically completed but is still "waiting" for the Ninh Binh - Hai Phong expressway.

Preparing land to start construction of Ninh Binh - Hai Phong expressway

|

Ninh Binh - The province is focusing on directing the acceleration of site clearance progress to start the Ninh Binh - Hai Phong expressway project, the section passing through the province.

Spring comes to key transport projects in Ninh Binh

|

Ninh Binh - A series of traffic works will be put into operation during the 2025 Lunar New Year to serve people's travel needs.

Nghe An has many options for naming new communes after the arrangement

|

Nghe An - Some localities named new communes after districts with serial numbers, some other localities named them with historical and traditional cultural elements.

The Ministry of Public Security informs about new features on VNeID for flying

|

The VNeID application has just integrated a new feature to serve passengers getting on a plane from buying tickets, going through security checkpoints... the entire process without paperwork.

List of 65 expected commune-level administrative units in Thai Binh after the reorganization

|

Thai Binh - According to the draft project, after the arrangement, the whole Thai Binh province will now decrease from 242 to 65 commune-level administrative units.

The scale of Hai Phong City after merging with Hai Duong province

|

Hai Phong - Hai Phong City is collecting voters' opinions on the draft Project to merge with Hai Duong province.

Thai Binh coastal road project accelerates to the finish line

NAM HỒNG |

Thai Binh - The coastal road project is being accelerated by the contractor, striving to open the entire route on the occasion of National Day, September 2 this year.

The overpass worth nearly VND1,500 billion connecting Nam Dinh - Ninh Binh awaits the highway

Lương Hà |

Nam Dinh - The Day River overpass connecting Nam Dinh and Ninh Binh provinces has been basically completed but is still "waiting" for the Ninh Binh - Hai Phong expressway.

Preparing land to start construction of Ninh Binh - Hai Phong expressway

NGUYỄN TRƯỜNG |

Ninh Binh - The province is focusing on directing the acceleration of site clearance progress to start the Ninh Binh - Hai Phong expressway project, the section passing through the province.

Spring comes to key transport projects in Ninh Binh

NGUYỄN TRƯỜNG |

Ninh Binh - A series of traffic works will be put into operation during the 2025 Lunar New Year to serve people's travel needs.