These days, the working atmosphere at the construction site of Component Project 3 of the Khanh Hoa - Buon Ma Thuot Expressway Construction Project Phase 1 is very urgent and urgent.
With high determination, contractors are racing against time, striving to complete the project by the end of November this year, practically welcoming the upcoming National Party Congress successfully.
Currently at the construction site, the investor has directed the implementation of 41 construction teams, mobilizing nearly 800 officers, engineers, workers and nearly 500 modern machines and equipment to work continuously.
In construction package No. 02 undertaken by Tan Nam Construction Joint Stock Company and Hoang Nam Bridge and Road Construction Company Limited (subcontractor), the work of asphalt paving the road surface is being accelerated.
Mr. Tran Van Hong, Deputy Commander of the construction site of package 02, said that our package has a total length of 15.5km. After overcoming initial difficulties in site clearance, it has now reached about 72% of the volume, ensuring overall progress.
In particular, package 02 currently has 18 construction teams, mobilizing 260 human resources and more than 150 specialized equipment to operate continuously in three shifts. The road surface is covered with crushed stone and has reached over 92%, all 10/10 bridges on the route have been successfully installed, of which 9 basic bridges have been technically opened to traffic.
In package No. 01, 16.5km long (section Km69+500 - Km86+00), constructed by Son Hai Group Company Limited and Saigon Construction and Trading Company Limited (subcontractor), the overall progress reached about 83%.
Currently, contractors are speeding up the construction of the C16 asphalt concrete layer, reinforced slopes, lighting systems, and at the same time, thoroughly handling landslides, completing service roads and drainage systems.
According to the Dak Lak Province Traffic Construction Investment and Rural Development Project Management Board (investor), as of October 9, 2025, Component Project 3 has reached nearly 72% of the contract value.
This shows the great efforts of the investor and construction units in ensuring the progress and quality of the project.