Lam Dong removes difficulties and obstacles in key projects

|

Lam Dong - Chairman of Lam Dong People's Committee Tran Hong Thai requested the Department of Finance to quickly coordinate and remove difficulties and obstacles in key projects.

Reasons for slow disbursement of public investment capital

According to the Lam Dong Provincial Department of Finance, since the beginning of the year, the total disbursed capital has reached 253 billion VND, reaching 3.5% of the plan, not reaching the set target.

In 2025, the whole province will be allocated a total of VND 7,173.422 billion in public investment capital. Key projects including expressway, Ta Hoet lake, Dong Thanh lake, Kazam lake... are facing many difficulties, the capital disbursement progress is slow, and has not met requirements.

In addition, there are 3 remaining projects including the Investment Project to build the western bypass of Bao Loc city; the Ta Hoet reservoir construction project; the Dong Thanh reservoir project.

Explaining the reasons for the delay in the progress of key projects and low disbursement, Mr. Ton Thien San, Director of the Department of Finance of Lam Dong province, said: "Many projects related to forests and forest land cause difficulties in converting land use purposes".

According to Mr. San, there are projects that have to adjust the project items to locations with no forests, so the project investment time is extended.

In fact, through the survey, the capacity and responsibility of investors and construction contractors, the consulting unit is still weak, the responsibility is not high. The units lacked initiative and determination in directing the acceleration of project implementation and disbursement of public investment capital.

Investment supervision has not received due attention from authorities at all levels, and projects that are behind schedule have not been promptly handled...

Focus on removing difficulties and obstacles

The Director of Lam Dong Provincial Department of Finance added that in the coming time, the unit will inspect and urge investors to take advantage of favorable weather to speed up construction progress. If difficulties or problems arise, they will promptly propose to the Provincial People's Committee to resolve them.

For the Tan Phu - Bao Loc expressway construction project alone, a member of the Working Group under the Department of Finance has completed the review of the technical research report.

The investor has completed the environmental impact assessment dossier and submitted it to the Ministry of Natural Resources and Environment for approval.

As for the Bao Loc - Lien Khuong expressway project, the investor is completing the technical research report according to the appraisal opinion of the competent authority.

According to research, the Lam Dong Provincial Department of Finance is urgently reviewing, urging, and removing difficulties in a series of important projects, contributing to changing the appearance of urban areas in the locality.

Including the project to build new urban area No. 6 (Da Lat); New urban area of Ly Thuong Kiet - Bao Loc road; New urban area of Nam Song Da Nhim; Investment project to build part of Van Tam residential area; Bi Doup residential area project (Lac Duong district).

In the face of the above situation, Mr. Tran Hong Thai, Chairman of Lam Dong Provincial People's Committee, assigned the Department of Finance to closely coordinate with relevant units to quickly remove difficulties and obstacles in key projects.

Thereby, ensuring the disbursement progress of public investment capital according to the set plan. "If projects are delayed or cannot be implemented, there is a part of the fault of departments, branches... The Provincial People's Committee is ready to work with each project, wherever there are difficulties, to resolve them there", the Chairman of Lam Dong Provincial People's Committee emphasized.

In the coming time, the Lam Dong Provincial Department of Finance will coordinate with departments, branches, People's Committees of districts and cities to drastically implement solutions for disbursing public investment capital in 2025. Thereby, strive for the disbursement rate of public investment capital in 2025 to reach over 95%.

TIN LIÊN QUAN

Tropical depression appears near the Philippines, the East Sea may welcome a storm this week

|

The low pressure near the Philippines strengthened into a tropical depression on July 14, with the potential to strengthen into a storm in the East Sea.

AI cameras in Hanoi can identify wanted subjects

|

According to the Director of Hanoi Police, the AI camera system is capable of recognizing faces, can automatically identify wanted subjects and then report to the command center.

Billiards legend suddenly passes away while resting at hotel

|

Famous Taiwanese billiards player Chang Jung-lin suddenly passed away while resting at a hotel.

Civil servants wear life jackets, cross the river to the capital's only island commune

|

Hanoi - At 6am, when the sun had not yet risen, the first ferries at Chu Minh Wharf took officers and civil servants across the Red River to Minh Chau island commune.

Look up the fastest high school graduation exam scores in 2025 on Lao Dong

|

The 2025 high school graduation exam scores will be announced by the Ministry of Education and Training at 8:00 a.m. on July 16. Candidates can look up the fastest exam scores on Lao Dong.

Legal inspection when buying project land

Minh Huy (T/H) |

The project land is attractive but has potential risks. Understanding the legal documents, transaction conditions and inspection methods helps you invest safely and avoid losing unfair money.

Hanoi pushes social housing progress, projects in Long Bien are still abandoned

KHÁNH AN |

Hanoi - Although the city is constantly pushing the progress to complete the target of social housing, the approved project in Long Bien is still a vacant land.

Island commune in Binh Dinh will transform with a series of resort projects

Thảo Phương |

Binh Dinh - Nhon Chau island commune will be invested with more than 400 billion VND to develop 4 tourist attractions with a resort system, marine parks and many service utilities.

Resolving difficulties for 5 component projects of the North - South Expressway project

PHẠM ĐÔNG |

The Deputy Prime Minister has directed a series of solutions to remove difficulties and obstacles for 5 component projects of the North-South Expressway to soon reopen the route.

Investing in the Suoi Cai road expansion project in Binh Duong

ĐÌNH TRỌNG |

Binh Duong - The Provincial People's Committee agreed on the investment policy for the Suoi Cai road expansion project in Tan Uyen city, Binh Duong province.