Lang Son asks for additional investment money for Huu Nghi - Chi Lang Expressway

Khánh Linh |

Lang Son - The Huu Nghi - Chi Lang expressway project is facing legal and financial difficulties, pushing the locality into a state of "running out of capital".

The expressway under construction is "cut off capital"

The Huu Nghi - Chi Lang Expressway is nearly 60km long, with a total investment of more than VND 11,000 billion, of which the State capital is about VND 5,500 billion, the rest is arranged by investors.

The project passes through Chi Lang, Cao Loc, Van Lang districts and Lang Son city, expected to complete the connection between Bac Giang - Lang Son and Dong Dang - Tra Linh, promoting the border economy.

Started in April 2024, the project has cleared more than 84% of the site, constructed about 50km and completed most of the design.

Cao toc Huu Nghi - Chi Lang dang duoc thi cong kieu “xoi do“. Anh: Khanh Linh
The Huu Nghi - Chi Lang Expressway is being constructed in the " sticky rice and bean" style. Photo: Khanh Linh

However, when adjusting the scale of the Tan Thanh - Coc Nam section from 2 to 4 lanes, the project encountered great difficulties in both legality and finance.

In the document sent to the Government, Lang Son province stated that according to Law No. 57/2024/QH15 (effective from January 15, 2025), PPP projects in disadvantaged areas can increase the State capital ratio to a maximum of 70%.

However, because the project was approved and constructed before the law took effect, it is not subject to transition provisions. The adjustment dossier currently lacks sufficient legal basis to submit to the Provincial People's Council.

Regarding finance, Lang Son province said it is no longer able to allocate an additional VND 2,700 billion to increase the State capital ratio. The province has allocated 1,500 billion VND for the project in the 2021-2025 period, but in 2024, there was a shortfall of 256 billion VND in land revenue and it is forecasted that 2025 will continue to be difficult.

The investor - Deo Ca consortium and its member units - also faced difficulties when the bank only approved a loan of VND 2,300 billion out of the total initial commitment of VND 4,423 billion. The initial financial plan was broken.

The People's Committee of Lang Son province proposed that the Government clarify the legal basis for applying a rate of 70% of State capital or adding transitional provisions, and at the same time propose the Central Government to support an additional VND 2,700 billion from the budget to continue adjusting and expanding the route from phase 1.

Cao toc 11.000 ti hien dang vuong nhieu vi tri mat bang. Anh: Khanh Linh
The 11,000 billion VND expressway is currently stuck with many site clearance locations. Photo: Khanh Linh

slow construction due to lack of land

Although the project is expected to be the "final link" in the expressway axis connecting Hanoi - Lang Son, the construction progress has only reached 11.66% of the contract value.

According to the report, although from March 2025, contractors have increased 239 personnel, 226 equipment and added 5 construction teams, the "sticky rice and bean" site situation has seriously affected the implementation.

Of the 497 households that had to be relocated, only 81 households have handed over the land. Hundreds of technical infrastructure works such as electric poles, telecommunications lines, and railway signals have not been handled.

Mr. Vu Xuan Huy - Director of the Executive Board of DCT 559 Investment Joint Stock Company - said: "We have mobilized more than 140 motorbikes, 400 engineers and workers. However, the lack of synchronous land makes it very difficult to organize construction".

Khánh Linh
TIN LIÊN QUAN

Real estate along the Hoa Binh - Moc Chau Expressway is about to increase in price

|

After the Hoa Binh - Moc Chau Expressway started construction at the end of September 2024, Northwest real estate began to have many clear changes.

Bottleneck at 2 expressway projects through Lang Son and Cao Bang

|

Lang Son - The Huu Nghi - Chi Lang and Dong Dang - Tra Linh expressway projects are racing to make efforts to open the route in 2025.

Relocating high-voltage power poles to build Dong Dang - Tra Linh expressway

|

Cao Bang - The locality will move 24 locations of 110kV power poles to serve the construction of the Dong Dang - Tra Linh expressway project.

Proposing the Ministry of Public Security to investigate a series of violations at the Vinh Long provincial housing project

|

The Government Inspectorate requested the Ministry of Public Security to receive documents to review and investigate the Hoang Hao Housing Project in Long Ho District, Vinh Long Province.

Gold price breaks peak of 120 million VND, discouraged when buying gold for wedding

|

Hanoi - Gold price on April 18 officially surpassed VND120 million/tael. Gold shops in Hanoi recorded the situation of people lining up early to buy.

US announces new port fees for ships linked to China

|

The US government has just announced new port fees for ships built or operated by China.

The reason why Saigon was named for a central ward of Ho Chi Minh City

|

HCMC - District 1 will name one of the four newly established wards "Saigon" after merging the 10 existing wards.

Thousands of cadres and teachers with regional allowance debts will be paid

|

Quang Tri - Cam Lo District will balance the budget to pay regional allowances to cadres and teachers who are in debt from 2014 to 2023.

Real estate along the Hoa Binh - Moc Chau Expressway is about to increase in price

Yên San |

After the Hoa Binh - Moc Chau Expressway started construction at the end of September 2024, Northwest real estate began to have many clear changes.

Bottleneck at 2 expressway projects through Lang Son and Cao Bang

Khánh Linh |

Lang Son - The Huu Nghi - Chi Lang and Dong Dang - Tra Linh expressway projects are racing to make efforts to open the route in 2025.

Relocating high-voltage power poles to build Dong Dang - Tra Linh expressway

Tân Văn |

Cao Bang - The locality will move 24 locations of 110kV power poles to serve the construction of the Dong Dang - Tra Linh expressway project.