Revealing the complex construction intersection on the Bien Hoa - Vung Tau Expressway connecting Dong Nai to Ho Chi Minh City

HÀ ANH CHIẾN |

Dong Nai - The intersection between Vo Nguyen Giap Street (Phuoc Tan Ward) and Bien Hoa - Vung Tau Expressway connecting to Ho Chi Minh City is gradually becoming clear.

The intersection between Vo Nguyen Giap Street and Bien Hoa - Vung Tau Expressway belongs to Component Project 1 - Bien Hoa - Vung Tau Expressway Project. This is one of the major intersections with complex construction.

Cao toc Bien Hoa - Vung Tau huong Dong Nai di TPHCM. Anh: HAC
Bien Hoa - Vung Tau Expressway from Dong Nai to Ho Chi Minh City. Photo: HAC

According to the Dong Nai Province Construction Investment Project Management Board, at this intersection item, contractors are speeding up the progress and completion of construction to ensure synchronization with the entire project, achieving the goal of opening the project's technical traffic before December 19, 2025 as requested by the Prime Minister.

According to Lao Dong Newspaper, the construction site of the intersection between Vo Nguyen Giap Street and Bien Hoa - Vung Tau Expressway is being urgently constructed, with many personnel and machinery mobilized to race for progress.

According to the Dong Nai Province Construction Investment Project Management Board, with Component Project 1, Bien Hoa - Vung Tau Expressway Project, contractors are implementing 30 construction teams with a total of more than 250 motorbikes, equipment and nearly 500 workers to construct the project.

Thi cong tai nut giao giua duong Vo Nguyen Giap voi duong cao toc Bien Hoa - Vung Tau thuoc Du an thanh phan 1. Anh: HAC
Construction at the intersection between Vo Nguyen Giap Street and Bien Hoa - Vung Tau Expressway under Component Project 1. Photo: HAC

According to Project Management Board 85 (Ministry of Construction) - Investor of Component Project 2 - Bien Hoa - Vung Tau Expressway Project: Currently, the asphalt concrete pavement of the section passing through Phuoc Thai Commune, Dong Nai Province has been completed and connected with Component Project 3 - Bien Hoa - Vung Tau Expressway Project, the section passing through Ho Chi Minh City (formerly Ba Ria - Vung Tau Province) has been technically opened to traffic since April 2025.

Component project 2, Bien Hoa - Vung Tau Expressway project through Dong Nai province is 18 km long, so far the total construction output of the project has reached more than 70% of the signed contract value. It is expected that by December 19, 2025, the construction output will reach about 85% of the contract value, qualified for technical traffic opening as required by the Prime Minister.

The Bien Hoa - Vung Tau Expressway is about 54 km long, of which the section passing through Dong Nai province is more than 34 km long, divided into two Component Projects 1, 2; the remaining section passing through Ho Chi Minh City (formerly Ba Ria - Vung Tau province) is nearly 20 km long, belonging to Component Project 3.

Some images recorded by Lao Dong Newspaper at the construction site of the intersection between Vo Nguyen Giap Street and Bien Hoa - Vung Tau Expressway:

Du an thanh phan 1, Du an duong cao toc Bien Hoa - Vung Tau do Ban quan ly dau tu xay dung tinh Dong Nai lam chu dau tu, thong xe ky thuat ngay 19.12.2025. Anh: HAC
Component project 1, Bien Hoa - Vung Tau Expressway project invested by Dong Nai Provincial Construction Investment Management Board will be technically opened to traffic on December 19, 2025. Photo: HAC
Cao toc Bien Hoa - Vung Tau huong ra nga tu Vung Tau va quoc lo 1. Anh: HAC
Bien Hoa - Vung Tau Expressway heads towards Vung Tau intersection and National Highway 1. Photo: HAC
Duong Vo Nguyen Giap huong ra nut giao voi duong cao toc Bien Hoa - Vung Tau. Anh: HAC
Vo Nguyen Giap Street towards the intersection with Bien Hoa - Vung Tau Expressway. Photo: HAC
Thi cong loi len cao toc Bien Hoa - Vung Tau. Anh: HAC
Construction of the entrance to Bien Hoa - Vung Tau Expressway. Photo: HAC
Can canh thi cong cao toc Bien Hoa - Vung Tau. Anh: HAC
Close-up of the Bien Hoa - Vung Tau Expressway construction. Photo: HAC
Nut giao vong xoay cong 11 ket noi quoc lo 51, duong Bui Van Hoa, duong Vo Nguyen Giap. Anh: HAC
The rotation of Gate 11 connects National Highway 51, Bui Van Hoa Street, and Vo Nguyen Giap Street. Photo: HAC

HÀ ANH CHIẾN
RELATED NEWS

Bien Hoa - Vung Tau Expressway is seamless between Ho Chi Minh City and Dong Nai

|

HCMC - The seamless connection between component project 2 and component 3 of Bien Hoa - Vung Tau Expressway forms a continuous moving axis from Dong Nai to Ba Ria.

Bien Hoa - Vung Tau Expressway risks missing the opening date

|

The Bien Hoa - Vung Tau Expressway project has only reached more than 51% of the construction volume, causing the technical traffic target on December 19 to be at risk of being behind schedule.

The opening of the Bien Hoa - Vung Tau expressway is the result of considering the arrangement of leaders

|

Dong Nai - The opening of the Bien Hoa - Vung Tau expressway on December 19 is the result of reviewing the arrangement and arrangement of leaders of the Provincial Construction Investment Project Management Board.

Billionaire Pham Nhat Vuong continues to rise in the list of the richest people on the planet

|

With assets increasing sharply, Mr. Pham Nhat Vuong - Chairman of Vingroup Corporation entered the top 91 richest billionaires on the planet.

Volleyball teams finalize the final list of participants in the 33rd SEA Games

|

The Vietnamese volleyball teams have determined the list of players who will final compete in the 33rd SEA Games.

The matrix of videos of violence, negativity is rampant and the silent consequences on mental health

|

The video of violence spreading on social media is silently causing psychological damage, causing many people to fall into anxiety and insecurity.

Waiting for the day the road leading to the gateway to the white plateau of Bac Ha is opened

|

Lao Cai - National Highway 4E leading to Bac Ha White Plateau is under construction to promote trade and tourism.

Disburse about VND2,400 billion to compensate for the construction site of Ho Chi Minh City Ring Road 4 through the old Binh Duong

|

HCMC - The units have disbursed compensation of about VND 2,400 billion for site clearance to build the Ho Chi Minh City Ring Road 4 project, the section passing through the old Binh Duong area.

Bien Hoa - Vung Tau Expressway is seamless between Ho Chi Minh City and Dong Nai

Thành An |

HCMC - The seamless connection between component project 2 and component 3 of Bien Hoa - Vung Tau Expressway forms a continuous moving axis from Dong Nai to Ba Ria.

Bien Hoa - Vung Tau Expressway risks missing the opening date

HÀ ANH CHIẾN |

The Bien Hoa - Vung Tau Expressway project has only reached more than 51% of the construction volume, causing the technical traffic target on December 19 to be at risk of being behind schedule.

The opening of the Bien Hoa - Vung Tau expressway is the result of considering the arrangement of leaders

HÀ ANH CHIẾN |

Dong Nai - The opening of the Bien Hoa - Vung Tau expressway on December 19 is the result of reviewing the arrangement and arrangement of leaders of the Provincial Construction Investment Project Management Board.