Opening a road of more than 42km through 9 communes and wards of Dong Nai province connecting the airport

HÀ ANH CHIẾN |

Dong Nai - The DT.770B road project, over 42km long, passes through 9 communes and wards connecting the eastern part of the province with National Highway 51 and Long Thanh airport.

On November 9, the Dong Nai Province Land Fund Development Center reported on the progress of the implementation plan and difficulties in implementing compensation for the DT.770B road project and proposed that the Provincial People's Committee direct the Provincial Construction Investment Project Management Board to promptly complete the procedures to approve the construction project as a basis for receiving the handover of boundaries, site clearance coordinates, and land acquisition maps.

The project has a total investment of more than VND 3,338 billion from the provincial budget (land use rights auction) with an implementation period from 2022 to 2026.

The project has a total land area of over 370 hectares with a total length of more than 42km passing through 7 communes: Xuan Bac, Xuan Que, Xuan Duong, Dau Giay, Gia Kiem, Long Phuoc, Phuoc Thai and 2 wards: Binh Loc, Xuan Lap (formerly Dinh Quan, Thong Nhat, Cam My, Long Thanh districts and Long Khanh city).

The total number of households whose land has been recovered is 803, with a plan to resettle about 354 households.

Currently, the project is carrying out the work of measuring and making land recovery maps, and it is expected that in December 2025, the work of measuring and extracting land recovery drawings will be completed to carry out the next work.

According to the Land Fund Development Center of Dong Nai province, the feasibility study report of the construction project has not been approved by the Provincial People's Committee.

San bay Long Thanh. Anh: HAC
Long Thanh Airport. Photo: HAC

DT 770B route is invested in construction connecting the eastern and northeastern districts of Dong Nai province with Long Thanh airport and Xuan Que - Song Nhan industrial parks, Bau Can - Tan Hiep industrial parks, connecting Bien Hoa - Vung Tau expressway, National Highway 51 and Cai Mep - Thi Vai seaport area (formerly Ba Ria - Vung Tau province, now Ho Chi Minh City).

The DT 770B road project will be invested in new construction with a length of more than 42km, with the starting point intersecting with DT 763 road (in Suoi Nho commune, old Dinh Quan district) and the end point intersecting with National Highway 51 (in Phuoc Thai commune, old Long Thanh district) planned to have a roadway of 60m, with 4-8 lanes.

Currently, Dong Nai province is investing in expanding 3 projects including DT 769, DT 770B and DT 773 with a total investment of more than VND 18,000 billion to connect Long Thanh airport.

HÀ ANH CHIẾN
RELATED NEWS

Proposal to clarify the basis for calculating the investment rate of Gia Binh airport project

|

The Gia Binh airport project has a total investment of about VND196,378 billion; of which phase 1 is about VND141,236 billion, phase 2 is about VND55,142 billion.

Vinh Airport is expected to reopen from December 19, 2025

|

Nghe An - After more than 5 months of suspension of operation for repair and upgrading, Vinh airport is expected to welcome the first flight back on December 19, 2025.

hesitation in transferring will reduce the opportunity to establish a hub position of Long Thanh airport

|

Dong Nai - According to ACV, if domestic airlines hesitate to move operations to Long Thanh airport, it will reduce the chance of establishing a hub position.

Inside the project worth over VND1,700 billion in Can Tho, many violations have just been pointed out

|

Can Tho - Can Tho Oncology Hospital project is like a large, desolate construction site, overgrown with grass and trees and construction materials.

Son La Hydropower Plant opens a bottom spillway to regulate reservoir

|

Son La - At 4:00 p.m. on November 9, Son La Hydropower Company opened a bottom spillway to regulate the lake's water level.

China lifts ban on strategic metal exports to the US

|

China has lifted a ban on exports of some key strategic metals to the US, effective from November 9.

On the day of completion, a chemical company in Lam Dong had a big explosion, killing 2 people

|

Lam Dong - The explosion that occurred at HC Bao Lam Joint Stock Company, in Bao Lam 1 commune, killed two workers on the day of completion.

Proposal to clarify the basis for calculating the investment rate of Gia Binh airport project

ANH HUY |

The Gia Binh airport project has a total investment of about VND196,378 billion; of which phase 1 is about VND141,236 billion, phase 2 is about VND55,142 billion.

Vinh Airport is expected to reopen from December 19, 2025

DUY CHƯƠNG |

Nghe An - After more than 5 months of suspension of operation for repair and upgrading, Vinh airport is expected to welcome the first flight back on December 19, 2025.

hesitation in transferring will reduce the opportunity to establish a hub position of Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - According to ACV, if domestic airlines hesitate to move operations to Long Thanh airport, it will reduce the chance of establishing a hub position.