The water level of the largest hydropower reservoir in the South on September 1st reached more than 55.5m

MINH CHÂU |

Dong Nai - The water level of Tri An hydropower reservoir on the morning of September 1st reached an elevation of more than 55.5m.

According to Tri An Hydropower Company, as of 6 am on September 1st, the water flow to Tri An reservoir is reaching 940m3/s, raising the reservoir water level to more than 55.5m, the total discharge flow to downstream is 0m3/s, and the downstream water level reaches 1m.

Previously, electricity output on August 31 at Tri An Hydropower Company reached nearly 6 million kWh.

Tri An Hydropower Plant has 4 units, with a total designed capacity of 400MW. This is the largest hydropower project in the Southern region, making a great contribution to the national power grid, helping to regulate domestic water sources, production, push saline and regulate floods for the downstream area.

The downstream area of Tri An hydropower plant is an area located along the Dong Nai River basin stretching across Dong Nai City, Ho Chi Minh City.

MINH CHÂU
RELATED NEWS

Water level of some hydropower reservoirs in the Central - Central Highlands region on August 31st

|

Hydropower reservoirs in the Central - Central Highlands region on the morning of August 31st maintained water levels lower than normal water levels.

Water levels of hydropower reservoirs in the North in the afternoon of August 30

|

The water level of many hydropower reservoirs in the Northern region is lower than the normal water level, while the amount of water flowing into the reservoir has a large difference.

Water level of Hoa Binh Hydropower Reservoir on August 30th

|

The water level of Hoa Binh Hydropower reservoir is lower than the normal level, while the reservoir continues to maintain power generation and regulate water flow through the plant.

Lai Chau adjusts Nam Si Luong 3 Hydropower protection plan

|

Lai Chau - The Provincial People's Committee has just approved the adjustment of the Dam and Reservoir Protection Plan for Nam Si Luong 3 Hydropower Plant.

Fire broke out at Dak Sak market in Lam Dong, 16 kiosks burned down

|

Lam Dong - A fire broke out at night at Dak Sak market, destroying 16 kiosks of 9 households, with estimated damage of more than 4 billion VND.

Ministry of Education and Training: Only 10th grade exams in public schools do not meet the needs

|

The 10th grade exam will only take place in areas with a large number of students but the public school system has not met the needs, such as Hanoi and Ho Chi Minh City.

Coach Yutaka Ikeuchi: U20 Vietnam still has a chance in the U20 Asian Cup qualifiers

|

Coach Yutaka Ikeuchi affirmed that U20 Vietnam still has a chance and will try to win in the remaining two matches.

Ministry of Health requests to focus efforts on rescuing victims of passenger car overturning in Gia Lai

|

The Ministry of Health requests Gia Lai and hospitals to focus on rescuing 20 victims injured in the passenger car overturning that killed 4 people.

Water level of some hydropower reservoirs in the Central - Central Highlands region on August 31st

Minh Nguyễn |

Hydropower reservoirs in the Central - Central Highlands region on the morning of August 31st maintained water levels lower than normal water levels.

Water levels of hydropower reservoirs in the North in the afternoon of August 30

Minh Nguyễn |

The water level of many hydropower reservoirs in the Northern region is lower than the normal water level, while the amount of water flowing into the reservoir has a large difference.

Water level of Hoa Binh Hydropower Reservoir on August 30th

Minh Nguyễn |

The water level of Hoa Binh Hydropower reservoir is lower than the normal level, while the reservoir continues to maintain power generation and regulate water flow through the plant.

Lai Chau adjusts Nam Si Luong 3 Hydropower protection plan

Thành An |

Lai Chau - The Provincial People's Committee has just approved the adjustment of the Dam and Reservoir Protection Plan for Nam Si Luong 3 Hydropower Plant.