In 2026, the project to open a road through 9 communes and wards of Dong Nai province to connect the airport will begin

HÀ ANH CHIẾN |

Dong Nai - The DT.770B road project, over 42km long, passing through 9 communes and wards connecting National Highway 51 and Long Thanh airport, is expected to start construction in April 2026.

On November 24, according to information from the Provincial Construction Investment Project Management Board, for 3 projects to upgrade, expand, and build new provincial routes 769, 773, and 770B to connect traffic with Long Thanh airport, the unit and the consulting contractor are currently implementing steps to complete the construction design documents after the basic design as well as prepare and submit for approval the feasibility study report of the projects.

Regarding the implementation progress, the Provincial Road 769 Upgrade and Expansion Project may start construction in February 2026.

Meanwhile, the projects to build provincial road 770B and upgrade and expand provincial road 773 are expected to start construction in April 2026.

The three routes mentioned above have a total investment of more than VND18,000 billion.

As for the Provincial Road Construction Project 769E, it also connects Long Thanh airport because it has to handle content related to intersections with the high-speed railway line on the North-South axis, the Thu Thiem - Long Thanh railway, so the progress is slower than the above projects. This project is expected to start construction at the end of 2026.

DT 770B route is invested in construction connecting the eastern and northeastern districts of Dong Nai province with Long Thanh airport and Xuan Que - Song Nhan industrial parks, Bau Can - Tan Hiep industrial parks, connecting Bien Hoa - Vung Tau expressway, National Highway 51 and Cai Mep - Thi Vai seaport area (formerly Ba Ria - Vung Tau province, now Ho Chi Minh City).

The DT 770B road project will be newly invested in construction with a length of more than 42km, with the starting point intersecting with DT 763 road and the end point intersecting with National Highway 51, planned to have a roadway of 60m, with 4-8 lanes.

The project has a total recovered land area of more than 370 hectares passing through 7 communes (Xuan Bac, Xuan Que, Xuan Duong, Dau Giay, Gia Kiem, Long Phuoc, Phuoc Thai) and 2 wards (Binh Loc, Xuan Lap).

HÀ ANH CHIẾN
RELATED NEWS

Opening 2 routes passing through 4 communes in Dong Nai connecting Ho Chi Minh City with Long Thanh airport

|

Dong Nai - The 25B and 25C road projects will be technically open to traffic at the end of 2025 and the beginning of 2026 to connect Long Thanh airport.

Solving the problem of one route carrying an entire airport in the Long Thanh airport project

|

Dong Nai - ACV recommends synchronizing transportation projects connecting to Long Thanh airport soon to solve the problem of "one route carries the entire airport".

Urgently complete the completion of the billion-dollar road connecting Long Thanh airport

|

Dong Nai - The T1 and T2 road projects connecting Long Thanh airport are being accelerated, striving to put into operation soon.

The case of a teacher fighting with a principal at a drinking party: With the participation of a prestigious person

|

Lao Cai - Tram Tau Commune Police verified and clarified the incident of a teacher fighting with a principal at a party celebrating Vietnamese Teachers' Day.

Land crack extends over 700m, Lam Dong continues to urgently evacuate 30 households

|

Lam Dong - A complex cracks in the soil stretched for hundreds of meters on a hill in D'ran commune, forcing the locality to urgently evacuate 30 households to ensure safety.

Black smoke column rises in the fire at a plastic factory in Hai Phong City

|

Hai Phong - A plastic factory in Truong Tan commune caught fire fiercely, with high black smoke, the authorities quickly arrived to control the fire.

Will minimize the time to issue construction permits

|

Deputy Minister Bui Xuan Dung said that the maximum time to issue a construction permit will be reduced (the maximum permit issuance period is expected to be 7 - 10 days).

The trade union provides emergency support of more than 1.5 billion VND to help Gia Lai workers recover from storms and floods

|

Gia Lai - The Vietnam General Confederation of Labor and local labor federations supported more than 1.5 billion VND for union members and workers in the province, helping them recover soon after the double natural disaster.

Opening 2 routes passing through 4 communes in Dong Nai connecting Ho Chi Minh City with Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The 25B and 25C road projects will be technically open to traffic at the end of 2025 and the beginning of 2026 to connect Long Thanh airport.

Solving the problem of one route carrying an entire airport in the Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - ACV recommends synchronizing transportation projects connecting to Long Thanh airport soon to solve the problem of "one route carries the entire airport".

Urgently complete the completion of the billion-dollar road connecting Long Thanh airport

Tâm Tú |

Dong Nai - The T1 and T2 road projects connecting Long Thanh airport are being accelerated, striving to put into operation soon.