Untraditional billion-dollar concrete barge house in Gia Lai demolished

Hoài Phương |

Gia Lai - The billion-dollar concrete hairpin project in Ia Gri village was forced to be demolished due to its unconventional design, causing public outrage because of concerns about the waste of the budget.

On October 13, the leader of the Gia Lai Provincial Construction Investment Project Management Board (DTXD) said that the Chu Pah District DTXD Project Management Board - the investor of the Hoan Kiem House Project in Ia Gri village (Bien Ho commune) - has dismantled the construction items according to the province's direction, to hand over the site to serve the Hoa Da Quy - Chu Dang Ya Fire Mountain Week 2025.

Du an Cong trinh Nha rong tai lang Ia Gri. Anh: Hoai Phuong
The Longan House Project in Ia Gri Village. Photo: Hoai Phuong

It is expected that the demolition will be completed on October 20, later than the time limit required by the province, which is before October 15 due to the impact of rain, but still ensuring enough time to prepare for the Week.

Cong trinh nha rong be tong bi pha do. Anh: Hoai Phuong
The concrete barge house project was demolished. Photo: Hoai Phuong

At the scene, the demolition work took place urgently, with the supervision of specialized agencies. Excavators and workers were mobilized, and each brick wall and concrete column was demolished one by one.

Be tong, sat thep
The reinforced concrete blocks are being demolished. Photo: Hoai Phuong
Du kien den ngay 20.10 se pha do xong nha rong be tong. Anh: Hoai Phuong
It is expected that the concrete mound will be demolished by October 20. Photo: Hoai Phuong

The Longan House project in Ia Gri village started construction in April 2025, under the planning of Chu Dang Ya Lake - Fire Mountain National Tourist Area, with a total investment of more than 9.4 billion VND, expected to be completed in November 2025.

May muc
Machinery was mobilized to demolish the project. Photo: Hoai Phuong

However, the project was "whistled" by the province and required to stop implementation due to many shortcomings. The Provincial People's Committee also forced the dismantling of all items before October 15, and transferred capital to other tasks and projects.

s
The demolition progress of the project is beyond the time limit assigned by the province. Photo: Hoai Phuong

The construction of the house is considered a project of profound cultural significance, expressing the unique identity of the J'rai people, and is expected to become a highlight in the space of folk culture, festivals and sustainable tourism development.

However, through on-site inspection, the Provincial People's Committee found that the project implementation still has many shortcomings, especially in the document preparation stage, consulting with professional agencies and local communities.

Gach da, sat thep ngon ngang tai khuon vien du an. Anh: Hoai Phuong
bricks, stone, steel are scattered at the project site. Photo: Hoai Phuong

Notably, the greenhouse project has been concreted, designed in violation of traditional models and arranged items that are not suitable for the J'rai ethnic culture, at risk of breaking the landscape of Chu Dang Ya volcano, seriously affecting the tourism image, not in accordance with the goals of the Mountainous and Ethnic Minority Program, creating bad public opinion.

Hoài Phương
RELATED NEWS

Create an environment and favorable conditions for private economic development

|

At the National Workshop "Promoting the role of the Vietnam Fatherland Front in private economic development" held on the afternoon of October 13, delegates presented their papers and contributed many opinions to the workshop theme.

Temporary suspension of principal in Da Lat to clarify the dirty food problem

|

Lam Dong - Xuan Huong Ward - Da Lat extended the temporary suspension of the Principal of Trung Vuong Primary School to serve the verification of information related to the "dirty food" case.

Building job positions to determine the number of civil servant and public employee positions

|

The Minister of Home Affairs emphasized the need for specific measures to restructure according to job positions and improve the quality of the staff and civil servants.

Bach Mai Hospital, Facility 2, completes construction and installation of 98%

|

Ninh Binh - The construction unit is making efforts, racing against time to complete the Bach Mai Hospital Project, Facility 2 in Ninh Binh.

A woman in Hanoi cried in a level 4 house after a historic flood

|

Hanoi - Historical flooding submerged the belongings of many households in Trung Gia commune, some people cried and watched their damaged assets after many days soaked in floodwaters.

Hundreds of peach trees in Hanoi have died, growers worry about losing Tet

|

Hanoi - After storm No. 11, the rising water of the Red River caused the peach garden in Phu Thuong ward (Hanoi) to be flooded, hundreds of trees died, growers worried about losing Tet.

Tây Gia Lai chờ cú hích từ 4 phường trọng điểm

Hoài Phương |

Gia Lai - 4 phường Pleiku, Diên Hồng, An Phú và Hội Phú giữ vai trò "đầu tàu" phát triển, kỳ vọng tạo cú hích tăng trưởng cho vùng phía Tây tỉnh.

Bắt đối tượng xông vào nhà đuổi chém người ở Gia Lai

Hoài Phương |

Gia Lai - Sau khi phê ma túy, Lợi cầm dao xông vào nhà dân đuổi chém người, khiến nhiều người hoảng sợ bỏ chạy ra đường.

Xuất hiện thủ đoạn mạo danh cán bộ hành chính công để lừa đảo ở Gia Lai

Hoài Phương |

Gia Lai cảnh báo tình trạng mạo danh cán bộ Trung tâm Phục vụ hành chính công cấp xã để lừa đảo, chiếm đoạt thông tin cá nhân của người dân.