Launching the Dong Khe Campaign in 2026, 85 days and nights to complete the expressway

Tân Văn |

Cao Bang - The Provincial People's Committee has just coordinated to organize the launching ceremony of the Dong Khe 2026 campaign to complete phase 1 of the Dong Dang - Tra Linh expressway.

On the morning of February 26, at the construction site of the Dong Dang - Tra Linh expressway, the People's Committees of Cao Bang and Lang Son provinces and the joint venture of investors officially launched the "Dong Khe Campaign 2026", setting a target to complete phase 1 of the project before May 19, 2026, as directed by Prime Minister Pham Minh Chinh.

Previously, at the working session on February 20, leaders of the Ministry of Construction said that throughout the route, contractors mobilized more than 1,300 equipment, 2,800 personnel, and organized 210 simultaneous construction teams.

Giai đoạn 1 dự án cao tốc Đồng Đăng - Trà Lĩnh đã thông tuyến trên 80km. Ảnh: Tân Văn
Phase 1 of the Dong Dang - Tra Linh expressway project has opened more than 80km. Photo: Tan Van

The volume of excavation and embankment reached nearly 40 million m3; 85/93km has been cleared. The output value of phase 1 reached about 65% of the total contract value - a figure showing the determination to accelerate on the large mountainous construction site in the North.

The Dong Dang - Tra Linh expressway is expected to open a strategic connecting axis, shorten travel time, and promote trade in border areas.

In phase 2, Cao Bang province is reviewing the plan to expand 93.35km already built, and at the same time invest in nearly 27.7km connecting to Tra Linh international border gate, striving to complete it in 2027 - about one year earlier than the initial plan.

Concluding the working session, Prime Minister Pham Minh Chinh assessed that the biggest obstacles of the project have basically been removed.

With the spirit of "only discuss doing, not discussing retreating", the head of the Government launched the "Dong Khe Campaign 2026" lasting 85 days and nights, requesting the entire political system to get involved, accelerate progress, and be determined to inaugurate phase 1 on May 19, 2026.

The Prime Minister also requested the Ministry of National Defense to mobilize forces to participate in appropriate tasks, contributing to ensuring the progress and quality of the project.

Giai đoạn 1 tuyến cao tốc Đồng Đăng - Trà Lĩnh được giao hoàn thành dịp 19.5.2026. Ảnh: Tân Văn
Phase 1 of the Dong Dang - Tra Linh expressway is scheduled to be completed on May 19, 2026. Photo: Tan Van

Real-world records at the construction site show that investors and contractors are mobilizing more than 1,300 equipment and more than 2,800 personnel on 211 construction fronts.

The volume of excavation and filling of the project has reached nearly 40 million m3, equivalent to the volume of excavation and filling of the entire Cao Bang province in about 5 years. To date, the output of phase 1 of the project has reached 7,459/11,476 billion VND (equivalent to 65% of the contract value).

To date, phase 1 of the Dong Dang - Tra Linh expressway project has opened 85/93 km.

The official launch of the campaign by the two localities is not only a commitment on time, but also an affirmation of the determination to complete a key infrastructure project, creating motivation for socio-economic development for the Northeast region.

Tân Văn
RELATED NEWS

Launching Tet tree planting, planting 5,000 trees in Vung Tau

|

Ho Chi Minh City - Vung Tau Ward VFF Committee has received more than 5,000 green trees, launching the "Tet tree planting, forever remembering Uncle Ho" campaign.

Minister of Construction becomes Commander of Dong Khe Campaign 2026

|

Minister of Construction Tran Hong Minh is the Commander of the Dong Khe Campaign to complete 2 expressways Huu Nghi - Chi Lang and Dong Dang - Tra Linh.

Dong Khe Campaign 2026 - completing 2 expressways in 85 days and nights

|

Prime Minister Pham Minh Chinh has given new directions for the deployment of the Huu Nghi - Chi Lang, Dong Dang - Tra Linh, Bac Kan - Cao Bang expressways.

It takes more than 30 minutes to get to the end of Lang street during rush hour

|

Hanoi - Rush hour morning of February 26, Lang street was congested for a long time in the area near intersections, vehicles moved slowly.

Loneliness on the sofa", "The day before the storm" and ACB Bank's strategy

|

The songs "Lonely on the Sofa" and "Day Without Storm" are considered communication strategies to help Asia Commercial Bank (ACB) connect closer with customers.

Complete construction of voting feature elsewhere on VneID

|

The Ministry of Public Security has issued guidelines for voters to participate in voting elsewhere electronically and complete the development of voting features elsewhere on VNeID.

Cambodia announces 50% elimination of online scams

|

Cambodia said that the campaign to crack down on online scams has helped reduce activity by half since the beginning of this year.

Gold price today 26/2: Unexpected drop on God of Wealth Day

|

Gold price today 26/2: Plain gold rings and domestic SJC gold bars simultaneously adjusted slightly down.

Launching Tet tree planting, planting 5,000 trees in Vung Tau

Thành An |

Ho Chi Minh City - Vung Tau Ward VFF Committee has received more than 5,000 green trees, launching the "Tet tree planting, forever remembering Uncle Ho" campaign.

Minister of Construction becomes Commander of Dong Khe Campaign 2026

PHẠM ĐÔNG |

Minister of Construction Tran Hong Minh is the Commander of the Dong Khe Campaign to complete 2 expressways Huu Nghi - Chi Lang and Dong Dang - Tra Linh.

Dong Khe Campaign 2026 - completing 2 expressways in 85 days and nights

Tân Văn |

Prime Minister Pham Minh Chinh has given new directions for the deployment of the Huu Nghi - Chi Lang, Dong Dang - Tra Linh, Bac Kan - Cao Bang expressways.